Nationwide Data Center Delay Watchlist
A continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, local restrictions, litigation, federal and utility dockets, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Every entry links to its documented public source.
National interconnection queue
Every ISO plus vertically integrated utilities with a public row-level queue, as of 2026-09-28. The full row-level queue is refreshed weekly. ERCOT Batch Zero row-level classifications are not yet published per Market Notice M-A080326-01.
Browse a section below. Download the full dataset (JSON) or review all sources and citations.
Tracked projects
Named data center projects with a documented delay, cancellation, withdrawal, or active review. Status reflects the most recent public signal.
| Project | Location | MW | Status | Cause | Notes | Sources |
|---|---|---|---|---|---|---|
Diode Ventures Cedar Creek Lake Diode Ventures |
Cedar Creek Lake TX · ERCOT |
withdrawn | Pre-moratorium withdrawal, cited by Governor's office as example | |||
Project Matador (Amarillo) Fermi America (FRMI) |
Amarillo / Potter County TX · ERCOT |
11,000 | delayed | 11 GW at build-out; 600 MW gas turbines procured; 1 GW target by end of 2026. Not affected by moratorium (BTM). Continuing construction. | ||
GW Ranch (Fort Stockton) Pacifico Energy |
Fort Stockton TX · ERCOT |
5,000 | delayed | 5 GW off-grid gas + 1.8 GW battery. Bypasses ERCOT entirely. Not affected by moratorium. | ||
Amazon 7.65 GW Gas Plant / Self-Contained Island Amazon Web Services / partner (AMZN) |
TX TX · ERCOT |
5,000 | delayed | 35 turbines, 5 GW campus delivery, operates as self-contained energy island off ERCOT. Announced days AFTER moratorium, no delay impact. | ||
Stargate / Abilene (Phase 1) Crusoe (MSFT,ORCL) |
Abilene TX · ERCOT |
1,200 | delayed | 900 MW BTM gas microgrid + grid blend at 1.2 GW. Continuing. Additional 4.5 GW gas capacity secured by Crusoe. | ||
Good Data Center Campus (Armstrong County) Google (via developer) (GOOGL) |
Armstrong County TX · ERCOT |
delayed | Private natural gas turbines under state air permit. Not affected by moratorium. | |||
Voltagrid Shackelford County Voltagrid (ORCL) |
Shackelford County TX · ERCOT |
700 | delayed | 210 industrial gas gensets. 700 MW. Off-grid. Delayed to 2029 per SemiAnalysis due to gas pipeline permitting. | ||
Oracle/OpenAI Texas Expansion (Original Plan) Oracle (ORCL) |
TX TX · ERCOT |
withdrawn | Oracle/OpenAI abandoned Texas expansion March 6, 2026 over financing negotiations. Pre-moratorium. Microsoft later stepped in. | |||
CleanSpark Texas Operations (all) CleanSpark (CLSK) |
TX TX · ERCOT |
pending review | 10-Q risk factor disclosure: 'evaluating scope and enforceability of August 3, 2026 letter'. Only known public SEC disclosure explicitly referencing the moratorium. | |||
Lighthouse (Port Washington) Vantage Data Centers / Oracle / OpenAI (ORCL) |
Port Washington WI · MISO |
litigation active | $15B project. Sierra Club/Midwest Environmental Advocates lawsuit filed July 10, 2026 in Ozaukee County. Also April 2026 ballot referendum limited DC construction. | |||
Spring Valley Technology Park Active Infrastructure |
Loudoun County / near Beaverdam Reservoir VA · PJM |
780 | cancelled | 325-acre, 3.54M sq ft. Planning Commission voted unanimously to recommend denial. 500+ residents attended hearing. | ||
Dulles Cloud South |
Prince William County VA · PJM |
cancelled | Nearly 2,000-acre campus. Board of County Supervisors voted unanimously to deny rezoning. | |||
Mountain Road Technology Park Tract |
Hanover County VA · PJM |
cancelled | Board of Supervisors voted 4-3 to deny rezoning. Water concerns (up to 90% of local supply). | |||
Prince William 2,100-acre Campus (37 buildings) |
Prince William County VA · PJM |
cancelled | 37 buildings, gigawatt-scale; killed on public-notice technicality (notices not run 6 days apart) | |||
Project Blue (Amazon-linked) Beale Infrastructure (AMZN) |
Tucson AZ · WECC |
cancelled | City Council voted 7-0 to end negotiations and halt annexation. | |||
New Carlisle $13B Data Center |
St. Joseph County / New Carlisle IN · MISO |
cancelled | St. Joseph County Council rejected after 10-hour meeting. | |||
Hobart Amazon Data Center Amazon (AMZN) |
Hobart IN · MISO |
litigation active | Lawsuit filed to block fill permit alleging state law violations | |||
Project Tango |
Palm Beach County / Arden FL · SERC |
cancelled | Palm Beach commissioners voted 5-1 to deny after 12+ hour meeting. | |||
Pine Island Data Center Development |
Pine Island MN · MISO |
litigation active | TRO issued blocking construction pending MCEA challenge. Construction was to begin July 2026. | |||
T5 @ Chicago IV T5 Data Centers |
Lake County / Grayslake IL · PJM |
litigation active | Lawsuit filed July 31, 2026 alleging inconsistent with Comprehensive Plan. Initial status hearing Oct 30. | |||
Markley Group Lowell Expansion Markley Group |
Lowell MA · ISO-NE |
litigation active | MA Superior Court blocked installation of 4 new diesel generators pending resident lawsuit. | |||
Hexa Builders Monroe Township Hexa Builders LLC |
Monroe Township / Gloucester County NJ · PJM |
litigation active | Hexa filed $300M lawsuit against township for zoning ordinances banning DCs. | |||
DC BLOX Nashville (Grassmere Park) DC BLOX |
Nashville / Grassmere TN · SERC |
litigation active | Filed federal lawsuit Aug 11 challenging Nashville moratorium. Claims vested rights. | |||
Imperial Valley $10B AI Data Center Imperial Valley Computer Manufacturing LLC |
Imperial CA · CAISO |
litigation active | $10B project. Civil rights lawsuit filed against City of Imperial in fed court. | |||
Natelli Investments Wake County 250MW Natelli Investments |
Wake County NC · PJM |
250 | withdrawn | Withdrew annexation and rezoning applications early 2026. | ||
Hays County / San Marcos DC |
Hays County / San Marcos TX · ERCOT |
cancelled | San Marcos City Council voted 5-2 against zoning in February 2026. | |||
Eagan Capital Expansion Eagan Capital |
Eagan MN · MISO |
litigation active | Filed lawsuit June 15 against Eagan for moratorium exceeding city authority. | |||
DataBank Orangetown Phase 2 DataBank |
Orangetown / Orangeburg NY · NYISO |
delayed | Orangetown Planning Board voted unanimously to require EIS, delaying project indefinitely. | |||
Boulder City BLM Site |
Boulder City NV · WECC |
under appeal | Boulder City Council voted unanimously to appeal BLM approval. | |||
University of Michigan / Los Alamos Data Center |
Ypsilanti MI · MISO |
delayed | Ypsilanti Community Utilities Authority passed yearlong halt on water/sewer for DCs (April 2026) | |||
Prince William Digital Gateway (PW Digital Gateway) QTS Data Centers (Blackstone); Compass Datacenters (BX) |
Gainesville, Prince William County VA · PJM |
1,700 | cancelled | One of the world's largest planned data center clusters (34 buildings, 22M SF) next to Manassas National Battlefield Park was voided by courts over inadequate public notice for… | ||
Dulles Cloud South (Dulles South data center project) |
Gainesville, Prince William County VA · PJM |
cancelled | Nearly 2,000-acre, 43M-SF proposal to rezone farmland/residential land to industrial for data centers was rejected 8-0 by the Prince William Board of Supervisors, following on… | |||
Bristow Campus data center project Stack Infrastructure |
Bristow/Nokesville area, Prince William County VA · PJM |
delayed | Board of Supervisors hearing on this Nokesville Road/Broad Run Creek campus was deferred amid community opposition; a supervisor said backers "know they don't have the votes." | |||
PW Digital Gateway landowner tax litigation QTS Data Centers (BX) |
Gainesville, Prince William County VA · PJM |
litigation active | Landowners under contract to sell parcels to QTS for the Digital Gateway sued Prince William County over sharply increased tax assessments tied to the (litigation-blocked)… | |||
Loudoun County data center application pause |
Loudoun County VA · PJM |
pending review | Board of Supervisors voted to begin process of pausing all new data center applications, site plans and substations countywide (250 existing data centers, 53.3M SF) until new… | |||
Hiddenwood Lane / Hiddenwood Assemblage rezoning (Aldie) JK Technology Holdings / Aldie homeowner group |
Aldie, Loudoun County VA · PJM |
withdrawn | Group of Aldie homeowners on Hiddenwood Lane seeking industrial rezoning (756,000 SF data center potential) to sell out of an area surrounded by data centers indefinitely… | |||
Innovation Gateway |
Sterling, Loudoun County VA · PJM |
pending review | 700,000 SF data center plus affordable-housing rezoning near the Innovation Station Metrorail stop; Planning Commission recommended denial (5-2) as incompatible with the Urban… | |||
Oaklawn data center rezoning (Leesburg) Oaklawn, LLC |
Leesburg, Loudoun County VA · PJM |
cancelled | Leesburg Town Council denied 5-1-1 a rezoning to add up to 450,000 SF of data centers linked to affordable-housing units, citing inconsistency with the Zoning Ordinance and… | |||
Mountain Road Technology Park (Tract) Tract |
Route 33/Mountain Road, Hanover County VA · PJM |
900 | cancelled | Hanover Board of Supervisors rejected the conditional-use permit and A1-to-M1 rezoning for a 900MW/430-acre campus on May 27, 2026, after the Planning Commission had earlier… | ||
Chesterfield Tract data center park (Branders Road) Tract |
161 Branders Road, Chesterfield County VA · PJM |
withdrawn | Tract withdrew its zoning request for a 744-acre rural campus after the Planning Commission unanimously recommended against it, citing inadequate infrastructure and sole access… | |||
Chesterfield data center project (unnamed) paused amid county lawsuits |
Chesterfield County VA · PJM |
litigation active | Local reporting confirms an active Chesterfield County data center project paused amid county-level lawsuits, following the Zoning Appeals Board's denial of an appeal on a… | |||
Gigaland Data Center Campus GigaLand LLC |
Remington, Fauquier County VA · PJM |
800 | withdrawn | Fauquier Planning Commission voted to recommend denial of the original 800MW/2.2M-SF rezoning; the developer officially withdrew the application in July 2026 and plans a… | ||
Remington Digital Campus |
Remington, Fauquier County VA · PJM |
pending review | Fauquier Planning Commission recommended denial of a separate campus near Remington Technology Park adjoining the Meadows of Remington neighborhood; a related private turbine… | |||
Amazon Data Services Warrenton data center Amazon Data Services (AMZN) |
Warrenton, Fauquier County VA · PJM |
litigation active | Citizens for Fauquier County and 10 residents sued in Fauquier Circuit Court to overturn the Town Council's special-use-permit approval for a 220,000 SF Amazon facility, alleging… | |||
Bel Pre Tech Park (Brandy Station data center campus) Culpeper Acquisitions LLC |
Brandy Station, Culpeper County VA · PJM |
pending review | County planners denied the 4.6M-SF, nine-building rezoning application near the historic Brandy Station battlefield; applicant requested Board of Supervisors consideration be… | |||
Brandy Station data center proposal (David Martin parcel) |
Brandy Station, Culpeper County VA · PJM |
withdrawn | An 88-acre Brandy Station rezoning was withdrawn after an initial denial from the Culpeper County planning commission amid Brandy Station resident opposition. | |||
Red Ace Data Center Campus |
Culpeper County VA · PJM |
delayed | Application tabled by Culpeper County officials, per Data Center Dynamics reporting; no further detail on eventual outcome. | |||
Stafford County stricter data center rules (GWV Data Center reclassification context) |
Stafford County VA · PJM |
delayed | Following a marathon public hearing, Stafford County adopted stricter data-center zoning rules that developers and residents split over, raising the bar for future rezoning… | |||
Spotsylvania County data center special-use permit standards / statewide moratorium resolution |
Spotsylvania County VA · PJM |
pending review | Spotsylvania supervisors split on requiring special-use permits for data centers (March 2025) and by August 2026 the Board backed a call for a statewide moratorium on data… | |||
1500 Gateway Data Center Project Penzance Development / 1500 Gateway Venture, LLC |
City of Fredericksburg VA · PJM |
under appeal | Fredericksburg Planning Commission unanimously rejected (7-0) the 2.1M-SF rezoning and Special Use Permit in December 2025, its second denial after an initial February 2025… | |||
Emerald Lakes Estates data center (Great Bridge) Doug Fuller / Emerald Lakes Estates |
Great Bridge, City of Chesapeake VA · PJM |
cancelled | Would have been Hampton Roads' first major data center; Chesapeake City Council unanimously denied the agricultural-to-light-industrial rezoning for a 350,000 SF facility on… | |||
Chesapeake 8-month data center application pause |
City of Chesapeake VA · PJM |
pending review | Chesapeake City Council voted to approve an 8-month hold on all new data center application decisions amid growing calls for a statewide Virginia moratorium. | |||
Chesapeake data center zoning text amendment (Green Sea area) |
City of Chesapeake VA · PJM |
delayed | Chesapeake Planning Commission recommended against a data-center zoning text amendment in May 2025; a related zoning text amendment was indefinitely continued by the Planning… | |||
Mt. Airy Planned Innovation, Research and Technology data center campus VALCO (applicant); Thompson Family Office (landowner) |
Ruther Glen/Jericho Road, Caroline County VA · PJM |
withdrawn | Caroline County Board of Supervisors denied 5-1 a comprehensive-plan amendment for a 900-acre campus near the North Anna River; VALCO then withdrew its rezoning request. The… | |||
Google Botetourt County data center campus Google (GOOGL) |
Botetourt County VA · PJM |
litigation active | Western Virginia Water Authority stated it will not supply the 10-million-gallons/day Google sought; a FOIA lawsuit forced disclosure of secret water-use contracts (judge ordered… | |||
Campbell County data center rezoning (MESH Capital site) MESH Capital LLC |
Concord District, Campbell County VA · PJM |
cancelled | Campbell County Board of Supervisors voted 5-2 to reject removing 2000-era protective conditions from a 57-acre site marketed for up to three data centers, after dozens of… | |||
Surry County data center moratorium |
Surry County VA · PJM |
pending review | Surry County enacted an initial 60-day pause on data center approvals in June 2026, then extended it to a full two-year moratorium on July 21, 2026, while directing staff to… | |||
Powhatan County data center zoning proposal (Route 60/Page Road) Newport Equities / JMS Investments |
Powhatan County VA · PJM |
delayed | A community petition ("Preserve Powhatan") urged the Planning Commission to block a 120-acre data-center zoning proposal near the Chesterfield County line; the Board of… | |||
Amazon Louisa County data center (third project, cancelled) Amazon (AMZN) |
Louisa County VA · PJM |
cancelled | Amazon pulled a proposed third Louisa County data center project in July 2025 after strong community resistance, even as it continued building two other campuses in the county. | |||
Amazon Louisa County data center campus (Northeast Creek overlay, active construction) Amazon (AMZN) |
Louisa County VA · PJM |
litigation active | Homeowner Austin Newsom sued Amazon for private nuisance over brown water, dust and construction noise at Amazon's second Louisa County campus; a federal judge allowed the… | |||
Amazon Birchwood power plant data center campus Amazon (AMZN) |
Sealston, King George County VA · PJM |
litigation active | Board of Supervisors moved in April 2024 to re-rezone the old Birchwood power plant site back to agricultural, threatening Amazon's planned 19-building, 7.25M SF campus; Amazon… | |||
New Kent County data center-friendly technology overlay district |
New Kent County VA · PJM |
cancelled | Faced with widespread public disapproval at town-hall meetings, New Kent County supervisors spiked the plan to create a data-center-friendly overlay zone in July 2026,… | |||
Plaza 500 data center campus / Edsall Data Center Substation 2232 Starwood Capital Group (Starwood Digital Ventures) |
Lincolnia, Fairfax County VA · PJM |
pending review | Alexandria City Council formally asked Fairfax County to deny the Edsall Road substation feeding this 226,469 SF Starwood data center near the Bren Mar neighborhood; Rep. Don… | |||
Manassas National Battlefield adjacent data center litigation (American Battlefield Trust) QTS / Compass Datacenters (BX) |
Manassas/Gainesville, Prince William County VA · PJM |
cancelled | American Battlefield Trust sued to stop data center construction abutting Manassas National Battlefield Park; after a judge initially dismissed part of the suit (Nov 2024), the… | |||
Brightseat Tech Park (former Landover Mall site) Brightseat Associates LLC (Lerner Enterprises / The Tower Cos.) |
Landover, Prince George's County MD · PJM |
820 | pending review | Despite securing final approvals for 4.1M SF of data centers in Oct 2024, County Executive Aisha Braveboy ordered a temporary halt to all data center permitting on Sept 15, 2025… | ||
Prince George's County Qualified Data Centers moratorium (Brandywine area) |
Brandywine, Prince George's County MD · PJM |
pending review | Prince George's County Council initially voted against advancing data centers (Nov 2024) and enacted a countywide moratorium on "Qualified Data Centers" extended to expire June… | |||
Quantum Frederick |
Frederick County MD · PJM |
litigation active | Maryland Supreme Court blocked a citizen-driven referendum bid seeking to overturn a county ordinance that expanded the ~1,600-acre Quantum Frederick campus by 1,000 acres to… | |||
Charles County Zoning Text Amendment 25-187 (data center zoning enablement) |
Charles County MD · PJM |
withdrawn | Charles County Planning Commission twice recommended denial of ZTA 25-187, which would have permitted data centers in industrial zones, after hearings featuring "no data centers"… | |||
Penzance Bedington data center campus Penzance Management |
Bedington, Berkeley County WV · PJM |
delayed | Gov. Patrick Morrisey announced the $4B, 500+ acre Penzance data center near the Potomac River on Feb 26, 2026; more than 300 residents packed a March 20 county commission town… | |||
Jefferson County (WV) data center moratorium |
Jefferson County WV · PJM |
pending review | Jefferson County Board of Commissioners issued a 10-month moratorium (May 19, 2026) on new data center applications/rezonings, excepting sites already zoned via Planned… | |||
Microsoft New Albany / Heath / Hebron Licking County data center campuses Microsoft (MSFT) |
New Albany, Heath, Hebron, Licking County OH · PJM |
delayed | Microsoft paused all three Licking County data center sites (New Albany, Heath, Hebron; $1B combined, 700+ acres) in April 2025 while "evaluating sites in line with our… | |||
Amazon Data Services Sunbury data center campus Amazon (AMZN) |
Sunbury, Delaware County OH · PJM |
pending review | Sunbury has an active data center development moratorium (through Jan 31); residents are gathering signatures for a city charter amendment capping data center peak load at 25MW… | |||
Aligned Data Centers Pataskala facility Aligned Data Centers |
Pataskala, Licking County OH · PJM |
200 | delayed | Pataskala residents are collecting signatures for a municipal charter amendment capping data center peak load at 25MW, aimed squarely at blocking this proposed 200MW/89-acre… | ||
Pennhurst data center (East Vincent Township) Pennhurst Holdings LLC |
East Vincent Township, Chester County PA · PJM |
under appeal | East Vincent Township officials unanimously rejected a 1.9M-SF data center on the historic Pennhurst State School site; the developer plans to appeal to the Chester County Court… | |||
East Whiteland data center (Chesco) |
East Whiteland Township, Chester County PA · PJM |
litigation active | A controversial 1.6M-SF data center in East Whiteland faced community legal challenges over its approval; the project survived a court denial of the challengers' appeals in June… | |||
North Coventry boutique data center (Envision Land Use) Envision Land Use |
North Coventry Township, Chester County PA · PJM |
cancelled | North Coventry Township supervisors preemptively voted 3-2 to reject a proposed 120,000 SF data center near a PECO substation before a formal application was even filed,… | |||
Chester County temporary data center moratorium |
Chester County PA · PJM |
pending review | Chester County approved a temporary countywide moratorium on new data center project approvals to allow time for zoning study and regulation drafting. | |||
King of Prussia data center campus (Brian O'Neill applications) Brian O'Neill |
Upper Merion Township, Montgomery County PA · PJM |
litigation active | Developer Brian O'Neill sued Upper Merion Township; a Montgomery County judge issued an injunction (Aug 13, 2026) preventing the township from taking further action on his King… | |||
Keystone Trade Center AI data center campus (Amazon/NorthPoint) NorthPoint Development |
Falls Township, Bucks County PA · PJM |
delayed | Despite construction proceeding on the former U.S. Steel site (part of a $20B statewide Amazon investment), Falls Township residents organized a nearly 4,000-signature petition… | |||
Northampton County proposed data center farm conversions |
Northampton County PA · PJM |
delayed | Northampton County residents packed public meetings voicing fierce opposition ("I don't want you") to proposed data centers taking over farmland; a local coordinated "No Data… | |||
Homer City Energy Campus Homer City Redevelopment / Homer City Generation |
Homer City, Indiana County PA · PJM |
4,400 | pending review | Pennsylvania DEP fast-tracked and approved an air-quality permit (157 days vs. the projected 285) for this 4.4GW gas-fired data center campus at a former coal plant despite 500+… | ||
New Hill Digital Campus Natelli Holdings (Natelli Investments LLC) |
New Hill/Apex, Wake County NC · SERC |
300 | withdrawn | Developer withdrew annexation and rezoning applications for a 300MW campus near the Shearon Harris Nuclear Plant after a 2,000+ signature petition and intense resident backlash… | ||
Triangle Innovation Park West (TIP West) Eco TIP West LLC (Kirk Bradley / Lee-Moore Capital) |
Moncure, Chatham County NC · SERC |
750 | litigation active | Chatham County's 12-month moratorium on new data center/crypto-mine permits (adopted Feb 11, 2026) halted processing of TIP West's site plan; Eco TIP West sued the county in… | ||
Chatham County data center and crypto-mine moratorium |
Chatham County NC · SERC |
pending review | Chatham County commissioners unanimously approved a 12-month moratorium on new data center and cryptocurrency-mine permits (through February 2027) to draft new zoning rules and… | |||
Gates County data center moratorium |
Gates County NC · SERC |
pending review | Gates County's board of commissioners unanimously approved a one-year pause on new data center approvals amid growing statewide North Carolina opposition to hyperscale projects. | |||
Person County Microsoft data center Microsoft (MSFT) |
Person County NC · SERC |
delayed | Person County residents publicly demanded answers from Microsoft over a planned local data center; Microsoft hosted a community meeting in June 2026 amid rising central-NC… | |||
Hexa Builders Monroe Township data center (Black Horse Pike redevelopment) Hexa Builders LLC |
Williamstown, Monroe Township, Gloucester County NJ · PJM |
litigation active | After winning preliminary approval for two warehouses in January 2026, Hexa amended its application to swap in a 1M-SF data center; Monroe Township passed ordinances in April… | |||
Former Newton Airport site data center proposal |
Andover Township, Sussex County NJ · PJM |
litigation active | A developer sued Andover Township in state Superior Court (filed July 10, 2026) to overturn its data-center ban, alleging officials enacted the prohibition preemptively before… | |||
James City County data center special-use review policy |
James City County VA · PJM |
pending review | James City County supervisors moved to require special-use permit review for all data centers rather than by-right development, directing staff to draft a formal policy… | |||
Frederick County (VA) countywide data center ban consideration |
Frederick County VA · PJM |
pending review | Frederick County supervisors moved to consider a countywide ban on new data centers, following sustained opposition from Winchester-area residents citing six proposed projects;… | |||
DC Blox Indianapolis (Warren Township) DC Blox |
Warren Township, Indianapolis (Marion County) IN · MISO |
approved but citywide moratorium pending | One of three Indianapolis data centers drawing the most community opposition (energy, water, noise). Approved in July 2026 and would be exempt from the moratorium the City-County… | |||
Metrobloks Martindale-Brightwood Metrobloks |
Martindale-Brightwood, Indianapolis (Marion County) IN · MISO |
approved but citywide moratorium pending | Approved in May 2026 despite opposition; cited as one of three Indianapolis projects driving the citywide moratorium push. | |||
Sabey Data Center (Decatur Township) Sabey Data Centers |
Decatur Township, Indianapolis (Marion County) IN · MISO |
approved but citywide moratorium pending | Metropolitan Development Commission approved the $4B Sabey project in March 2026; one of the three flashpoint projects behind Indianapolis's moratorium debate. | |||
Google Franklin Township Campus (withdrawn) Google (GOOGL) |
Franklin Township, Indianapolis (Marion County) IN · MISO |
withdrawn | Google withdrew a proposal to rezone hundreds of acres in Franklin Township for a data center campus after contested opposition to the rezoning. | |||
New Carlisle $13B Data Center (St. Joseph County) Amazon (reported) (AMZN) |
New Carlisle, St. Joseph County IN · MISO |
rezoning denied | St. Joseph County Council voted 7-2 after a 10-hour, marathon meeting to deny rezoning ~1,000 acres of farmland off Chicago Trail. Opposition cited environmental impact,… | |||
Hobart Amazon Data Center Campus Amazon (AMZN) |
Hobart (Lake County), Ross Township IN · MISO |
active litigation | Hobart Plan Commission approved a fill permit Nov 6, 2025 for a 725-acre Economic Redevelopment Area near wetlands by Deep River. Residents sued alleging permit issued without… | |||
Microsoft Granger Data Center Microsoft (MSFT) |
Granger, St. Joseph County IN · MISO |
approved amid opposition | Approved Microsoft project in St. Joseph County drew continued resident protests at an open house over energy, water, and jobs concerns even after approval, part of broader… | |||
301 Digital Crossroads / CoreWeave (Hammond) CoreWeave / Decennial Group (CRWV) |
Hammond IN · MISO |
development agreement expired | City of Hammond announced the expiration of the $7B Development Agreement at 301 Digital Crossroads after required milestones were not met by the June 30, 2026 deadline; two… | |||
Clinton County Data Center / Precast Plant / Hydroponic Farm Unnamed developer |
Clinton County IN · MISO |
rezoning denied | Clinton County Board of Commissioners voted 3-0 to deny rezoning ~714.55 acres from A-1 agricultural to I-1 light industrial for a mixed data center, precast plant, and… | |||
Boone County Unincorporated Data Center Moratorium |
Boone County (unincorporated) IN · MISO |
moratorium in force | Boone County Board of Commissioners unanimously approved a one-year moratorium (effective June 16, 2026 to June 15, 2027) on new data center development in unincorporated Boone… | |||
Madison County Data Center Moratorium (extended) |
Madison County IN · MISO |
moratorium extended | Madison County commissioners unanimously extended a data-center moratorium to a full year to draft zoning rules, potentially including a permanent ban. Majority of residents at… | |||
Meta New Albany Data Center (Socrates South / AEP substation dispute) Meta (META) |
New Albany, Licking County OH · PJM |
250 | regulatory approval pending | Meta sought to draw 120-250MW from an idle AEP Ohio substation originally built for Intel's delayed chip fab (Intel now slated 2030-31, delayed from original date). AEP Ohio and… | ||
Microsoft Licking County Data Center (construction paused) Microsoft (MSFT) |
Licking County OH · PJM |
construction paused | Microsoft halted early-stage construction on a $1B Ohio site (three parcels; two reserved for farmland), citing reassessment of cloud/AI infrastructure needs, evolving… | |||
Amazon Data Services Sunbury Campus Amazon (AMZN) |
Sunbury, Delaware County OH · PJM |
proposed amid local moratorium and ballot fight | Sunbury has a data-center development moratorium in place until Jan 31 (2027); residents fear council could approve the $2B Amazon facility once it expires and are collecting… | |||
Conserve Ohio Statewide Data Center Ban Ballot Initiative |
Statewide (Ohio) OH · PJM |
signature gathering | Ohio Ballot Board approved a proposed constitutional amendment to prohibit large data center construction; Conserve Ohio needed 413,487 signatures from 44+ counties by July 1,… | |||
Lighthouse Campus (Port Washington), Oracle/Vantage/OpenAI Oracle / Vantage Data Centers (ORCL) |
Port Washington, Ozaukee County WI · MISO |
1,000 | active litigation | Nearly 1GW Stargate-partnership campus. Wisconsin PSC's April 2026 order required hyperscale operators (incl. Oracle) to post financial security before power service; estimated… | ||
Microsoft Mount Pleasant AI Campus (Foxconn site) Microsoft (MSFT) |
Mount Pleasant, Racine County WI · MISO |
construction partially paused | Built on former Foxconn site; total footprint ~1,121 acres across three parcels (215, 115, 791 acres); Microsoft now owns ~1,900 acres in Mount Pleasant. Microsoft paused… | |||
Microsoft Kenosha Data Center (proposed) Microsoft (MSFT) |
Kenosha, Kenosha County WI · MISO |
under council consideration | Residents packed multiple public forums urging Kenosha Common Council to slow consideration, citing water extraction, 24/7 noise, air quality tied to a linked 1,186 MW… | |||
QTS DeForest / Vienna Annexation ($12B, cancelled) QTS Data Centers (BAM) |
DeForest / Town of Vienna, Dane County WI · MISO |
cancelled | QTS's $12B proposal required annexing 1,600 acres from the Town of Vienna into DeForest. On Jan 27, 2026 village staff determined the project 'not feasible in DeForest' after ~7… | |||
Pine Island Data Center (Google) Ryan Companies (developer) (GOOGL) |
Pine Island, Goodhue County MN · MISO |
2,700 | construction halted by court | Could require up to 2,700MW. MCEA sued in October 2025 alleging environmental review only covered a generic 'technology center'/'light industrial' use, not disclosing Google as… | ||
Eagan Capital Expansion (Data Center Moratorium Suit) Eagan Capital |
Eagan, Dakota County MN · MISO |
active litigation | Eagan's development-pause ordinance (20MW+ new / 9MW+ expansion) is challenged by Eagan Capital, arguing the moratorium exceeds the city's authority; lawsuit filed to void the… | |||
Farmington Technology Park (Tract) Tract |
Farmington, Dakota County MN · MISO |
708 | active litigation | Denver-based Tract's 340-acre, up-to-12-building, 2.5M-sq-ft campus (~$5B at full buildout) on former golf-course/school land. Residents sued on technical and later environmental… | ||
Meta Rosemount Data Center (UMore Park) Jimnist LLC (Meta subsidiary) (META) |
Rosemount, Dakota County MN · MISO |
final decision paused | Planning Commission approved the site plan, but the City Council paused final action until after Dec 20 pending completion of a required 5-year Alternative Urban Areawide Review… | |||
Minneapolis Citywide Data Center Development Pause |
Minneapolis, Hennepin County MN · MISO |
moratorium in force | Minneapolis City Council approved a five-month pause on new data center development (excludes downtown centers under 350,000 sq ft) to study environmental, energy, and… | |||
Elk River Proposed Data Center |
Elk River, Sherburne County MN · MISO |
planning commission recommended denial | Elk River's planning commission recommended against a proposed data center despite advocates citing an estimated $800,000 in additional city revenue. | |||
Inver Grove Heights Proposed Data Center (Qlevr, former Travel Tags building, Carmen Avenue East) Qlevr |
Inver Grove Heights (Dakota County) MN · MISO |
pending review | Qlevr, which proposes a 54,000 square foot data center in the former Travel Tags building, sued the city after it adopted a one-year data center moratorium, saying its… | |||
University of Michigan / Los Alamos High-Performance Computing Facility University of Michigan / Los Alamos National Laboratory |
Ypsilanti Township, Washtenaw County MI · MISO |
100 | opposed planned | 144.5-acre site on Textile Road near Ford Lake Dam; $1.2B taxpayer-supported project planned to start construction 2027, operational by 2031. Ypsilanti City Council unanimously… | ||
Saline Township 'The Barn', OpenAI/Oracle Stargate Campus Related Digital (ORCL) |
Saline Township, Washtenaw County MI · MISO |
1,400 | rezoning denied then litigation settled | Part of OpenAI/Oracle's Stargate initiative; ~1,400MW from DTE Energy; 575 acres of farmland proposed for rezoning within a ~1,000-acre campus (two-thirds to remain open space).… | ||
Alterra Development Marshall Data Center (Brooks Industrial Park) Alterra Development |
Marshall, Calhoun County MI · MISO |
1,000 | moratorium delay | Alterra purchased 270 acres in Brooks Industrial Park near wetlands/a lake; original concept (gas plant + data center, ~1,000MW/1GW) later dropped the gas plant, cutting energy… | ||
Microsoft / Franklin Partners Covenant Business Park (Lowell-area township) Microsoft / Franklin Partners (MSFT) |
Township adjacent to Lowell (Kent County) MI · MISO |
rezoning paused | Estimated $500M-$1B investment over 3-5 years. Site needs rezoning from industrial PUD to light industrial. A December 2025 planning commission public hearing was… | |||
West Michigan Hyperscale Proposals (Solon, Lowell, Gaines Townships) |
Solon, Lowell, and Gaines Townships (Kent County) MI · MISO |
opposed proposed | Residents protested outside The Right Place's Developer Day (June 9-11, 2026) over multiple hyperscale proposals across three townships; criticism centered on private… | |||
Gotion Green Township Battery/Data Plant (abandoned) Gotion |
Green Township, near Big Rapids MI · MISO |
abandoned | Gotion abandoned its planned Green Township facility after legal challenges, environmental issues, and backlash over the company's China ties; Michigan had committed a $715M… | |||
T5 @ Chicago IV (Grayslake) T5 Data Centers |
Grayslake, Lake County IL · PJM |
1,550 | active litigation | Up to 472 acres within the $750M, 641-acre Cornerstone mixed-use development; ~1.55GW electrical demand from ComEd. Village Board approved between Sept 2024-May 2025. On July 31,… | ||
Project Vector / Endeavour Energy DeKalb Data Center Endeavour Energy |
DeKalb IL · PJM |
opposed pending council vote | Also referred to as the 'Edged data center'; ~560 acres along Route 23; Planning and Zoning Commission backed the project after a crowded hearing, but a Change.org petition drew… | |||
South Elgin Data Center (Whiterose Partners / Kenyon Brothers) Whiterose Partners / Kenyon Brothers Co. |
South Elgin, Kane County IL · PJM |
48 | opposed effectively stalled | 20-acre, 200,000-sq-ft, 48MW proposal at Kenyon Road/Route 25 requiring annexation, rezoning, and special-use permit. A petition gathered 4,800 signatures within 48 hours; a July… | ||
Aurora Data Center and Warehouse Moratorium |
Aurora, Kane/DuPage Counties IL · PJM |
moratorium in force | Aurora City Council enacted a 180-day moratorium (Sept 25, 2025) on new data center and warehouse development to research standards and draft zoning rules; applications can be… | |||
Project Cardinal (Yorkville) |
Yorkville, Kendall County IL · PJM |
active litigation | 1,037-acre planned campus, approved earlier in 2026. Residents (Preserve Our Yorkville & Community LLC) sued in April alleging the city failed to give required public notice,… | |||
Project Steel (Yorkville, Eldamain Corridor) |
Yorkville, Kendall County IL · PJM |
active litigation | Second Yorkville lawsuit, filed by residents including Teska Family Farm, along the Eldamain Corridor; land was annexed/rezoned from residential to manufacturing; suit alleges… | |||
Meyer Project / Yorkville Nexus V LLC Rezoning (withdrawn) Green Door Capital |
Yorkville, Kendall County IL · PJM |
withdrawn | ~130-acre rezoning request (91 acres west, 37 acres east) south of Project Steel; Planning and Zoning Commission rejected in January 2026; City Council vote postponed in March;… | |||
DC Blox Nashville Zoo-Area Data Center DC Blox |
Nashville, Davidson County TN · SERC |
active litigation | DC Blox filed a federal lawsuit against Metro Nashville after the city stopped processing permits under its temporary data-center moratorium (in effect through December 2026),… | |||
Hillwood Industrial/Data Center Development (Wilson County) Hillwood |
Wilson County TN · SERC |
rezoning rejected moratorium recommended | Texas-based Hillwood's proposed 1,380-acre, 10.35M-sq-ft industrial development (no data-center tenant named) near I-40 was rejected by Wilson County commissioners roughly 18… | |||
xAI Colossus 1 & 2 (Memphis) xAI / SpaceX |
Memphis, Shelby County TN · SERC |
active litigation | NAACP sued xAI on April 14, 2026 alleging air pollution from unpermitted gas turbines powering Colossus 1/2 in a majority-Black Memphis community; DOJ intervened on xAI's side… | |||
Serverfarm Clarksville ($6.6B) Serverfarm |
Clarksville, Montgomery County TN · SERC |
under construction amid scrutiny | $6.6B project beside Johnson Regional Medical Center advancing (cranes visible, hillside cleared as of January 2026) despite growing community scrutiny over communication, water… | |||
Douglas County I-20 Data Center Permit Denial (11-building/3-warehouse application) |
Douglas County (near I-20 / Carroll County line) GA · SERC |
permit denied | Douglas County commissioners voted 4-1 to deny a proposed data center permit near the Carroll County line/I-20 after a packed, contentious commission meeting. Separately, a… | |||
Project Sail (Coweta County) Prologis / Atlas Development (PLD) |
Coweta County (Sargent community, near Newnan) GA · SERC |
900 | approved active litigation | Nine-building, 4.34M-sq-ft, ~900MW campus on 829 acres of protected rural conservation land near Georgia Power's Plant Yates. First surfaced Dec 31, 2024; Coweta commissioners… | ||
Project Pegasus (Coweta County) American Real Estate Partners (backed) |
Coweta County GA · SERC |
delayed amid moratorium | Second Coweta County data-center proposal (Virginia-based American Real Estate Partners-backed developers) caught in the same 2025 county moratorium and zoning rewrite that… | |||
Newton County Data Center Application Moratorium |
Newton County (incl. Covington, Social Circle, Porterdale) GA · SERC |
moratorium in force | Newton County Board of Commissioners unanimously enacted a 30-day moratorium on new data-center applications to update ordinances amid a rapid influx of requests (does not affect… | |||
QTS Atlanta Data Center Expansion (Howell Station, tax break withdrawn) QTS Data Centers (BAM) |
Atlanta, Fulton County (Howell Station) GA · SERC |
tax incentive withdrawn | Development Authority of Fulton County had considered a $45M tax break for a QTS expansion near the Howell Station neighborhood; the request was withdrawn amid public outcry even… | |||
Project Tango (Palm Beach County) |
Palm Beach County (near Arden / Loxahatchee) FL · FRCC |
denied without prejudice | Palm Beach County commissioners denied the hyperscale AI data center 'without prejudice' after nearly 12 hours of debate, meaning the developer may revise and resubmit; site… | |||
XF Group Sarasota County Hyperscale Data Center Freeze XF Group |
Sarasota County (Cattlemen Road) FL · FRCC |
moratorium in force | Sarasota County commissioners voted July 8, 2026 to halt acceptance, review, and approval of hyperscale data centers (50MW+) until at least July 2027 along Cattlemen Road;… | |||
MIA-1 Data Center (Iron Mountain, Westview) Iron Mountain (IRM) |
Westview, unincorporated Miami-Dade County FL · FRCC |
16 | under construction amid opposition | 16MW, 150,000-sq-ft, $150M facility on a 3.4-acre industrial site in a predominantly Black community. Approved by-right under existing industrial zoning classified as a… | ||
Alachua Phoenix Commercial Park (rumored data center) |
Alachua, Alachua County FL · FRCC |
rumored no application filed | 104-acre Phoenix Commercial Park site east of San Felasco Tech City was listed as a 'high megawatt data center development site' and later relisted as an 'industrial… | |||
Meade County 138-Acre Data Center Rezoning (denied) |
Meade County (near Brandenburg) KY · SERC |
rezoning denied | 138-acre site along Joe Prather Highway; Planning and Zoning Commission voted unanimously against rezoning from agricultural to light industrial and the Fiscal Court agreed with… | |||
Lexington-Fayette Former Lexmark Property Data Center Moratorium |
Lexington-Fayette Urban County KY · SERC |
moratorium in force | Lexington-Fayette Urban County Government unanimously passed a moratorium on new data center development at a proposed site on the former Lexmark property, effective through… | |||
Burgin / Mercer County Proposed Data Center (draft ordinance pending) |
Burgin, Mercer County KY · SERC |
under review no zoning process | Residents allege developers targeted Burgin because it lacked a formal planning/zoning process; the Mercer County Joint Planning and Zoning Commission was set to discuss a draft… | |||
Meta Hyperion & Evest Data Centers (Richland Parish) Meta / Entergy (META) |
Richland Parish LA · SERC |
5,000 | regulatory disclosure dispute | Combined Hyperion and Evest campuses represent Meta's >5GW power request, described as the largest in Louisiana history; Entergy proposing 10 new gas plants (3 approved 2025, 7… | ||
xAI Southaven Data Center & Gas Turbine Plant (noise/class action) xAI / SpaceX (MZX Tech LLC) |
Southaven, DeSoto County MS · SERC |
active litigation | One of three xAI data centers in the Memphis metro built with 57 temporary gas turbines and a permit for 41 additional permanent turbines. Three Southaven residents filed a… | |||
Downtown Kansas City High-Rise Data Center (Quality Hill / Western Newspaper Union Building) Revitalization Unlimited |
Kansas City, Jackson County MO · SPP |
permit denied | Miami-based developer Revitalization Unlimited proposed a 384-foot, 20-story data center atop the historic Western Newspaper Union building in Quality Hill; Kansas City Plan… | |||
St. Charles County Data Center Moratorium |
St. Charles County MO · SPP |
moratorium in force | St. Charles County Council unanimously approved a six-month moratorium on new data centers after overwhelming public opposition; County Executive Steve Ehlmann said more research… | |||
Google Stillwater Data Center Campus (up to 6 buildings) Google (GOOGL) |
Stillwater, Payne County OK · SPP |
under construction amid water concerns | Google building up to six data centers; first two buildings expected to use ~2.7M gallons/day, rising to 8.1M gallons/day if all six are built (against ~7M gallons/day current… | |||
Project Anthem (East Tulsa) |
East Tulsa, Tulsa County OK · SPP |
phase vote delayed | Tulsa City Council voted unanimously (Mar 25, 2026) for a nine-month citywide data-center construction moratorium; Project Anthem's first and second phases were exempted, but the… | |||
Sand Springs Meta-Backed Data Center Meta (reported) (META) |
Sand Springs, Tulsa County OK · SPP |
opposed proposed | Tribal advocates and residents protested secrecy around a Meta-backed Sand Springs data center proposal; hundreds attended public meetings opposing the project. | |||
Project Pilot / Beale Infrastructure De Soto Campus Beale Infrastructure (Mount Sunflower Properties LLC) |
De Soto, Johnson County KS · SPP |
approved expanded amid opposition | Kansas' first hyperscale data center; ~300-acre site near the Panasonic EV battery plant on the former Flint Commerce Center/Ad Astra Park site. De Soto City Council approved the… | |||
Apple Waukee Data Center (extension) Apple (AAPL) |
Waukee, Dallas County IA · MISO |
delayed extension requested | $1.3B facility (400,000 sq ft) originally due to complete by August 2022; Apple requested a five-year extension to August 2027, citing need for more design/build time. Only… | |||
Linn County Unincorporated Area Data Center Moratorium |
Linn County (unincorporated, near Cedar Rapids) IA · MISO |
moratorium in force | Linn County Board of Supervisors approved an 18-month moratorium (2-1 vote, through Jan 1, 2028) for unincorporated county areas to update its data-center ordinance, conduct a… | |||
MidAmerican Energy Salix Data Center Exploration MidAmerican Energy (BRK.A) |
Salix, Woodbury County IA · MISO |
early stage amid county moratoriums | MidAmerican Energy annexed nearly 1,000 acres of farmland into Salix to explore data center development, even as neighboring Plymouth, Sioux, and Woodbury counties adopted… | |||
NorthMark Strategies / Valara Holdings Computing Center (former Kohler plant) NorthMark Strategies (Valara Holdings) |
Spartanburg County SC · SERC |
450 | permitting challenged | $2.8B conversion of a former Kohler kitchen/bath plant (also a longtime bitcoin-mining site) into a computing center. State regulators initially approved ~50MW; company sought to… | ||
Stream Data Centers Marion County (abandoned) Stream Data Centers |
Marion County SC · SERC |
400 | abandoned | Dallas-based Stream Data Centers dropped a planned 400MW, 400-acre, ~600,000-sq-ft campus in an industrial park near Marion, SC, citing 'utility timing constraints', MPD Electric… | ||
Greenwood County Data Center Moratorium |
Greenwood County SC · SERC |
moratorium in force | Greenwood County Council advanced a one-year moratorium on data centers in a 4-3 vote. | |||
Nebius Data Center (Oxmoor Valley, Birmingham) Nebius (NBIS) |
Birmingham, Jefferson County (Oxmoor Valley) AL · SERC |
active litigation | Under construction off Lakeshore Parkway. Jefferson County Circuit Judge ruled July 11, 2026 that Oxmoor Valley residents' lawsuit against the city's approval process can… | |||
Bessemer Proposed Data Center (Little Blue Creek) |
Bessemer, Jefferson County AL · SERC |
zoning request paused active litigation | Proposed site near ecologically sensitive Little Blue Creek and Five Mile Creek (habitat for the endangered watercress darter). Bessemer City Council removed the zoning item from… | |||
Jones Eagle / Jones Digital DeWitt Crypto Data Center Jones Eagle LLC / Jones Digital |
DeWitt, Arkansas County AR · SPP |
active litigation temporary block | Owner Qimin 'Jimmy' Chen (naturalized US citizen born in China) challenged Arkansas Act 636 (2023) and Act 174 (2024), which bar data-center/crypto-mining property ownership by… | |||
AVAIO Data Center Project (Pulaski County) AVAIO |
Pulaski County AR · SPP |
moratorium exemption rejected | Pulaski County Quorum Court rejected a proposed data-center moratorium that would have carved out an exemption specifically for the AVAIO project; separately, Little Rock's own… | |||
Grant County Data Center FOIA Dispute |
Grant County AR · SPP |
active litigation records dispute | Public-records (FOIA) litigation over a proposed Grant County data center; part of a broader pattern of Arkansas Democrat-Gazette records lawsuits seeking data-center contract… | |||
Imperial Data Center (Imperial Valley Computer Manufacturing / IVCM) Imperial Valley Computer Manufacturing, LLC (developer Sebastian Rucci) |
Imperial County (near city of Imperial) CA · CAISO |
delayed | Would be largest data center in California at ~1M sq ft; promoted as producing 2,500 construction jobs and $28.7M/yr tax revenue; county supervisors first approved parcel merger… | |||
GI Partners Santa Clara Data Center (2805 Bowers Avenue) GI Partners |
Santa Clara CA · CAISO |
delayed | Four-story data center; site cost $79M. Delayed ~5 months versus planned construction timeline before City Council approval on Aug 29, 2024. | |||
Coachella Valley Technology Campus Stronghold Power Systems |
Coachella (Riverside County) CA · CAISO |
cancelled | Six data centers proposed across 450 acres of agricultural land; was to anchor a new city-run utility agency; council unanimously voted to terminate the Stronghold agreement… | |||
Eight Form El Segundo Data Center (750 N. Nash Street) Eight Form |
El Segundo (Los Angeles County) CA · CAISO |
withdrawn | Proposed replacing a 15-year-old Hyatt Place hotel with 160-foot, five-story data center plus dedicated electrical substation. | |||
Monterey Park Data Center (HMC StratCap) HMC StratCap |
Monterey Park (Los Angeles County) CA · CAISO |
cancelled | 247,000 sq ft facility that would have used ~3x electricity of entire 60,000-person city; would have sat under 500 feet from nearest home; ban can only be overturned by another… | |||
Behring AI Campus / Data Center (415 20th St.) Behring Companies |
Oakland CA · CAISO |
20 | delayed | ~20,000 sq ft of an 83,000 sq ft, 4-story building; part of a larger complex with a proposed 39-story apartment tower above 19th St BART station. | ||
San Jose Data Center Pipeline (multiple Equinix and other projects) Multiple (incl. Equinix) (EQIX) |
San Jose CA · CAISO |
pending review | Environmental groups Green Foothills flagged 'grandfathering' risk since developers may rush applications ahead of new standards; active CEQA EIR review process for Equinix… | |||
High-Speed Rail Corridor Data Center Deals (Merced/Madera) California High-Speed Rail Authority (co-development partners TBD) |
Merced / Madera / Kern County CA · CAISO |
pending review | CEO Ian Choudri says hyperscalers in talks for Central Valley sites including Kern County; Madera mayor Cecilia Gallegos said city would reject data centers over water use. | |||
Project Blue (Tucson) Beale Infrastructure (originally Amazon Web Services-linked; AWS later withdrew) (AMZN) |
Pima County / Tucson AZ · WECC |
litigation active | Biggest development ever proposed in Pima County/southern Arizona; developer is San Francisco-based Beale Infrastructure; despite Tucson rejection and Amazon's exit, project is… | |||
Chandler AI Data Center (Sinema-lobbied project) Unnamed New York developer |
Chandler AZ · WECC |
cancelled | Chandler already hosts 10 data centers and adopted 2022 rules limiting where they can be built; vote drew national progressive praise as a rare rejection of major tech-industry… | |||
NTT Mesa Data Center NTT (9432.T) |
Mesa AZ · WECC |
delayed | NTT spent $300M on land in southeast Mesa (Pecos/Crismon roads) in March 2025; requesting minor modifications to city allowances. | |||
Casa Grande 480-Acre Data Center Campus (Willis/Barnes parcels) Undisclosed (landowners Dale Willis and Vernon Barnes; law firm representation) |
Casa Grande (Pinal County) AZ · WECC |
under appeal | No end user/tenant publicly identified; waiver includes 800 net acre-foot water cap, on-site power requirement, noise limits, decommissioning rules, $5M community contribution. | |||
Tract Goodyear/Buckeye Data Center Tract |
Goodyear and Buckeye (Maricopa County) AZ · WECC |
withdrawn | Company announced a replacement project near Buckeye airport in August 2024 with similar characteristics after securing mayoral support. | |||
Boulder City BLM Data Center (Townsite Solar 2 / Eldorado Valley) Townsite Solar 2, LLC |
Boulder City (Clark County) NV · WECC |
halted | On September 1, 2026 the U.S. Department of the Interior's Board of Land Appeals granted a stay of the Bureau of Land Management decision that allowed Townsite Solar 2, LLC to… | |||
Tract Northern Nevada Land Portfolio (Storey County/Reno area) Tract |
Storey County / Washoe County NV · WECC |
litigation active | Tract has purchased more than 12,000 acres across northern Nevada; company says it never sought subsidized costs and committed nearly $1B toward NV Energy infrastructure. Related… | |||
Reno Data Center Pipeline (city-wide moratorium) Multiple developers |
Reno NV · WECC |
halted | Initial 30-day moratorium adopted per city rules, then extended after a 9-hour public meeting with 5+ hours of comment; some council members want to study a permanent ban. | |||
Boardman Transmission Line / Amazon Data Center Support Infrastructure Amazon Web Services (AMZN) |
Boardman (Morrow County) OR · WECC |
litigation active | Decision on Boardman data center delayed in 2023 by new testimony; transmission line dispute continued into 2026 with regulatory challenges. | |||
Hillsboro Data Center Pipeline (city moratorium) Multiple developers |
Hillsboro (Washington County) OR · WECC |
halted | Hillsboro is one of Oregon's largest tech hubs (Intel/Silicon Forest); existing facilities may continue operating. | |||
Cascade Locks Data Center (Roundhouse Digital Infrastructure) Roundhouse Digital Infrastructure |
Cascade Locks (Hood River County) OR · WECC |
cancelled | Cited as an early precedent case for electoral backlash against data center approvals nationally. | |||
Umatilla County Eastern Oregon Data Center Moratorium Petition Multiple (Amazon and others) (AMZN) |
Umatilla County / Morrow County OR · WECC |
pending review | Part of broader statewide push including a legislature-considered one-year moratorium on data center tax breaks that Gov. Kotek has expressed support for. | |||
Seattle Data Center Pipeline (citywide moratorium) Multiple developers |
Seattle WA · WECC |
halted | Notable given Seattle is home to Amazon and Microsoft; part of a wider wave of Washington state municipal moratoria. | |||
Spokane Data Center Pipeline (citywide moratorium) Multiple (incl. Avista large-load customer) (AVA) |
Spokane WA · WECC |
halted | Data Center Coalition warned the moratorium sends a bad signal to a $1B+ minimum investment industry and could push Spokane out of site-selection conversations. | |||
Federal Way Data Center Moratorium Undisclosed |
Federal Way WA · WECC |
halted | Part of broader Puget Sound-region wave of municipal pauses. | |||
Grant County PUD Data Center Load Growth Cap Multiple (Microsoft and others in Quincy/Moses Lake corridor) (MSFT) |
Grant County (Quincy/Moses Lake) WA · WECC |
delayed | Quincy is historically Microsoft's flagship 'data centers gone right' market; new caps signal a shift even in the most data-center-friendly Washington jurisdiction. | |||
Broomfield Data Center Pipeline (18-month moratorium) Multiple developers |
Broomfield CO · WECC |
10 | halted | Threshold set at 10 MW; part of a wave of Front Range municipalities enacting pauses in 2026. | ||
Project Taurus (Colorado Springs) Raeden |
Colorado Springs (El Paso County) CO · WECC |
50 | delayed | On September 17, 2026 the Colorado Springs City Council voted 7-2 to postpone its decision on the appeal of the Project Taurus development plan modification until April 13, 2027,… | ||
Douglas County / Parker Flexential Data Center Flexential |
Douglas County (Parker) CO · WECC |
litigation active | Tax rebate value approximate ($19M); denial and rebate approval reflect a split regulatory record in the same county within months. | |||
Aurora Data Center Pipeline (moratorium debate) Multiple (incl. Microsoft Aurora AI Campus) (MSFT) |
Aurora CO · WECC |
delayed | Councilwoman Amy Wiles championed a pause; council ultimately opted for regulation over outright ban, but process caused delay for pipeline projects including the Microsoft… | |||
Lex Developments Pocatello Data Center ($2.6B) Lex Developments |
Pocatello (Bannock County) ID · WECC |
under appeal | Proposed at a former polysilicon plant site; Idaho Conservation League highlighted unprecedented cumulative energy use concerns, comparing water use to an 18-hole golf course or… | |||
Meta Kuna Data Center Expansion Pause Meta (META) |
Kuna (Ada County) ID · WECC |
delayed | Original $800M facility reached 'peak construction' before expansion was paused; 2023 Idaho law nearly stripped Kuna's urban renewal incentive tied to the project. | |||
Stratos Project (Box Elder County) Undisclosed developer (backed by Kevin O'Leary) |
Box Elder County UT · WECC |
7,000 | litigation active | Roughly 20,000-acre hyperscale campus near the Great Salt Lake requiring an estimated 7 GW of power - more than double Utah's current statewide energy use; celebrity investor… | ||
West Jordan Facebook Data Center (historical, cancelled) Facebook (Meta) (META) |
West Jordan UT · WECC |
cancelled | Historical precedent case frequently cited in current Utah data center debates; included for completeness though outside the post-Jan 2024 window as background context. | |||
Project Jupiter (Santa Teresa / Doña Ana County) Yucca Growth Infrastructure (developer); Oracle and OpenAI (end users) (ORCL) |
Santa Teresa (Doña Ana County) NM · WECC |
litigation active | Bonds ($165B) issued for Oracle/OpenAI development before Planning & Zoning Commission had voted on zoning, per plaintiff allegations; judge dismissed pro se resident's second… | |||
Project Zenith (Roswell) Undisclosed |
Roswell (Chaves County) NM · WECC |
pending review | County framework would only apply to projects seeking public incentives; privately financed projects exempted. | |||
Meta Los Lunas Expansion (Phase 3) Meta (META) |
Los Lunas (Valencia County) NM · WECC |
pending review | Original Meta investment estimated at $3.3B in Los Lunas; expansion phase raised renewed local water-use scrutiny. | |||
New York Statewide Hyperscale Data Center Moratorium (Executive Order 62) Multiple developers statewide |
Statewide NY · NYISO |
halted | First state to enact such a moratorium; affects pending projects including STAMP (Genesee County), Tonawanda, and Niagara Falls proposals; legislature had separately passed its… | |||
STAMP Data Center (Stream U.S. Data Centers / Genesee County) Stream U.S. Data Centers (via Genesee County Economic Development Center) |
Town of Alabama, Genesee County (STAMP industrial park) NY · NYISO |
250 | litigation active | 2.2M sq ft facility; $1.46B in requested state/local sales tax breaks ($716M state + $716M local); Hochul had previously called it a 'local decision' she wouldn't override (March… | ||
Wildflower Yaphank Data Center Wildflower |
Yaphank, Town of Brookhaven (Suffolk County) NY · NYISO |
halted | Long Island Power Authority said it does not anticipate service issues, with infrastructure costs borne by the developer; Suffolk County Water Authority says no water application… | |||
Lysander Data Center Moratorium Undisclosed |
Lysander (Onondaga County, Syracuse area) NY · NYISO |
halted | Part of the broader Syracuse-area wave of caution following major Micron/semiconductor-adjacent development pressure in the region. | |||
Islip Data Center Moratorium Consideration Undisclosed |
Islip (Suffolk County) NY · NYISO |
pending review | Reflects a cascading pattern of Long Island towns adopting pauses in mid-2026. | |||
Markley Group Lowell Data Center Generator Expansion Markley Group |
Lowell MA · ISO-NE |
litigation active | This is a litigation update on the previously tracked Markley Group Lowell Expansion entry - court-ordered construction pause specifically targeting diesel backup generator… | |||
Westfield Data Center ($4B) Undisclosed developer |
Westfield MA · ISO-NE |
delayed | Case highlights retroactive political risk even for previously-approved projects as statewide sentiment on data centers shifts. | |||
Atlas Capital Group Bloomfield Data Center Atlas Capital Group |
Bloomfield (Hartford County) CT · ISO-NE |
pending review | Proposed 900,000 sq ft data center plus 127,000 sq ft substation (over 1M sq ft total) at 132 Griffin Road North; among the first major hyperscale-scale proposals in Connecticut. | |||
New Haven Data Center Moratorium Proposal Multiple (regulatory, no single named project) |
New Haven CT · ISO-NE |
pending review | Precautionary, policy-level pause rather than a response to one specific project; part of statewide CT data center policy debate. | |||
Nottingham Business Park Data Center Nottingham Business Park LLC (developer Thomas Moulton) |
Nottingham NH · ISO-NE |
withdrawn | One of the largest small-town grassroots petition campaigns against a single data center project nationally. | |||
Verrus Data Center (Mill Creek Corporate Center) Verrus |
Salem (Marion County) OR · WECC |
pending review | Same statewide wave as Hillsboro's 120-day moratorium, enacted the same week; large crowds filled the Salem Public Library auditorium for the hearing. | |||
Smithfield Data Center (Hanton City Investments) Hanton City Investments LLC |
Smithfield RI · ISO-NE |
litigation active | A test case for whether an in-process application filed shortly before a newly passed local ban can be grandfathered in. | |||
Bates Mill Data Center (Lewiston) Undisclosed developer |
Lewiston ME · ISO-NE |
cancelled | Proposed inside a historic mill building; project's secrecy (unnamed backers) fueled resident suspicion and contributed to rejection. | |||
Diode Ventures Cedar Creek Lake Data Center Diode Ventures |
Henderson County (Cedar Creek Lake / Cedar Creek Reservoir) TX · ERCOT |
withdrawn | Update/confirmation of previously tracked entry - confirms formal withdrawal date and cause; Cedar Creek Lake is a major regional drinking-water and recreation reservoir, which… | |||
Blueprint Data Centers Taylor Facility Blueprint Data Centers |
Taylor (Williamson County) TX · ERCOT |
litigation active | 135,000 sq ft facility; case highlights title/deed-restriction risk as an emerging litigation vector for Texas data center siting distinct from zoning or environmental claims. | |||
Meta Temple Data Center Meta (META) |
Temple (Bell County) TX · ERCOT |
delayed | Part of the same Meta redesign wave that paused the Kuna, Idaho facility. | |||
Project Patriot / Knox Ranch (Granbury) Bilateral Energy |
Granbury (Hood County) TX · ERCOT |
litigation active | One of several Hood County data center disputes (see also Comanche Circle/Sailfish and Project Red/Yellow entries) reflecting a concentration of Central Texas litigation around… | |||
Comanche Circle / Sailfish Investors Data Center Sailfish Investors (developer Ryan Hughes) |
Hood County TX · ERCOT |
delayed | Included here as a delay/opposition case even though ultimately approved, given the scale of community pushback documented in local coverage; distinct 2,100-acre parcel from the… | |||
Project Red and Project Yellow (Hood County) National CRE Holdings and Greenland Capital |
Hood County TX · ERCOT |
under appeal | Two related data center proposals in Hood County, adding to the county's concentration of contested projects alongside Comanche Circle and Project Patriot/Knox Ranch. | |||
Wichita Falls Data Center Rezoning (Data Nova X) Data Nova X (originally proposed under different developer branding) |
Wichita Falls TX · ERCOT |
cancelled | Rezoning rejection halted the project as proposed; local coverage noted skepticism over the developer's rebranding partway through the approval process. | |||
RCM Hill LLC Data Center (Hill County) RCM Hill LLC |
Hill County TX · ERCOT |
litigation active | Notable as a case where litigation pressure from the developer side successfully forced a county to reverse its own moratorium. | |||
Highlander SM One LLC Data Center (San Marcos) Highlander SM One LLC |
San Marcos (Hays County) TX · ERCOT |
cancelled | Distinct developer/parcel from the already-tracked Hays County/San Marcos data center entry; this project was rejected outright twice rather than approved. | |||
Skybox Datacenters San Angelo Project Skybox Datacenters |
San Angelo (Tom Green County) TX · ERCOT |
delayed | City-owned land angle distinguishes this from typical private-parcel disputes; raised transparency and public-benefit questions locally. | |||
Red Oak Data Center Rezoning (Compass Datacenters) Compass Datacenters |
Red Oak (Ellis County) TX · ERCOT |
delayed | Included as a documented opposition/delay case with a notable community-benefit concession, even though the rezoning was ultimately approved. | |||
Texas Statewide Data Center Interconnection Audit (ERCOT Batch Zero) Multiple (up to ~300 projects statewide, including Sherman/Grayson County pipeline) |
Statewide (ERCOT footprint, incl. Sherman/Grayson County) TX · ERCOT |
halted | Sherman/Grayson County is a major semiconductor and data-infrastructure growth corridor (Texas Instruments, GlobiTech) directly affected by the pause; this is a statewide… | |||
HB 259 - Large Energy Use Facilities |
Alaska (statewide) AK |
cancelled | Alaska HB 259 (introduced January 2026 by Rep. Donna Mears) would require large energy facilities (peak demand ≥20 MW) to enter community benefit agreements with the host… | |||
Crow Holdings Development / CHI Acquisitions LP City of Fayetteville Crow Holdings Development / CHI Acquisitions LP |
City of Fayetteville GA |
cancelled | Crow Holdings Development and CHI Acquisitions LP officially withdrew their appeal on March 18, 2026 to build a 300,000 sq ft data center on 37.4 acres on Highway 85 North near… | |||
HB 1063 |
Georgia (statewide) GA |
cancelled | Requires electric utilities and new data centers (100+ MWH peak annual demand) to agree on contract terms that shield other power customers from construction and operation costs.… | |||
SB 34 |
Georgia (statewide) GA |
denied | Georgia SB34 would have prohibited data center fuel generation and transmission costs from being included in residential electricity rates, requiring commercial data centers to… | |||
POWER Act (SB4016) + Tax Pause |
Illinois (statewide) IL |
cancelled | Illinois: The POWER Act (SB 4016/HB 5513), sponsored by Rep. Robyn Gabel (Evanston) and Sen. Ram Villivalam, establishes comprehensive statewide standards for data center… | |||
SB 400 |
Kansas (statewide) KS |
cancelled | Kansas SB 400 would require data centers to use closed-loop cooling systems (no water evaporation) and authorize municipalities, local district attorneys, and the state attorney… | |||
SB 526 |
Kansas (statewide) KS |
cancelled | SB 526 adds a zoning requirement to Kansas's existing SB 98 data center sales tax exemption program, mandating that data centers must be located on land zoned for industrial or… | |||
LD 307 Moratorium Amendment LiquidCool (seeking exemption for Loring data center) |
Maine (statewide) ME |
26 | denied | Governor Janet Mills VETOED LD 307 on April 24, 2026, "An Act to Establish the Maine Data Center Coordination Council and Place a Temporary Limitation on Certain Data Centers."… | ||
Google / Meta / Metrobloks Missouri (statewide legislation) Google / Meta / Metrobloks |
Missouri (statewide legislation) MO |
cancelled | Missouri has multiple data center bills (proposed by Google / Meta / Metrobloks). HB 3362 and HB 3364 (Reps. Colin Wellenkamp, Scott Miller, Mike Costlow), titled the 'AI… | |||
HB 4424 |
Oklahoma (statewide) OK |
cancelled | HB 4424, filed by House Speaker Kyle Hilbert (R-Bristow), ends data center eligibility for Oklahoma's property tax exemption program, which covers facility property taxes for the… | |||
SB 1488 |
Oklahoma (statewide) OK |
cancelled | SB 1488, introduced by Sen. Kendal Sacchieri (R-Blanchard), would establish a moratorium on new data centers in Oklahoma until November 2029 while the Corporation Commission… | |||
Fairwater Wisconsin (Mount Pleasant) (referenced) |
Wisconsin Legislature (SB 729 Data Center Accountability Bill) WI |
denied | Sen. Jodi Habush Sinykin (D-Whitefish Bay) and Rep. Angela Stroud (D-Ashland) introduced the first Wisconsin bill to hold data centers accountable. SB 729 / LRB 5432 would create… | |||
Microsoft (Mount Pleasant data center), Meta (Beaver Dam data center) Wisconsin (statewide moratorium bill) Microsoft (Mount Pleasant data center), Meta (Beaver Dam data center) |
Wisconsin (statewide moratorium bill) WI |
cancelled | Wisconsin SB 1061 would have imposed a moratorium on new data center construction until the state established a data center planning authority, prohibited cost-shifting to… | |||
Crane Data Centers Pierce Township Campus (near former Beckjord plant) Crane Data Centers |
Pierce Township (Clermont County) OH · PJM |
300 | halted | Crane Data Centers, based in San Francisco, presented a concept for a 300 MW campus of three buildings of roughly 200,000 to 300,000 square feet on about 300 acres of wooded,… | ||
Legacy Investing North Loop Data Center (former Star Tribune Heritage Printing Facility) Legacy Investing |
Minneapolis (Hennepin County) MN · MISO |
20 | withdrawn | Virginia-based Legacy Investing terminated its purchase agreement for the vacant former Star Tribune printing plant in the North Loop, where it had proposed a 20 MW data center… | ||
MCNI Concord Township Data Center Rezoning MCNI (LLC) |
Concord Township, Hancock County (near Garner) IA · MISO |
delayed | The Hancock County Planning and Zoning Commission unanimously denied MCNI's request to rezone about 724 acres from agricultural to industrial for a potential data center after a… | |||
DC Rapids LLC Data Center (former papermill site) DC Rapids LLC |
Wisconsin Rapids (Wood County) WI · MISO |
pending review | The Wisconsin Rapids Plan Commission voted 7-0 on September 16, 2026 to recommend denial of DC Rapids LLC's conditional use and site review applications to redevelop the former… | |||
Harrington Logistics Building Data Center (Maguire Hayden) Maguire Hayden |
Harrington (Kent County) DE · PJM |
24 | halted | The Harrington City Council unanimously rejected on August 17, 2026 the zoning change needed to allow a proposed 24 MW data center at the former Harrington Logistics cold storage… | ||
Project Oak (Walt Sanders Road data center campus) |
Coweta County (Walt Sanders Road, near Newnan) GA · SERC (Georgia Power) |
halted | The Coweta County Board of Commissioners unanimously denied a rezoning request to amend conditions on an industrially zoned 255-acre site that limited it to office and warehouse… | |||
LightHouse Data Centers campus at 300 Jones Road (former paper mill site) LightHouse Data Centers (property acquired by a Lightstone Group affiliate) |
Spartanburg County SC · SERC (Duke Energy Carolinas) |
60 | halted | County planning staff rejected the development application on June 26, 2026 for five items not in compliance with the Unified Land Management ordinance. On August 25, 2026 the… | ||
Project Tomahawk (Parvin Road and FM 1385) White Rose Partners |
Prosper (Collin and Denton Counties) TX · ERCOT |
withdrawn | White Rose Partners sought rezoning of about 37 acres at Parvin Road and FM 1385 for a 225,000 square foot data center estimated at about $580 million. On September 1, 2026 the… | |||
Inver Grove Heights Proposed Data Center |
Inver Grove Heights, Dakota County MN · MISO |
final vote delayed | City council delayed a final vote after a packed, contentious meeting erupted in boos over the delay. | |||
Meta Alabama Meta |
Alabama AL |
cancelled | In Alabama, SB 354 would impose a one-year moratorium on construction of new large-scale solar power facilities, Prompted by opposition to a 4,500-acre solar project in Stockton… | |||
Green Digital LLC City of Harrison Green Digital LLC |
City of Harrison AR |
cancelled | Harrison passed a moratorium on data centers and crypto mining on May 25, 2023 after hundreds of residents objected to a Green Digital LLC crypto facility (a subsidiary with… | |||
Project Range Tract |
Maricopa County AZ |
1,800 | cancelled | Tract withdrew its $14B 'Project Range' application for a 30-building, 5.6M sq ft data center campus on ~1,000 acres near Yuma and Perryville roads in unincorporated Maricopa… | ||
NE Edge Waterford / East Lyme NE Edge |
Waterford / East Lyme CT |
300 | denied | CT Siting Council denied Dominion Energy's petition to modify Millstone Power Station boundaries for NE Edge's 1.5M sq ft hyperscale data center (300MW, ~15% of reactor output).… | ||
Sentinel Grove Technology Park / Project Jarvis Epic Estates 68 LLC / Timberline Real Estate Partners |
St. Lucie County FL |
1,000 | cancelled | In St. Lucie County, Florida, The developer of Sentinel Grove Technology Park (Project Jarvis), a proposed 1,218-acre, 15-million-square-foot, $13.5B data center campus at 1GW… | ||
Atlas Development LLC Adairsville area (Bartow County) Atlas Development LLC |
Adairsville area (Bartow County) GA |
cancelled | In Adairsville area, Georgia, Atlas Development sought to rezone 588 acres from agricultural for a $4.5 billion, six-building, 2.27M sq ft data center campus called 'Project… | |||
Brennan Investment Group Barrington Hills Brennan Investment Group |
Barrington Hills IL |
cancelled | Brennan Investment Group withdrew its $2 billion data center proposal for land south of Penny Road and west of Pond Gate Drive in Barrington Hills, Illinois, a suburb northwest… | |||
Cloud Centers Lisle Cloud Centers |
Lisle IL |
50 | cancelled | In Lisle, Illinois, Cloud Centers proposed a 256,000 sq ft, 50MW data center on the former Lockformer toxic-contaminated site (18 acres). Over 300 residents packed a public… | ||
Karis Data Center (Nokia/Lucent Campus) Karis Critical |
Naperville IL |
36 | denied | Naperville, Illinois, City Council voted 6-1 to deny Karis Critical's proposal for a 145,000 sq ft data center on the former Nokia/Lucent campus (36 MW, $250M, 40 acres). A… | ||
Western Hospitality Partners Pekin Western Hospitality Partners |
Pekin IL |
denied | In Illinois, Hundreds of residents packed a city council meeting to challenge a data center proposed on the Lutticken Farm along the Mahomet Aquifer, Which serves nearly 1… | |||
Brassie Golf Course Data Center Provident Realty Advisors |
Town of Chesterton IN |
cancelled | Provident Realty Advisors proposed a $1.3B data center on the 200-acre former Brassie Golf Course site along Pearson Road. The plan called for eight buildings at 150,000 sq ft… | |||
Project Flo Google |
Franklin Township (Indianapolis) IN |
400 | cancelled | Google withdrew its 468-acre 'Project Flo' data center in Franklin Township, Indianapolis on September 22, 2025, hours before the City-County Council was expected to vote it… | ||
Provident Realty Advisors Town of Burns Harbor Provident Realty Advisors |
Town of Burns Harbor IN |
cancelled | Provident Realty Advisors, after being rejected in Chesterton, proposed a seven-building, 102-acre data center campus at the corner of S. Babcock and Haglund Roads on the… | |||
Poe Companies / PowerHouse Data Centers (approved project) Louisville Poe Companies / PowerHouse Data Centers (approved project) |
Louisville KY |
400 | denied | One 525MW data center project in southwest Louisville has been cleared to proceed, built by Poe Companies and PowerHouse Data Centers (starting at 100MW, expanding to 400MW).… | ||
Project Lincoln: OC Data Center Western Hospitality Partners |
Oldham County KY |
600 | cancelled | Western Hospitality Partners proposed 'Project Lincoln: OC Data Center,' a $6B, 600MW facility initially planned for 267 acres at 3557 North Highway 53. Due to fierce opposition… | ||
Thomas A. Hobbs Living Trust (applicant) Meade County Thomas A. Hobbs Living Trust (applicant) |
Meade County KY |
cancelled | Thomas A. Hobbs Living Trust requested rezoning of a 138-acre site along Joe Prather Highway (25025 Joe Prather Hwy, Ekron) from Agricultural/Residential to Light Industrial for… | |||
Servistar Realties Westfield Servistar Realties |
Westfield MA |
delayed | A $3-4 billion, 2.7M sq ft hyperscale data center campus proposed at 199 Servistar Industrial Way. State legislature passed a 20-year sales tax exemption. By Dec 2025, developers… | |||
Amazon AWS / Natelli Holdings Calvert County Amazon AWS / Natelli Holdings |
Calvert County MD |
denied | Calvert County Board of Commissioners voted 2-3 against a proposed 24-month moratorium on data center permits. Commissioner Hart had proposed the moratorium after Amazon AWS… | |||
Meta Howell Township Meta |
Howell Township MI |
cancelled | Township enacted a unanimous six-month moratorium on Nov. 20, 2025 after ~2 hours of public comment. Trustee Bob Wilson confirmed Meta was behind the project, estimating a $9B… | |||
Amazon/AWS City of Becker Amazon/AWS |
City of Becker MN |
600 | cancelled | Amazon planned a multibillion-dollar data center near the Xcel Sherco coal-fired power plant in Becker, proposing 250 diesel backup generators. In March 2025, the Minnesota PUC… | ||
Geronimo Power Nobles County Geronimo Power |
Nobles County MN |
denied | Nobles County (MN) Board of Commissioners voted 3-2 on April 21, 2026 to deny a zoning change that would have allowed Geronimo Power's proposed $4 billion, ~640-acre data center… | |||
Oppidan / Connect Data Centers Apple Valley Oppidan / Connect Data Centers |
Apple Valley MN |
denied | Oppidan/Connect Data Centers' Apple Valley Technology Park proposal (seven buildings on former sand/gravel mining site, five as data centers) faced community opposition over… | |||
Oppidan City of North Mankato Oppidan |
City of North Mankato MN |
500 | cancelled | Oppidan halted its data center project citing lengthy permitting for diesel generators. MCEA (Minnesota Center for Environmental Advocacy) sued the city in August 2025, alleging… | ||
Harper Road Technology Park Diode Ventures |
City of Peculiar MO |
750 | cancelled | Peculiar originally added a 'data center' definition to its light industrial zoning, enabling Diode Ventures' proposed $1.5B Harper Road Technology Park, a 500-acre campus with… | ||
Nebius Independence Nebius |
Independence MO |
1,200 | denied | Independence City Council approved $6.26 billion in tax breaks over 20 years for Nebius on March 2, 2026, including a 98% real property tax abatement, 90% personal property tax… | ||
Atlas Power / Sabey Data Center Properties Butte Atlas Power / Sabey Data Center Properties |
Butte MT |
250 | cancelled | Sabey Data Centers proposed two 500,000 sq ft buildings (1M sq ft total) on over 600 acres at Montana Connections Industrial Park in Butte, MT (Silver Bow County), requiring 325… | ||
Mooresville data center Tract |
Mooresville NC |
1,500 | cancelled | Denver-based Tract proposed the $30B Mooresville Technology Park on 400 acres of undeveloped land owned by Teresa Earnhardt, widow of NASCAR champion Dale Earnhardt. The project… | ||
Project Delta Engineered Land Solutions |
Stokes County NC |
cancelled | Stokes County Board of Commissioners approved (3-2 vote) in January 2026 the rezoning of approximately 1,845 acres of residential-agricultural land along the Dan River for heavy… | |||
Champion Farm Data Center Campus Province Group |
Perry Township OH |
cancelled | Province Group formally withdrew its zoning application for a data center campus in Perry Township/Perry Village as of July 2025. The developer had signed an agreement to… | |||
PRSM Preble County Patrick Scanlon (developer) |
Preble County OH |
denied | Preble County Planning Commission unanimously (11-0) denied rezoning of 300 acres of farmland for a data center. The developer withdrew his application in October after residents… | |||
Mvskoke Technology and Innovation Park Undisclosed |
Muscogee (Creek) Nation OK |
cancelled | Jordan Harmon and Mackenzie Roberts (both Muscogee Nation citizens) organized town halls after plans emerged to build a massive AI data center on 5,500 acres of Muscogee Nation… | |||
Project Atlas Beale Infrastructure |
Coweta OK |
400 | cancelled | In Coweta, Oklahoma, Beale Infrastructure's $800M Project Atlas proposed 295 acres for an Amazon/AWS data center with 400MW capacity. The Planning Commission voted 4-1 to deny… | ||
Intel / Stack Infrastructure Hillsboro (SB 1586) Intel / Stack Infrastructure |
Hillsboro (SB 1586) OR |
cancelled | SB 1586, which would have brought 373 acres of rural land into Hillsboro's UGB for tech industries, was shelved. Separately, Councilor Kipperlyn Sinclair's data-center moratorium… | |||
Cleveland Cliffs Steel Plant Data Center Brian O'Neill (developer) |
Conshohocken / Plymouth Township PA |
cancelled | A developer attempted to convert the Cleveland Cliffs steel plant on 66 acres of Plymouth Township's riverfront corridor into a data center for undisclosed Big Tech tenants. Over… | |||
Kriger / Alpesh 'Al' Patel Blakely Kriger / Alpesh 'Al' Patel |
Blakely PA |
1,500 | cancelled | Developers proposed a data center campus offering up to 1.5GW of capacity on 209 acres in Blakely Borough, requiring power equivalent to the entire output of the nearby… | ||
NorthPoint Development Hazle Township NorthPoint Development |
Hazle Township PA |
denied | Hazle Township, Pennsylvania, Board of Supervisors unanimously rejected NorthPoint Development's 1,280-acre, 15-building 'Project Hazelnut' data center campus in Luzerne County… | |||
Pennhurst Data Center Penn Hurst Holdings DE LLC |
East Vincent Township (Pennhurst) PA |
denied | East Vincent's planning commission recommended rejection of a proposed 1.9 million sq ft data center at the former Pennhurst State School and Hospital for the second time.… | |||
Project Spero TigerDC (HG Tiger DC I LLC) |
Spartanburg County (NorthMark/Project Spero) SC |
400 | cancelled | TigerDC formally withdrew its $3 billion 'Project Spero' AI data center from Tyger River Industrial Park after Spartanburg County Council unanimously voted down two… | ||
Applied Digital Toronto Applied Digital |
Toronto SD |
430 | cancelled | Applied Digital confirmed its proposed $5B, 430MW data center campus near Toronto, SD is 'unlikely to go forward' after the legislature rejected tax incentives. The CEO stated… | ||
Sioux Falls Hyperscale Data Center Gemini Data Center SD LLC (Gemini Capital) |
Lincoln County SD |
500 | denied | Lincoln County Commissioner Joel Arends proposed a one-year moratorium on hyperscale data centers requiring 100+ MW, calling it an opportunity to 'press pause and further… | ||
Bitcoin Mining Data Center Red Dog Technologies |
Franklin County TN |
35 | denied | Franklin County Commission denied rezoning for Red Dog Technologies' proposed Bitcoin mining data center near Tullahoma. Residents said noise would be unbearable and damage… | ||
CloudBurst Data Centers / Highlander SC One LLC Hays County CloudBurst Data Centers / Highlander SC One LLC |
Hays County TX |
1,200 | denied | Water advocates identified 5 data centers proposed for the Hays County, Texas, region during historic drought (proposed by CloudBurst Data Centers / Highlander SC One LLC)… | ||
Comanche Circle Sailfish Development |
Hood County TX |
denied | Hood County (40 miles SW of Fort Worth) has received at least five data center applications (proposed by Sailfish Development). Commissioners voted down a proposed moratorium… | |||
Highlander SC One LLC San Marcos Highlander SC One LLC |
San Marcos TX |
380 | denied | San Marcos, Texas, City Council voted 5-2 at 2:14 AM on February 18, 2026 to deny zoning amendments for a $1.5 billion, 380 MW data center by Highlander SC One LLC (Fort Worth)… | ||
Texas Solar Works Lubbock Texas Solar Works |
Lubbock TX |
cancelled | Planning and Zoning Commission voted 4-3 to reject a 936-acre hyperscale AI data center zoning change from Low Density Single Family to General Industrial, requested by Hugo Reed… | |||
Amazon/AWS Louisa County Amazon/AWS |
Louisa County VA |
cancelled | Amazon Web Services withdrew a conditional use permit application for a 7.2 million-square-foot data center campus on 1,370 acres in Louisa County's Mineral area (south of Davis… | |||
Balico Pittsylvania County Balico |
Pittsylvania County VA |
3,500 | cancelled | The Pittsylvania County Board of Supervisors voted to deny a massive 2,200-acre datacenter campus proposal that would have included 84 datacenter buildings and a 3,500MW natural… | ||
Doug Fuller / Emerald Lakes Estates Chesapeake Doug Fuller / Emerald Lakes Estates |
Chesapeake VA |
denied | Chesapeake City Council unanimously rejected a proposal to rezone 22.6 acres of agricultural land for a 350,000 sq ft data center. The Planning Commission had voted 6-1 against… | |||
HB 503 |
Virginia (HB 503) VA |
denied | Prohibits Virginia utilities from recovering costs of transmission lines and energy generation serving data centers over 100 MW from residential ratepayers. Aimed at addressing… | |||
Hunting Hawk Technology Center HHHunt |
Hanover County VA |
900 | cancelled | In Hanover County, Virginia, HHHunt's proposed Hunting Hawk Technology Park, a 10-building, 400-acre data center campus near the Wyndham community capable of supporting up to 900… | ||
SB 393 - Virginia's Great Outdoors Act |
Virginia (SB 393) VA |
denied | Virginia SB 393, the Virginia's Great Outdoors Act (companion HB 641), was defeated in February 2026. The bill would have created a $250M/year dedicated funding stream for land… | |||
Tract Capital / Winchester Gateway LLC Frederick County Tract Capital / Winchester Gateway LLC |
Frederick County VA |
cancelled | In June 2025, the Frederick County Board of Supervisors voted by consensus against moving forward with applications for two large data centers: the proposed 644-acre Meadow Brook… | |||
Menomonie Data Center Balloonist LLC |
Menomonie WI |
750 | cancelled | Menomonie signed an NDA with Balloonist LLC in February 2024, over a year before announcing the $1.6B data center proposal in July 2025. Over the following six months, residents… | ||
Project Nova Microsoft |
Village of Caledonia WI |
900 | cancelled | Microsoft cancelled its 244-acre, 900 MW Caledonia data center (Project Nova) after a 2,000-signature petition and strong community opposition forced a rethinking of the plan.… | ||
Stargate / The Barn Related Digital / Oracle |
Saline Township Planning Commission MI |
1,400 | denied | After an August 5, 2025 first public hearing dominated by opposition, the Saline Township Planning Commission tabled Related Digital's 'conditional rezoning' application for 575… | ||
Duke Energy gas turbine proposal near Amazon data center Duke Energy |
Hamlet, NC NC |
denied | NC regulators denied Duke Energy’s $584 million gas turbine proposal near Hamlet, citing unanswered questions about data center demand and who would pay for the project. The… | |||
Project Taurus Raeden |
Colorado Springs CO |
delayed | Colorado Springs City Council voted to postpone a decision on the Project Taurus data center near Garden of the Gods after a daylong hearing with public comment. The delay… | |||
American Tower Corporation Pike Township (Indianapolis withdrawal) American Tower Corporation |
Pike Township (Indianapolis withdrawal) IN |
4 | cancelled | American Tower Corporation withdrew its rezoning petition for a proposed 20,000-square-foot data center near W. 79th Street and Township Line Road in Pike Township, Indianapolis,… | ||
Headwaters Site Development LLC Fauquier County (Catlett Station) Headwaters Site Development LLC |
Fauquier County (Catlett Station) VA |
cancelled | Headwaters Site Development LLC withdrew its rezoning application for a $400M, four-building data center on 67 acres at Catlett Road and Gaskins Lane in Fauquier County on July… | |||
Prologis Kosciusko County (Leesburg) Prologis |
Kosciusko County (Leesburg) IN |
denied | Kosciusko County, Indiana, Area Plan Commission unanimously denied (8-0) Prologis's rezoning request for 554 acres of farmland near Leesburg from agricultural to industrial for a… | |||
Oppidan Hampton Oppidan |
Hampton MN |
cancelled | Oppidan, an Excelsior-based developer, paused its data center project in Hampton after citing that the state would take too long to permit backup generators. Minnesota's… | |||
NOVEC Prince William County (Diamond Hill substation) NOVEC |
Prince William County (Diamond Hill substation) VA |
300 | denied | Prince William County, Virginia, Planning Commission voted 5-3 on March 11, 2026 to deny the Diamond Hill substation, a proposed 300 MW electric utility substation with a… | ||
Penzance Development / 1500 Gateway LLC Fredericksburg Penzance Development / 1500 Gateway LLC |
Fredericksburg VA |
600 | cancelled | Penzance Development / 1500 Gateway LLC proposed a 600 MW data center on 84 acres in Fredericksburg, Virginia. Residents of the Great Oaks Lane neighborhood objected to the… | ||
B+F Timpanogos Tech City of Provo B+F Timpanogos Tech |
City of Provo UT |
denied | The Provo City, Utah, Council voted unanimously (7-0) on March 11, 2026 to deny a zoning change for a proposed AI data center at 1507 S. 180 East in the East Bay area. Developer… | |||
Google / Microsoft Minnesota (Statewide) Google / Microsoft |
Minnesota (Statewide) MN |
cancelled | Bipartisan bill HF4077/SF4379 to ban local government officials from signing NDAs with data center developers is advancing through both chambers. The Senate version passed two… | |||
JRE Strategies LLC Ardmore JRE Strategies LLC |
Ardmore OK |
10 | cancelled | JRE Strategies LLC withdrew its data center proposal after the Ardmore, Oklahoma, Planning Commission voted 7-0 against rezoning 6.74 acres from single-family residential to… | ||
Project Accelerate Crosland Southeast / Crow Holdings / Engineered Land Solutions |
Matthews NC |
cancelled | Developers proposed a 123-acre data center campus (Project Accelerate) near I-485 and East John Street in Matthews, North Carolina, Mecklenburg County (by Crosland Southeast /… | |||
Rocklocker LLC Kalkaska County Rocklocker LLC |
Kalkaska County MI |
1,000 | cancelled | Rocklocker LLC (headed by Traverse City geologist Matt Rine) proposed a gigawatt-scale hyperscale data center on 1,440 acres of state-owned land near Island Lake and South River… | ||
PW Digital Gateway QTS Realty Trust / Compass |
Prince William County VA |
denied | Circuit Court Judge Kimberly Irving voided the December 2023 rezoning of 2,133 acres for the Prince William Digital Gateway, a multi-gigawatt data center hub by QTS Realty Trust… | |||
Brian O'Neill Properties Plymouth Township Brian O'Neill Properties |
Plymouth Township PA |
cancelled | Developer Brian O'Neill sought a zoning exception to convert the shuttered 66-acre Cleveland-Cliffs steel mill near Conshohocken into a 2M sq ft, 10-building AI data center in… | |||
Project Scott Provident Realty Advisors |
Archbald Borough PA |
denied | Council voted down Provident Realty Advisors' application to build a giant data center after months of growing outcry. About 200 residents showed up wearing yellow shirts.… | |||
Apple Valley Technology Park Oppidan Investment Company / Rockport LLC |
Apple Valley MN |
denied | Apple Valley, Minnesota, Planning Commission recommended denial on March 18, 2026 of three key components of the Apple Valley Technology Park data center project: the Preliminary… | |||
Green Chile Project (gas pipeline for Project Jupiter) Energy Transfer / Transwestern Pipeline Company |
Dona Ana County (Project Jupiter pipeline) NM |
denied | On March 20, 2026, New Mexico Commissioner of Public Lands Stephanie Garcia Richard denied Energy Transfer's application to build a segment of a 17-mile natural gas pipeline… | |||
Project Washington Starwood Digital Ventures |
Delaware (Coastal Zone Appeal) DE |
1,200 | denied | Delaware Coastal Zone Industrial Control Board unanimously upheld DNREC Secretary's decision that 'Project Washington' data center is not allowed under the Coastal Zone Act. The… | ||
Meyer Property Data Center Yorkville Nexus V LLC / Green Door Capital |
Yorkville IL |
cancelled | Yorkville Nexus V LLC / Green Door Capital WITHDREW the 91-acre Meyer Property data center rezoning application on April 14-15, 2026, following the city council's April 1 tabling… | |||
Project Hutto Zydeco Development |
Hutto TX |
70 | cancelled | On April 17, 2026, Zydeco Development withdrew its rezoning application for a proposed 950,000-square-foot data center at the southeast corner of County Road 119 and Limmer Loop… | ||
KRAMBU, Inc. Bonner (Missoula County) KRAMBU, Inc. |
Bonner (Missoula County) MT |
3 | cancelled | KRAMBU, an Idaho-based company, applied to install an AI data center at Bonner Mill Industrial Park at the confluence of the Clark Fork and Blackfoot rivers (the 'A River Runs… | ||
PSEG Frederick / Carroll / Baltimore Counties PSEG |
Frederick / Carroll / Baltimore Counties MD |
delayed | Maryland's PPRP recommended a new October deadline for PSEG to complete its application for the controversial 67-mile transmission line across three counties. Opponents believe… | |||
Outrigger Industrial Washington City Council, IN Outrigger Industrial |
Washington City Council, IN IN |
withdrawn | Washington City Council voted unanimously to cease all dealings with Outrigger Industrial after the developer failed to answer questions about a proposed 1,000,000-gallon/day… | |||
Beale Infrastructure Gardner, KS Beale Infrastructure |
Gardner, KS KS |
withdrawn | Beale Infrastructure pulled its data center proposal after Gardner city council declined tax incentives and ~200 residents from three counties opposed at the council meeting.… | |||
Oracle; OpenAI; Crusoe; Microsoft; NVIDIA Abilene, TX (Oracle/OpenAI drop flagship Stargate Abilene expansion; Meta in talks for Crusoe capacity) Oracle; OpenAI; Crusoe; Microsoft; NVIDIA |
Abilene, TX (Oracle/OpenAI drop flagship Stargate Abilene expansion; Meta in talks for Crusoe capacity) TX |
withdrawn | DCD reported that Oracle/OpenAI dropped plans to expand the flagship Abilene Stargate site further. Meta is in talks (with NVIDIA's help) to pick up Crusoe capacity. Additional… | |||
Lakeland Equity Group Cleveland City Council (1-yr moratorium proposed; Lakeland Equity permit rejected), OH Lakeland Equity Group |
Cleveland City Council (1-yr moratorium proposed; Lakeland Equity permit rejected), OH OH |
denied | Council Member Charles Slife proposed a 1-year data center moratorium to update zoning and define DC scales. Separately, the city rejected the construction permit application for… | |||
Lex Developments Pocatello Lex Developments |
Pocatello ID |
denied | A Pocatello hearing examiner denied a conditional-use permit for a data center on the former Hoku polysilicon site (about $2.26B projected), citing insufficient water and design… | |||
Inch & Co. / Eastern Land & Resources South Annville Township Inch & Co. / Eastern Land & Resources |
South Annville Township PA |
withdrawn | A $1.7B data center project (5 x 150,000 sq ft; developer 1235 Martina Drive Owner LLC / Inch & Co. / Eastern Land & Resources) was scrapped in South Annville Township after… | |||
Brewster Land Company Dorrance Township Brewster Land Company |
Dorrance Township PA |
denied | The Dorrance Township zoning hearing board unanimously denied a challenge (by Brewster Land Company) arguing the township's ordinance unlawfully excluded data centers; an appeal… | |||
AVAIO Digital Pulaski County Quorum Court (data center moratorium ordinance, failed on clerk miscount), AR AVAIO Digital |
Pulaski County Quorum Court (data center moratorium ordinance, failed on clerk miscount), AR AR |
denied | The Pulaski County Quorum Court appeared to pass a one-year data center moratorium on May 26, 2026 (with an exemption carved out for AVAIO Digital's planned Wrightsville… | |||
EdgeConneX (via East Village Dothan LLC) Douglas County Commission EdgeConneX (via East Village Dothan LLC) |
Douglas County Commission GA |
denied | Douglas County Commission voted 4-1 to deny a ~700+ acre, 4.4M sq ft data center campus rezoning. Hyperscaler unconfirmed. The 6-building campus, partly within the Dog River… | |||
Powers Ferry Place Prime Group Holdings |
Marietta City Council GA |
18 | delayed | After a Planning Commission 4-3 recommendation to approve, Marietta City Council tabled Prime Group Holdings' Powers Ferry Place rezoning -- a proposal to convert part of a… | ||
Karis Critical Hoffman Estates Karis Critical |
Hoffman Estates IL |
cancelled | Karis Critical withdrew its rezoning request for the 186-acre Plum Farms property (residential/commercial to manufacturing, to potentially enable a data center) after sustained… | |||
DAMAC Digital Edgerton (DAMAC data center denied; 6-month moratorium also denied), KS DAMAC Digital |
Edgerton (DAMAC data center denied; 6-month moratorium also denied), KS KS |
denied | Two-part Edgerton (KS) action: on June 11, 2026 the Planning Commission DENIED (3-2) Dubai-based DAMAC Digital's ~$860M data center (a conversion of a ~400,000-sq-ft warehouse at… | |||
Project Aquila RCM Hill, LLC |
Hill County (RCM Hill files $100M federal suit challenging data center moratorium), TX TX |
1,235 | cancelled | On May 28, 2026, RCM Hill, LLC sued Hill County, County Judge Shane Brassell, and Commissioners Jim Holcomb and Larry Crumpton in U.S. District Court (Western District of Texas,… | ||
Sanders Lane / Lage Assemblage I LLC Prince William County Board of Supervisors (Dulles South Innovation Center denial) Sanders Lane / Lage Assemblage I LLC |
Prince William County Board of Supervisors (Dulles South Innovation Center denial) VA |
denied | Prince William County Board of Supervisors voted 8-0 to deny the ~1,940-acre, 43M sq ft Dulles South Innovation Center comprehensive-plan amendment after a 5-hour public hearing… | |||
North Carolina |
NC NC |
paused | The article discusses where data center development is paused or banned in western North Carolina. | |||
Iowa Transparency Bill |
Iowa (statewide) IA |
cancelled | Iowa HF 2447, proposed by Rep. Cindy Golding (R-Cedar Rapids), creates new reporting requirements and utility rate structures for data centers. Data centers must file quarterly… | |||
Gigaland Fauquier County (Gigaland) Gigaland |
Fauquier County (Gigaland) VA |
600 | withdrawn | GigaLand withdrew its original datacenter application in Fauquier County, Virginia, after significant community opposition, but resubmitted a scaled-down proposal in early 2026,… | ||
Pennsylvania |
PA PA |
cancelled | As opposition to data centers grows, researchers are exploring the use of Pennsylvania’s abandoned mine lands for potential data center sites. The article discusses the… | |||
Nevada A Texas-based company |
Henderson NV |
withdrawn | A Texas-based company has withdrawn from a proposed hyperscale data center and natural gas plant project on federal land near Henderson, Nevada. The project's status is now… | |||
Chicago |
Chicago IL |
paused | The proposed data center project in Chicago is being paused, which may have financial implications for taxpayers. |
Methodology and scope
This watchlist tracks U.S. data center projects, operators, and jurisdictional actions that carry a documented public paper trail: securities filings, regulatory dockets, litigation, government statements, utility filings, and trade press. It is maintained as a neutral reference. Entries are recorded as observed; the tracker does not rank projects or advocate an outcome.
- Status reflects the most recent public signal for each entry. Where a project continues on schedule, that is recorded as plainly as a delay.
- Capacity is shown in megawatts where reported, and left blank where not disclosed.
- Local restrictions, utility dockets, lawsuits, and federal actions are drawn from primary filings and reputable outlets, each linked to its source.
- The ERCOT queue snapshot is extracted directly from the ERCOT GIS Report.
- Signals are collected on a recurring basis and reconciled into a single source of truth before publication.
Every citation on one page: Sources and citations. Companion policy map: SAVRN Data Center Moratorium Tracker. Capital side: North American Data Center Capital Atlas. Founder essay: The Queue Was the Fiction.
Seven references, one system
Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.
What is the Nationwide Data Center Delay Watchlist?
It is a continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Each entry links to its documented public source, and it is maintained as a neutral reference.
How is a project's status determined?
Status reflects the most recent public signal for each entry: halted, delayed, cancelled, pending review, litigation active, audit paused, under appeal, or withdrawn. Where a project continues on schedule, that is recorded as plainly as a delay.
How are delay days measured?
Delay days are measured against the original announced target where available, or against the first documented delay date.
How often is the watchlist updated?
Signals are collected on a recurring basis from SEC EDGAR and trade-press feeds and reconciled into the single source of truth before publication.
How is this different from the Data Center Moratorium Tracker?
The Moratorium Tracker maps state and local policy measures. This watchlist tracks named projects, operators, public-company exposure, and securities filings, with delay status and cause for each. The two are companion references.
Nationwide Data Center Delay Watchlist
Get these tracker updates by email
A short introduction on days 3, 7 and 14, plus updates for this tracker. Unsubscribe at any time.
We use your address to send the introduction and updates described above. See our Privacy Policy.