Nebius Group Data Center Capex and Sites
Nebius Group has raised a $700 million strategic equity round, a $3.75 billion equity-plus-converts package, approximately $4.3375 billion and $5.0 billion convertible note offerings, and a $2 billion Nvidia equity investment tied to scaling more than 5GW by 2030. Anchor contracts include a $17.4 billion five-year Microsoft agreement expandable to up to $19.4 billion, anchored at Vineland, New Jersey, and Meta agreements of $3 billion and then $27 billion over five years. Contracted-power guidance has escalated to more than 4GW, with Q1 2026 group revenue of $399.0 million and capex of approximately $2.5 billion.
Reported and guided spending
Audited, reported and guided figures as the filing or release states them. Reported lines are what was spent; guidance is what management said it expects. They are shown side by side and never combined.
| Period | Kind | Amount | As stated | Sources |
|---|---|---|---|---|
| Q1 2026 | reported | ~$2.5B | Q1 2026 capex approximately $2.5 billion; $6.3 billion of capital secured in the quarter, $2.3 billion positive operating cash flow, $9.3 billion ending cash |
|
| Q3 2025 | reported | $956M | Q3 2025 capex of $955.5 million against revenue of $146.1 million |
|
| FY2026 guidance | guidance | ≥$3.2B | 2026 revenue guidance of $3.0B-$3.4B (midpoint recorded) and $7B-$9B ARR; contracted-power guidance escalated from >1GW (Aug 2025) to >2.5GW, >3GW and currently >4GW |
Where Nebius Group builds
| Site | State | Place | Capital | MW | Status | Sources |
|---|---|---|---|---|---|---|
Highridge Business Park AI factory with PPL Electric Utilities |
Pennsylvania | Butler Township, Schuylkill County | n.a. | 1,200 | announced | |
Vineland build-to-suit facility with Microsoft |
New Jersey | Vineland | n.a. | 300 | announced | |
Independence AI factory campus Groundbreaking 12 May 2026 |
Missouri | Independence, Jackson County | n.a. | n.a. | construction | |
Kansas City colocation |
Missouri | Kansas City | n.a. | n.a. | announced |
Financing transactions
Transactions that name Nebius Group as a party or attach to one of its named sites. Amounts are as stated; overlapping commitments are never summed.
| Parties | Instrument | Amount | Date | Site | Sources |
|---|---|---|---|---|---|
Nebius Group + Meta Second, far larger Meta agreement following the initial $3 billion deal. |
other | $27.0B | compute purchase beginning early 2027 | n.a. | |
Nebius Group + Microsoft AI infrastructure agreement anchored at the Vineland, New Jersey facility, with more than 100,000 GB300 units planned. |
other | $17.4B | September 2025 | Vineland build-to-suit facility (NJ) | |
Nebius Group Upsized private offering of convertible senior notes. Closed 24 August 2026 with aggregate principal of $5.75 billion after initial purchasers exercised options: $3.45 billion of 0.50% notes due 2030 and $2.3 billion of 4.50% notes due 2034. Holders exchanged $400 million of 2029 notes and $400 million of 2031 notes for approximately 15.8 million Class A shares |
convertible | ~$5.8B | Priced 19 August 2026; closed 24 August 2026 | n.a. | |
Nebius Group Private offering of convertible senior notes with aggregate gross proceeds of approximately $4.3 billion. |
convertible | ~$4.3B | closed March 20, 2026 | n.a. | |
Nebius Group Combined stock offering and convertible notes raise. |
convertible | $3.8B | September 2025 | n.a. | |
Nebius Group + Meta Initial Meta compute agreement, signed as Nebius described current available capacity as sold out. |
other | $3.0B | n.a. (reported alongside sold-out capacity commentary) | n.a. | |
Nvidia + Nebius + Nebius Group Nvidia committed $2 billion of equity to Nebius on March 11, 2026, under a partnership to scale more than 5GW by 2030, having also participated in Nebius's December 2024 round. |
equity raise | $2.0B | March 11, 2026; plus Dec 2024 round participation | n.a. | |
Industrial Development Funding + Oaktree + Bloom Energy + Nebius Group Industrial Development Funding and Oaktree agreed to invest $1.7 billion to deploy Bloom Energy fuel cells supplying dedicated behind-the-meter power to Nebius AI cloud infrastructure. The specific Nebius sites were not named in the fetched coverage. Nebius later adopted Bloom fuel cells in the approved plan for its Vineland, New Jersey campus |
project equity investment in behind-the-meter power | $1.7B | Announced 16 July 2026 | n.a. | |
AIB Data Centers Inc. (AIB CLT1 LLC) + Nebius AIB Data Centers signed a binding agreement with Nebius for 50 MW of critical IT capacity at its facility in the southeastern United States, delivered in two data halls and supported by AIB's 15-year Electric Service Agreement for 65 MW of utility load at the site. AIB's Form 10-Q identifies the 65,000 kVA agreement with its CLT-01 Campus in Spartanburg County, South Carolina, a former 40 MW bitcoin hosting facility being repurposed to about 65 MW. The release does not name the town. AIB's investor presentation says Nebius's guaranty backs the contract, rent commences hall by hall (two 25 MW halls targeted at about months 10 and 14), and the 12-year term runs from the first hall. |
lease | ≥$1.3B | Announced 30 September 2026 (AIB release via GlobeNewswire); contract value from AIB investor presentation furnished on Form 8-K 30 September 2026; ESA service scheduled to begin 1 October 2026 | AIB Data Centers CLT-01 Campus (SC) | |
Nebius Group + Reflection AI startup Reflection signed a deal worth more than $1 billion to secure computing capacity from Nebius, including access to Nvidia's latest chips. The agreement builds on Reflection's June 2026 compute agreement with SpaceX. Contract term and data center locations were not disclosed |
compute capacity agreement | ≥$1.0B | Announced 14 July 2026 | n.a. | |
Nvidia + CoreWeave + Nebius + Nscale + Lambda + Crusoe Nvidia backstops $860M of partner data center lease obligations, with $470M escrowed, across CoreWeave, Nebius, Nscale, Lambda and Crusoe. |
guarantee | $860M | Date n.a. in this part | n.a. | |
Nebius Group + MUFG + ABN AMRO + Bank of America + Deutsche Bank + HSBC Nebius raised its first secured debt, backed by deployed GPU infrastructure and contracted cash flows from an agreement with an investment-grade customer. MUFG was structuring agent and sole bookrunner; Citi, Credit Agricole CIB, ING and Morgan Stanley were senior lead arrangers, with Goldman Sachs also participating |
debt facility | $775M | Announced 17 July 2026 | n.a. | |
Nebius Group + Nvidia + Accel Strategic equity financing to accelerate roll-out of full-stack AI infrastructure. |
equity raise | $700M | December 2, 2024 | n.a. |
Sourced facts on Nebius Group
- Q1 2026 group revenue reached $399.0 million (from $50.9 million a year earlier), with AI-cloud revenue of $389.7 million and group adjusted EBITDA of $129.5 million.
- Nebius plans to deploy more than 100,000 GB300 units for the Microsoft agreement, and described available capacity as sold out while targeting 2.5GW contracted and 800MW-1GW connected by end-2026.
Sources for Nebius Group
Every source cited on this page, once each. The full atlas source register is at Capital Atlas sources.
- nebius.comNebius
- yahoo.comRepublican Herald via Yahoo News
- nebius.comNebius
- reuters.comReuters
- yahoo.comNJ.com via Yahoo News
- nbcphiladelphia.comNBC10 Philadelphia
- finance.yahoo.comYahoo Finance
- 247wallst.com24/7 Wall St.
- techtimes.comTech Times
- nebius.comNebius
- assets.nebius.comQ1 2026 shareholder letter
- datacenterdynamics.comDCD
- nebius.comNebius
- sec.govSEC EDGAR (Nebius 6-K)
- nebius.comNebius
- datacenterdynamics.comDCD
- nebius.comNebius
- finance.yahoo.comReuters via Yahoo Finance
- finance.yahoo.comAIB Data Centers release (GlobeNewswire via Yahoo Finance)
- sec.govAIB Data Centers Form 10-Q for quarter ended 30 June 2026 (SEC)
- sec.govAIB Data Centers Form 8-K Exhibit 99.1, investor presentation Q3 2026 (SEC)
- thestar.com.myThe Star (Reuters)
- datacenterdynamics.comDCD
- nebius.comNebius
- nebius.comNebius
NeoCloud and GPU cloud: one page each
The figure beside each provider is its count of named sites in the atlas.
Seven references, one system
Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.