Voltage Park Data Center Capex and Sites

Voltage Park was seeded when Jed McCaleb's nonprofit purchased approximately $500 million of Nvidia H100 GPUs (24,000 units) in October 2023, and later received a $900 million grant from McCaleb. In January 2026 it merged with Lightning AI in a deal valuing the combined company at more than $2.5 billion, with more than $500 million of ARR, 60MW, more than 35,000 Nvidia GPUs and six data centers across four states. It also acquired GPU marketplace TensorDock in April 2025.

Updated October 8, 2026 6 named sites 9 financing transactions 3 sourced facts 18 sources
Voltage Park
NeoCloud and GPU cloud
Financing regimephilanthropic / nonprofit seeding (Navigation Fund, McCaleb grant) plus merger equity
Named sites
6
Site-level commitments the atlas ties to Voltage Park
Disclosed site capital
n.a.
Sum of named sites with a stated dollar figure. Not a capex total; see the spending table
Disclosed capacity
n.a.
Sum of named sites with a stated megawatt figure
Financing transactions
9
Transactions naming Voltage Park or tied to one of its sites
Spending

Reported and guided spending

Audited, reported and guided figures as the filing or release states them. Reported lines are what was spent; guidance is what management said it expects. They are shown side by side and never combined.

PeriodKindAmountAs statedSources
Oct 2023 raise ~$500M
Approximately $500 million of Nvidia H100 GPUs purchased by Jed McCaleb's nonprofit; 24,000 H100s per the Navigation Fund's later description
reported Jan 2026 raise $900M
$900 million grant from McCaleb
Named sites

Where Voltage Park builds

SiteStatePlaceCapitalMWStatusSources
Allen facility
Texas Allen n.a. n.a. operating
Fort Worth facility
Texas Fort Worth n.a. n.a. operating
Puyallup facility
Washington Puyallup n.a. n.a. operating
Quincy facility
Washington Quincy n.a. n.a. operating
Salt Lake City facilities (two)
Utah Salt Lake City n.a. n.a. operating
Sterling facility
Virginia Sterling n.a. n.a. operating
Financing

Financing transactions

Transactions that name Voltage Park as a party or attach to one of its named sites. Amounts are as stated; overlapping commitments are never summed.

PartiesInstrumentAmountDateSiteSources
CleanSpark + Anviran, LLC (Meta subsidiary) + Meta Platforms (guarantor)
CleanSpark signed a 20-year triple-net lease for 175 MW of critical IT load at Sandersville, Georgia, with deliveries expected to begin in Q4 2027. The tenant also executed a letter of intent and exclusivity arrangement covering CleanSpark's Texas portfolio of 718 acres and up to 885 MW. CleanSpark estimated landlord project costs of $10 million to $12 million per MW On 17 September 2026 CleanSpark disclosed the tenant as Anviran, LLC, a wholly owned subsidiary of Meta, with Meta guaranteeing rent and operating expenses. The investor presentation shows development cost of about $11.9 million per IT MW, rent commencing 30 November 2027 and about $330 million of average annual NOI, and CleanSpark proposed a $2.227 billion senior secured notes offering to fund the remaining Sandersville build. The 17 September 2026 investor presentation states a 3.0% annual rent escalator, rent commencement on 30 November 2027 and one 12-month option in addition to the two five-year extensions
lease ≥$6.6B Announced 14 July 2026 CleanSpark Sandersville data center (GA)
Voltage Park + Lightning AI
Merger creating an entity with more than $500 million of ARR, 60MW, more than 35,000 Nvidia GPUs and six data centers across four states.
merger ≥$2.5B January 2026 n.a.
CleanSpark, Inc. + CSDC Finance I, LLC (issuer) + CSRE Properties Sandersville, LLC (guarantor)
CleanSpark subsidiary CSDC Finance I, LLC priced a Rule 144A / Regulation S private offering of $2.276 billion of 7.875% senior secured notes due 2031 at 98.500% of principal on 18 September 2026, up from the $2.227 billion proposed on 17 September 2026. Net proceeds are to finance the remaining build-out cost of the Sandersville Facility, reimburse CleanSpark for prior equity contributions and fund debt service reserves. The notes are guaranteed by CSRE Properties Sandersville, LLC and secured by first-priority liens on substantially all assets of the issuer and guarantor and on the issuer's equity; CleanSpark provides a customary completion guarantee. Closing is expected on 25 September 2026. The facility is leased for 20 years to an unnamed high investment-grade global technology company (lease announced 14 July 2026). The 17 September 2026 investor presentation filed with the proposed-offering 8-K identifies the tenant as Anviran, LLC, a wholly owned subsidiary of Meta, with Meta guaranteeing rent and operating expenses, and shows a development cost of about $11.9 million per IT MW. As of 24 September 2026 no closing 8-K had been filed; closing remained expected on 25 September 2026. CleanSpark's Form 8-K filed 25 September 2026 reports that CSDC Finance I, LLC completed the offering on 25 September 2026: $2,276.0 million of 7.875% Senior Secured Notes due 2031 issued at 98.500% of principal under an indenture dated 25 September 2026 with U.S. Bank Trust Company, National Association as trustee and collateral agent, guaranteed by CSRE Properties Sandersville, LLC. Net proceeds finance the remaining cost of the Sandersville, Georgia data center facility, reimburse CleanSpark for prior equity contributions and fund debt service reserves. CleanSpark provides a customary completion guarantee for the facility.
project bond $2.3B Priced 18 September 2026 (purchase agreement); closed 25 September 2026 (Form 8-K filed 25 September 2026) CleanSpark Sandersville data center (GA)
CleanSpark, Inc. + Cantor Fitzgerald
CleanSpark completed a Rule 144A offering of $1,150,000,000 of 0.00% Convertible Senior Notes due 2032 on 13 November 2025, issued at par for net proceeds of about $1.13 billion. It used about $460.0 million to repurchase shares from note investors and intends to use the remainder to expand its power and land portfolio, develop data center infrastructure, repay bitcoin-backed credit lines and for general corporate purposes.
convertible ~$1.1B Purchase agreement 10 November 2025; completed 13 November 2025 n.a.
Voltage Park + Jed McCaleb
Grant funding cited in the merger reporting.
other $900M reported January 2026 n.a.
Voltage Park + Navigation Fund + Jed McCaleb
The GPU purchase that seeded Voltage Park's fleet.
other ~$500M October 2023 n.a.
TAR (Transformative American Resources) + Spark Capital
Austin-based TAR raised a $120 million Series A at a $1 billion post-money valuation to build off-grid solar and battery power systems for data centers, with gas backup for emergencies, and is executing a utility-scale deployment with one of the largest neoclouds in West Texas
other ~$120M Announced 10 September 2026 n.a.
Rune + Spark Capital + Union Square Ventures + Lowercarbon Capital + Activate Capital + Committed Capital + Timeless Partners + Logos Fund
San Francisco based Rune announced a $40 million Series A led by Spark Capital, with Union Square Ventures, Lowercarbon Capital, Activate Capital, Committed Capital, Timeless Partners and Logos Fund, bringing total funding to $53.5 million, alongside the launch of RELIC, a modular compute system installed behind the meter inside operating solar farms using clipped and curtailed power without a grid connection. pv magazine reports an active RELIC installation inside a 200 MW operating solar farm in Texas; the site and its compute capacity in MW are not disclosed. Proceeds are to secure more solar host agreements and scale the on-site compute footprint.
equity raise $40M Announced 16 September 2026 (Business Wire release); reported by pv magazine USA 24 September 2026 n.a.
Voltage Park + TensorDock
Voltage Park acquired GPU marketplace TensorDock.
acquisition n.a. April 2025 n.a.
The record

Sourced facts on Voltage Park

  • Voltage Park describes 36,000+ H100/B200/GB300 GPUs post-merger, across six data centers in four states with at least one facility in every US time zone.
  • Voltage Park acquired GPU marketplace TensorDock in April 2025.
  • Anchor customer contract values are n.a. in the fetched record.

NeoCloud and GPU cloud: one page each

The figure beside each provider is its count of named sites in the atlas.

Part of the North American Data Center Capital Atlas, refreshed every Tuesday, Thursday and Saturday. Site commitments overlap reported capital expenditure and overlap one another, so this page shows each figure as its source states it and never adds them into a single deployment number. Informational, not investment advice.
The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.