SAVRN Research · Living watchlist

Nationwide Data Center Delay Watchlist

A continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, local restrictions, litigation, federal and utility dockets, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Every entry links to its documented public source.

Updated 2026-09-28 Live · sources checked 53 min ago · 16 of 18 sources answered · 52 entries added in the last 7 days · last change 2026-10-03 Version 2.0.0 Coverage from 2024-01-01 Compiled by SAVRN Research
Scale model of a data center campus on a white plan: completed halls, cooling plant, and electrical substation rendered in copper, with queued future phases drawn as blueprint outline and a construction crane standing still
A data center campus rendered as a plan: completed structures shown built, queued phases shown as outline. The watchlist records which projects have moved and which are on hold.
Tracked projects
344
delayed, cancelled, or under review
Local restrictions
1150
county, city, township measures
Utility actions
272
PUC dockets and statements
Active lawsuits
63
filed or in progress
Stalled since Jan 2024
$170B+
across 20 states (Carbon Direct)
Q1 2026 delayed / cancelled
$130B
75 projects (Fortune)
ERCOT capacity at risk
49.8 GW
$8B–$15B revenue (BNEF)
Transformer lead time
128 wks
large power, average

National interconnection queue

Every ISO plus vertically integrated utilities with a public row-level queue, as of 2026-09-28. The full row-level queue is refreshed weekly. ERCOT Batch Zero row-level classifications are not yet published per Market Notice M-A080326-01.

32,382
Total queue rows
4,445 GW
Total capacity requested
46
Rows flagged data center
92
Large-load / DC studies
By status
Withdrawn15,338
IA signed8,099
Active4,163
Unknown2,003
Other1,978
Study706
Suspended95
By source, ISO and utility
PJM9,263
Alliant Energy6,968
MISO3,873
CAISO2,281
Dominion Energy VA2,178
NYISO2,148
ERCOT2,003
ISO-NE1,751
SPP1,028
Ameren Illinois146
AEP Indiana Michigan91
Consumers Energy88
Evergy Kansas88
AEP PSO80
AEP Ohio72
We Energies58
PacifiCorp56
AEP SWEPCO47
Evergy Missouri40
El Paso Electric39
AEP APCo34
MidAmerican Energy32
Ameren Missouri18

Would you like the weekly update?

Every week we re-verify every project on this watchlist and publish what moved. You get one email when it goes out.

Also send me

Receive a short introduction on days 3, 7 and 14, plus the updates you select. Unsubscribe in one click. Privacy ·

You're on the list. The next weekly update will land in your inbox when it publishes.
You are subscribed. Read the latest tracker

Browse a section below. Download the full dataset (JSON) or review all sources and citations.

Public companies

Publicly traded issuers with material exposure to tracked projects or jurisdictions, with links to SEC EDGAR and the most recent disclosure on record.

TickerCompanyExposureEDGARMost recent disclosure
DLR Digital Realty Trust Multi-tenant Texas exposure via Dallas metro; commented favorably on Abbott initiative Aug 7, 2026 Filings ↗ 2026-08-07 · press: Digital Realty Welcomes Abbott Initiative
3 on record
APLD Applied Digital Texas-heavy HPC portfolio Filings ↗ 2026-07-29 · 10-K: Applied Digital fiscal 2026 annual report covering AI data center buildout and risk…
4 on record
IREN Iris Energy (IREN) Childress, TX facility Filings ↗ 2026-08-13 · 8-K: IREN delivers Horizon 1 50MW AI data center to Microsoft at Childress Texas
3 on record
RIOT Riot Platforms Rockdale + Corsicana + Navarro, TX Filings ↗ 2026-08-10 · 8-K: $9.1B AI lease at Rockdale + Q2 2026 results
5 on record
MARA Marathon Digital Texas presence via various JVs Filings ↗ 2026-08-06 · 10-Q: MARA second quarter 2026 report disclosing ERCOT Batch Zero and August 3 2026 Texas…
3 on record
CLSK CleanSpark Texas operations, filed explicit moratorium disclosure Filings ↗ 2026-08-06 · 10-Q: CleanSpark third quarter fiscal 2026 report disclosing August 3 2026 Abbott directive…
3 on record
BTDR Bitdeer Texas mining-to-HPC transition Filings ↗ 2026-08-10 · 6-K: Bitdeer reports unaudited second quarter 2026 results with AI cloud and HPC leasing update
3 on record
CORZ Core Scientific TX HPC exposure; recent AMD AI datacenter pact Filings ↗ 2026-08-14 · 8-K: Core Scientific reports update on merger with CoreWeave
4 on record
BE Bloom Energy On-site power partner Filings ↗ 2026-07-28 · 10-Q: Bloom Energy Q2 2026 Form 10-Q, quarterly report with data center fuel cell agreements
3 on record
AMZN Amazon (AWS) Texas 7.65 GW gas plant + Hobart lawsuit + Tucson cancellation Filings ↗ 2026-08-07 · news: Amazon confirmed as backer of 7.65 GW private gas power plant for Texas data centers
4 on record
MSFT Microsoft Stargate/Abilene + Wisconsin cancellations Filings ↗ 2026-07-29 · 10-K: Microsoft fiscal 2026 Form 10-K, annual report with cloud and AI infrastructure spending
3 on record
GOOGL Alphabet/Google Armstrong TX (BTM) + Pine Island MN (litigation) + Indiana cancellation Filings ↗ 2026-07-23 · 10-Q: Alphabet Q2 2026 Form 10-Q, quarterly report with technical infrastructure investment
4 on record
META Meta Platforms TX facility reported near Austin (unverified) Filings ↗ 2026-08-10 · news: Abbott data center agreement with Meta appears to have no impact on Northeast El Paso…
3 on record
ORCL Oracle Abandoned TX site March 2026; Wisconsin lawsuit; Shackelford Cty delay Filings ↗ 2026-08-17 · news: Oracle drops lawsuit challenging Wisconsin data center credit rules
3 on record
NVDA NVIDIA OpenAI datacenter lease disclosure (10-Q Aug 17) Filings ↗ 2026-08-17 · news: OpenAI to lease Ohio data center backed by NVIDIA guarantee
3 on record
No matches.

Methodology and scope

This watchlist tracks U.S. data center projects, operators, and jurisdictional actions that carry a documented public paper trail: securities filings, regulatory dockets, litigation, government statements, utility filings, and trade press. It is maintained as a neutral reference. Entries are recorded as observed; the tracker does not rank projects or advocate an outcome.

  • Status reflects the most recent public signal for each entry. Where a project continues on schedule, that is recorded as plainly as a delay.
  • Capacity is shown in megawatts where reported, and left blank where not disclosed.
  • Local restrictions, utility dockets, lawsuits, and federal actions are drawn from primary filings and reputable outlets, each linked to its source.
  • The ERCOT queue snapshot is extracted directly from the ERCOT GIS Report.
  • Signals are collected on a recurring basis and reconciled into a single source of truth before publication.

Every citation on one page: Sources and citations. Companion policy map: SAVRN Data Center Moratorium Tracker. Capital side: North American Data Center Capital Atlas. Founder essay: The Queue Was the Fiction.

The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.
Check this address →
What is the Nationwide Data Center Delay Watchlist?

It is a continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Each entry links to its documented public source, and it is maintained as a neutral reference.

How is a project's status determined?

Status reflects the most recent public signal for each entry: halted, delayed, cancelled, pending review, litigation active, audit paused, under appeal, or withdrawn. Where a project continues on schedule, that is recorded as plainly as a delay.

How are delay days measured?

Delay days are measured against the original announced target where available, or against the first documented delay date.

How often is the watchlist updated?

Signals are collected on a recurring basis from SEC EDGAR and trade-press feeds and reconciled into the single source of truth before publication.

How is this different from the Data Center Moratorium Tracker?

The Moratorium Tracker maps state and local policy measures. This watchlist tracks named projects, operators, public-company exposure, and securities filings, with delay status and cause for each. The two are companion references.

Nationwide Data Center Delay Watchlist

Get these tracker updates by email

A short introduction on days 3, 7 and 14, plus updates for this tracker. Unsubscribe at any time.

We use your address to send the introduction and updates described above. See our Privacy Policy.

You’re on the list. Your subscription is saved.