SAVRN Research · Living watchlist

Nationwide Data Center Delay Watchlist

A continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, local restrictions, litigation, federal and utility dockets, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Every entry links to its documented public source.

Updated 2026-09-28 Live · sources checked 53 min ago · 16 of 18 sources answered · 52 entries added in the last 7 days · last change 2026-10-03 Version 2.0.0 Coverage from 2024-01-01 Compiled by SAVRN Research
Scale model of a data center campus on a white plan: completed halls, cooling plant, and electrical substation rendered in copper, with queued future phases drawn as blueprint outline and a construction crane standing still
A data center campus rendered as a plan: completed structures shown built, queued phases shown as outline. The watchlist records which projects have moved and which are on hold.
Tracked projects
344
delayed, cancelled, or under review
Local restrictions
1150
county, city, township measures
Utility actions
272
PUC dockets and statements
Active lawsuits
63
filed or in progress
Stalled since Jan 2024
$170B+
across 20 states (Carbon Direct)
Q1 2026 delayed / cancelled
$130B
75 projects (Fortune)
ERCOT capacity at risk
49.8 GW
$8B–$15B revenue (BNEF)
Transformer lead time
128 wks
large power, average

National interconnection queue

Every ISO plus vertically integrated utilities with a public row-level queue, as of 2026-09-28. The full row-level queue is refreshed weekly. ERCOT Batch Zero row-level classifications are not yet published per Market Notice M-A080326-01.

32,382
Total queue rows
4,445 GW
Total capacity requested
46
Rows flagged data center
92
Large-load / DC studies
By status
Withdrawn15,338
IA signed8,099
Active4,163
Unknown2,003
Other1,978
Study706
Suspended95
By source, ISO and utility
PJM9,263
Alliant Energy6,968
MISO3,873
CAISO2,281
Dominion Energy VA2,178
NYISO2,148
ERCOT2,003
ISO-NE1,751
SPP1,028
Ameren Illinois146
AEP Indiana Michigan91
Consumers Energy88
Evergy Kansas88
AEP PSO80
AEP Ohio72
We Energies58
PacifiCorp56
AEP SWEPCO47
Evergy Missouri40
El Paso Electric39
AEP APCo34
MidAmerican Energy32
Ameren Missouri18

Would you like the weekly update?

Every week we re-verify every project on this watchlist and publish what moved. You get one email when it goes out.

Also send me

Receive a short introduction on days 3, 7 and 14, plus the updates you select. Unsubscribe in one click. Privacy ·

You're on the list. The next weekly update will land in your inbox when it publishes.
You are subscribed. Read the latest tracker

Browse a section below. Download the full dataset (JSON) or review all sources and citations.

Lawsuits

Filed or active litigation over data center projects, moratoriums, permits, and environmental review.

PartiesCourtCauseFiledStatusSources
DC BLOX
v. Metro Nashville (Metropolitan Government of Nashville and Davidson County)
DC BLOX alleges Nashville officials obstructed its proposed data center near Nashville Zoo by enacting a moratorium, pausing permit processing, and…
U.S. District Court for the Middle District of Tennessee zoning 2026-08-11 active
Sierra Club Wisconsin (represented by Midwest Environmental Advocates)
v. Wisconsin Department of Natural Resources (DNR)
Challenges DNR's decision to issue permits for Vantage Data Centers' $15B Port Washington campus without a full Environmental Impact Statement…
Ozaukee County Circuit Court, Wisconsin environmental 2026-07-10 active
Eagan Capital
v. City of Eagan, Minnesota
Challenges city's data center moratorium, alleging the city overstepped its authority by effectively regulating electricity consumption via…
Minnesota state court (venue not specified in coverage) zoning 2026-07-06 active
Preservation of Community Well-being Collective (residents of Saddlebrook Farms, Grayslake, Mundelein, Round Lake Park)
v. Village of Grayslake; T5 Data Centers; Alter Asset Management Company
Alleges the village obfuscated the nature of the 472-acre T5@Chicago development during approvals and proceeded without proper notice/public input.…
Illinois state court, Lake County (venue not explicitly confirmed in coverage) zoning 2026-08-06 active
Hexa Builders LLC; 3043 Williamstown Urban Renewal LLC
v. Mayor and Township Council of Monroe (Gloucester County, NJ); Planning Board of Monroe Township; township officials
Challenges Monroe Township's redevelopment-plan amendment and township-wide data center ban as arbitrary/capricious and violating equal protection,…
Superior Court of New Jersey, Gloucester County, Law Division
GLO-L-805-26
civil rights 2026-06-09 active
Imperial Valley Computer Manufacturing LLC (IVCM)
v. City of Imperial, CA; City Council member Katherine Burnworth; City Manager Dennis Morita; City Attorney Kathrine Turner; Planning Director Othon Mora
Civil-rights suit alleging coordinated administrative obstruction and retaliation to derail a permitted $10B AI data center; claims include failure…
U.S. District Court, Southern District of California
3:26-cv-00128
civil rights 2026-01-12 active
Imperial Valley Computer Manufacturing LLC (IVCM) / related developer
v. Imperial Irrigation District and associated water authorities
Developer sues seeking access to Colorado River water allocations for the Imperial Valley AI data center project amid broader water-rights disputes…
California / federal court (venue as reported) environmental 2026-06-15 active
Sierra Club (San Diego and Imperial Counties chapter); City of Imperial
v. Imperial County, California (real party: Imperial Valley Computer Manufacturing, developer Sebastian Rucci)
On September 9, 2026 Judge Anderholt issued a final decision, following an August tentative ruling, setting aside the county's April 2026 lot merger…
Imperial County Superior Court, California (Judge L. Brooks Anderholt) environmental 2026-05-27 litigation active
Lowell residents (including Alex Solange, Mary Wambui and others)
v. Markley Group; Massachusetts Department of Environmental Protection (permit referenced)
Massachusetts' first lawsuit against a data center; challenges MassDEP's permit for 8 additional diesel generators at Markley's Lowell facility,…
Massachusetts state court (Superior Court, Middlesex County presumed) environmental 2026-05-07 active
Lowell residents (class action)
v. Markley Group
Class-action nuisance/environmental suit filed against Markley Lowell data center over noise and generator pollution, separate from the MassDEP…
Massachusetts state court environmental 2026-07-19 active
Minnesota Center for Environmental Advocacy (MCEA)
v. City of Pine Island, Minnesota; Ryan Companies US, Inc.
Alleges the city's Alternative Urban Areawide Review (AUAR) for the Google-linked Project Skyway data center violated the Minnesota Environmental…
District Court of Goodhue County, Minnesota, First Judicial District
25-CV-25-2298
environmental 2025-10-16 TRO granted
Hobart, Indiana residents (incl. Soriano, Venegas/Koteles, Joseph Conn per garbled court coverage)
v. Hobart city officials; Hobart City Council; Hobart Commission; landowner/Amazon Data Services (referenced)
Sought to block a fill permit and earthmoving for a proposed 168-acre Amazon data center site, alleging local-regulation and due-process violations.…
Lake Superior Court, Indiana zoning 2025-12-10 dismissed
Coalition to Protect Prince William County / American Battlefield Trust-aligned groups
v. Prince William County Board of Supervisors (and, in a companion posture, the County itself co-litigated against the developer)
Challenged the county's rezoning approval for the ~2,100-acre Prince William Digital Gateway data center corridor near Manassas Battlefield.…
Virginia Circuit Court, Prince William County (with appeal to Court of Appeals of Virginia) zoning 2024-01-12 dismissed
Bristow-area residents
v. Prince William County / Devlin Technology Park developer
Residents sued to block the Devlin Technology Park data center project approval near Bristow, VA.
Virginia Circuit Court, Prince William County zoning 2024-01-01 active
Citizens for Fauquier County
v. Town of Warrenton, VA; Amazon Data Services
Challenges Warrenton's approval of an Amazon data center, alleging improper zoning board process. Court of Appeals of Virginia sided with the…
Virginia Circuit Court (Fauquier), with appeal to Court of Appeals of Virginia zoning 2023-12-13 active
Louisa County, VA homeowner
v. Amazon Data Services
Homeowner alleges brown well water, dust, and constant loud noise caused by nearby Amazon data center construction.
Virginia Circuit Court, Louisa County environmental 2026-07-28 active
American Battlefield Trust / Manassas Battlefield preservation coalition
v. Prince William County, VA (rezoning approvals)
Virginia Court of Appeals blocked approvals covering roughly 37 data centers near Manassas Battlefield, a decision closely tied to the broader…
Court of Appeals of Virginia zoning 2026-04-07 preliminary injunction
Chesterfield County, VA residents/opposition group
v. Chesterfield County Board of Supervisors
Lawsuit opposing a data center project (linked to Meta-area development) alleges numerous Virginia Freedom of Information Act (Sunshine Law)…
Virginia Circuit Court, Chesterfield County civil rights 2026-04-01 active
Coweta County, Georgia residents
v. Project Sail data center developer / Coweta County
Residents sue to block the Project Sail data center development in Coweta County, GA.
Georgia state court (Coweta County) zoning 2026-05-11 active
Community groups (Stokes County, NC)
v. Stokes County / data center developer
Community groups sue over a planned data center in Stokes County, North Carolina.
North Carolina state court zoning 2026-03-13 active
Joliet, IL residents/opposition group
v. City of Joliet, Illinois
Lawsuit challenges the zoning and approval process for a proposed Joliet, IL data center.
Illinois state court (Will County) zoning 2026-05-26 active
Fort Meade, FL residents
v. City of Fort Meade, Florida
Residents sue the city to block a hyperscale data center land deal, alleging governance/procedural improprieties.
Florida state court (Polk County) civil rights 2026-06-23 active
Franklin Coalition
v. Data center developers (Franklin/Simpson County, KY area)
Franklin Coalition sues data center developers challenging the local approval process.
Kentucky state court zoning 2026-04-15 active
Michigan residents (Dowagiac-area data center neighbors)
v. Data center operator (unnamed in initial coverage)
Residents sue over constant 24/7 noise emitted by a data center, citing health concerns; a related class action was filed in Dowagiac, MI.
Michigan state court environmental 2026-05-29 active
Wisconsin residents
v. Microsoft Corporation
Residents sue Microsoft over noise caused by a new data center; a related public-records suit sought disclosure of projected water use by…
Wisconsin state court environmental 2026-03-01 active
Southaven, MS-area residents (class action)
v. xAI; SpaceX
Class action alleges data center 'nuisance' (noise/pollution) from co-located xAI/SpaceX facility in Southaven, Mississippi.
Federal court (N.D. Mississippi, per Reuters coverage) environmental 2026-06-09 active
NAACP (Memphis chapter / national)
v. xAI (Colossus / Colossus 2 gas turbines, Memphis, TN)
NAACP sued over unpermitted gas turbines at xAI's Memphis Colossus data center under the Clean Air Act. The Trump administration/DOJ moved June 2026…
Federal court (W.D. Tennessee, per reporting) environmental 2025-06-01 active
Sierra Club Wisconsin Chapter; Clean Wisconsin; Port Washington residents
v. Wisconsin DNR (air permit for Vantage Data Centers)
Environmental groups formally challenge/comment against air quality permits for the Port Washington data center, separate from the broader EIS…
Wisconsin DNR administrative process / Ozaukee County Circuit Court environmental 2026-06-01 active
Environmental groups (Georgia)
v. Georgia Environmental Protection Division / Plant Bowen gas turbine operators (data center-linked power)
Environmental groups challenge the air permit for gas turbines at Plant Bowen tied to Georgia data center power buildout; separate reporting covers…
Georgia state administrative/court proceeding environmental 2026-03-02 active
Rise St. James; allied environmental groups
v. Louisiana Department of Environmental Quality; Meta (Hyperion data center-linked gas power)
Challenge to air pollution permitting tied to Meta's Hyperion data center gas-power buildout in Louisiana; judge dismissed the challenge to Meta's…
Louisiana state court / administrative appeal environmental 2026-02-01 dismissed
Earthjustice and allied groups
v. Formosa Plastics; Louisiana Department of Environmental Quality
Groups sue over Formosa Plastics' permit extensions in Louisiana's industrial corridor, part of the broader wave of air-permit litigation tied to…
Louisiana state/administrative appeal environmental 2026-01-15 active
Data center opposition group
v. Missouri city government; proposed data center developer
Opposition group sues a Missouri city and the proposed data center developer over project approval.
Missouri state court zoning 2026-04-20 active
New Jersey neighbors (unspecified township)
v. Data center operator (unnamed)
Neighbors sue over persistent humming noise emitted by a nearby New Jersey data center.
New Jersey state court environmental 2026-04-01 active
Environmental/community groups (North Carolina)
v. Amazon; Duke Energy
Amazon-Duke Energy diesel backup power plans for an NC data center face legal pushback from environmental and community advocates over permitting.
North Carolina state administrative/court proceeding environmental 2026-08-01 active
Federal Energy Regulatory Commission (Commission-initiated)
v. PJM Interconnection; MISO; SPP; CAISO; ISO-NE; NYISO (and associated transmission owners)
FERC issued Section 206 show-cause orders directing all six RTOs/ISOs to justify or reform large-load/co-location interconnection rules for data…
Federal Energy Regulatory Commission (administrative proceeding, not a court)
RM26-4-000
regulatory 2026-06-18 show cause
Eco TIP West (Triangle Innovation Park West)
v. Chatham County, North Carolina
Sanford-based Eco TIP West sued in April 2026 after the Board of Commissioners adopted a 12-month moratorium on data centers in February 2026.…
North Carolina Superior Court, Chatham County zoning 2026-04 litigation active
Data center developer
v. Hill County, Texas
Developer filed a $100M lawsuit against Hill County, Texas after the county rescinded prior data center approvals/incentives amid moratorium activity.
Texas state court contract 2026-06-01 active
Citizens for Fauquier County
v. Warrenton, VA Board of Zoning Appeals
CFFC's zoning board appeal on the Amazon data center was rejected, which the group alleged occurred illegally, leading to further litigation (see…
Virginia Circuit Court, Fauquier County zoning 2023-08-01 dismissed
Loudoun County, VA homeowners
v. Dominion Energy; Virginia State Corporation Commission (as regulator)
Homeowners challenged Dominion Energy's data-center-driven transmission line siting; reporting indicates homeowners appear to have lost before the…
Virginia State Corporation Commission / Virginia courts zoning 2026-07-01 dismissed
Dr. Michelle Finch-Mincey, Lehman Mincey Jr. and Raymond Carver
v. Effingham County, Georgia
Three residents challenge Ordinance 2026-352, which county commissioners gave final approval on August 4, 2026 and which cleared the way for Project…
Superior Court of Effingham County, Georgia zoning 2026-09-02 litigation active
City of Edgerton, Kansas
v. Kimberly Twente, Carrie Schmidt, Public Trust Collective Inc.
The city sued residents who circulated a citizen-initiated petition (about 208 signatures) for an ordinance to block the DAMAC Digital data center…
Johnson County District Court, Kansas ballot initiative 2026-08 dismissed
National CRE Holdings LLC; Greenland Capital LLC
v. Hood County, Texas
The developers argued that two proposed data center campuses, Project Red and Project Yellow, were automatically approved because the county did not…
355th Judicial District Court, Hood County, Texas (appeal to the Second Court of Appeals) zoning under appeal
Trenton, Ohio residents (relators led by Blankenship)
v. Trenton City Council (Butler County, Ohio); intervenor Trenton Data Center Campus
Five residents filed a July 2026 petition to amend the Trenton city charter to prohibit construction of data centers; the board of elections…
Supreme Court of Ohio
Case No. 2026-1035; State ex rel. Blankenship v. Trenton City Council, Slip Opinion No. 2026-Ohio-3406
ballot initiative 2026-08 decided
Jazmin Villegas and a second Red Oak resident (both live within 200 feet of the rezoned land)
v. City of Red Oak, Texas; its mayor and five City Council members
Two residents sued the city, its mayor and five council members during the first week of September 2026 over the City Council's May 2026 rezoning of…
Texas state court, Ellis County zoning 2026-09 litigation active
David Lambiaso (partner, TerraWatt)
v. City of St. Louis; St. Louis Board of Adjustment
The developer of a planned 120 MW, $3.1 billion data center in the former Famous-Barr warehouse on Market Street in Midtown St. Louis, next to the…
Missouri state court, City of St. Louis (court not named in coverage) zoning 2026-09-16 litigation active
NSI A.1 LLC (affiliated with developer Trent Overhue)
v. City of Springfield, Missouri
The suit challenges Springfield's 120-day moratorium on accepting and processing data center applications, passed by City Council as a special…
Greene County Circuit Court, Missouri (Judge Nathan Taylor) zoning 2026-09-17 litigation active
Perry Township, Stark County, Ohio residents
v. Perry Township Board of Trustees; Panattoni Development Company; other local public bodies
Residents sued over approvals tied to Panattoni's 100-acre, 240 MW data center in Perry Township, which broke ground earlier in 2026 and is…
Ohio state court, Stark County (court not named in coverage) open meetings 2026-09-01 litigation active
Brian O'Neill (MLP Ventures)
v. Upper Merion Township Board of Supervisors, Montgomery County, Pennsylvania
Land use appeals from the supervisors' unanimous August 13, 2026 denial of five land development plans totaling about 4.6 million square feet for a…
Montgomery County Court of Common Pleas, Pennsylvania zoning 2026-09-16 litigation active
Preserve Montgomery County, LLC (Montgomery County residents and property owners)
v. Montgomery County, Missouri; Missouri Department of Economic Development (dismissed September 2026)
The group alleges the county violated the Missouri Sunshine Law in approving data center projects, including failure to properly post public notice…
Cole County Circuit Court, Missouri (Judge Cotton Walker) open meetings 2026-02 litigation active
Great Lakes Neighbors, Inc.
v. City of Port Washington Joint Review Board; City of Port Washington; Vantage Data Centers (added March 2026)
The suit sought to void Tax Incremental District No. 5, the roughly $458 million TIF district the city approved in November 2025 for Vantage Data…
Ozaukee County Circuit Court, Wisconsin (Judge Adam Gerol) tax incentive 2026-01-02 dismissed
Beverly and Phillip J. Morris; Lindsay and Christopher Wilson; Jonathan and Holly Zeigler; Adam Clack and Alexis Spain (Morgan County, Georgia residents)
v. Meta; Joint Development Authority of Jasper, Morgan, Newton and Walton Counties; Holder Construction Company; Plateau Excavation Inc.
Eight residents who rely on private wells allege that tree clearing, blasting and excavation for Meta's two data center campuses at Stanton Springs…
Georgia state court (court not confirmed in coverage read) nuisance 2026-08 litigation active
Spartanburg County residents represented by the Southern Environmental Law Center
v. Spartanburg County, South Carolina; Valara Holdings (NorthMark Strategies subsidiary)
The suit alleges the county violated its land management ordinance by processing the roughly $2.8 billion to $3 billion Valara data center and…
South Carolina state court, Spartanburg County (court not named in coverage) zoning 2026-07-06 litigation active
Landowners Miles Crosby and Jennifer Singleton
v. Colleton County
Landowners Miles Crosby and Jennifer Singleton sued Colleton County, South Carolina, challenging a new zoning ordinance allowing 'special exception'…
community impact, environmental, tax incentive, zoning 2026-02-05 active
The City of Imperial
v. Imperial County
Multiple lawsuits surround data center development in Imperial Valley. The City of Imperial sued Imperial County in December 2025 to force…
environmental, water 2025-01-28 active
Developer behind proposed data center on South National
v. city
The developer filed a lawsuit against the city regarding a moratorium affecting a proposed data center project.
moratorium 2026-09-18 active
Microsoft
v. Virginia State Corporation Commission
Microsoft is preserving its right to appeal a Virginia utility commission decision on transmission cost assignment. The company has until November…
Challenging the direct assignment of transmission costs for data center transmission 2026-09-18 active
Kanter
v. O'Leary
The document references an exhibit related to the opening of an AI data center in Utah and mentions protesters.
2:26-cv-00664-TC-CMR
2026-09-21 active
Anand
v. U.S. Department of Health and Human Services
This document references a 2023 decision by the D.C. Circuit Court of Appeals citing Mead Data Center, Inc. v. Department of the Air Force.
4th Circuit (D.C. Cir.)
4th 1061
2026-09-15 ruling
Stealth Consulting Management, Inc. and Fintree Holding Group
v. Viking Data Centers LLC, Wen Xiao Li, Soffia Wathne, Anna Bergljot
This is a civil case filed in the United States District Court for the Southern District of New York. The case was filed on September 21, 2026, and…
United States District Court Southern District of New York
1:26-cv-05296-CM
2026-09-21 active
New Energy Economy, Center for Biological Diversity
v. New Mexico Environment Department, Project Jupiter data center developer
The New Mexico Supreme Court unanimously rejected challenges by environmental groups to the Project Jupiter data center's regulatory permits. The…
New Mexico Supreme Court Challenges to regulatory proceedings for Project Jupiter data center, including air quality permit application and use of emergency water well 2026-09-17 ruling
State ex rel. Kidd
v. Clinton Cty. Bd. of Elections
The lawsuit challenges a proposed ordinance related to data centers.
2026-09-18 active
ERNEST POPESCU
v. Iron Mountain Data Centers LLC
The court issued an order granting in part in this case. The order is documented as Case No. 2:25-cv-00219-RSM.
UNITED STATES DISTRICT COURT WESTERN DISTRICT OF WASHINGTON AT SEATTLE
2:25-cv-00219-RSM
2026-09-23 ruling
United States
v. Palacios Palacios
The document is a certification of records from the Defense Manpower Data Center, part of the Personnel Readiness Management Agency. It is related…
22-CR-20104-JB
2026-10-02 active
No matches.

Methodology and scope

This watchlist tracks U.S. data center projects, operators, and jurisdictional actions that carry a documented public paper trail: securities filings, regulatory dockets, litigation, government statements, utility filings, and trade press. It is maintained as a neutral reference. Entries are recorded as observed; the tracker does not rank projects or advocate an outcome.

  • Status reflects the most recent public signal for each entry. Where a project continues on schedule, that is recorded as plainly as a delay.
  • Capacity is shown in megawatts where reported, and left blank where not disclosed.
  • Local restrictions, utility dockets, lawsuits, and federal actions are drawn from primary filings and reputable outlets, each linked to its source.
  • The ERCOT queue snapshot is extracted directly from the ERCOT GIS Report.
  • Signals are collected on a recurring basis and reconciled into a single source of truth before publication.

Every citation on one page: Sources and citations. Companion policy map: SAVRN Data Center Moratorium Tracker. Capital side: North American Data Center Capital Atlas. Founder essay: The Queue Was the Fiction.

The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.
Check this address →
What is the Nationwide Data Center Delay Watchlist?

It is a continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Each entry links to its documented public source, and it is maintained as a neutral reference.

How is a project's status determined?

Status reflects the most recent public signal for each entry: halted, delayed, cancelled, pending review, litigation active, audit paused, under appeal, or withdrawn. Where a project continues on schedule, that is recorded as plainly as a delay.

How are delay days measured?

Delay days are measured against the original announced target where available, or against the first documented delay date.

How often is the watchlist updated?

Signals are collected on a recurring basis from SEC EDGAR and trade-press feeds and reconciled into the single source of truth before publication.

How is this different from the Data Center Moratorium Tracker?

The Moratorium Tracker maps state and local policy measures. This watchlist tracks named projects, operators, public-company exposure, and securities filings, with delay status and cause for each. The two are companion references.

Nationwide Data Center Delay Watchlist

Get these tracker updates by email

A short introduction on days 3, 7 and 14, plus updates for this tracker. Unsubscribe at any time.

We use your address to send the introduction and updates described above. See our Privacy Policy.

You’re on the list. Your subscription is saved.