SAVRN Research · Living watchlist

Nationwide Data Center Delay Watchlist

A continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, local restrictions, litigation, federal and utility dockets, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Every entry links to its documented public source.

Updated 2026-09-28 Live · sources checked 52 min ago · 16 of 18 sources answered · 52 entries added in the last 7 days · last change 2026-10-03 Version 2.0.0 Coverage from 2024-01-01 Compiled by SAVRN Research
Scale model of a data center campus on a white plan: completed halls, cooling plant, and electrical substation rendered in copper, with queued future phases drawn as blueprint outline and a construction crane standing still
A data center campus rendered as a plan: completed structures shown built, queued phases shown as outline. The watchlist records which projects have moved and which are on hold.
Tracked projects
344
delayed, cancelled, or under review
Local restrictions
1150
county, city, township measures
Utility actions
272
PUC dockets and statements
Active lawsuits
63
filed or in progress
Stalled since Jan 2024
$170B+
across 20 states (Carbon Direct)
Q1 2026 delayed / cancelled
$130B
75 projects (Fortune)
ERCOT capacity at risk
49.8 GW
$8B–$15B revenue (BNEF)
Transformer lead time
128 wks
large power, average

National interconnection queue

Every ISO plus vertically integrated utilities with a public row-level queue, as of 2026-09-28. The full row-level queue is refreshed weekly. ERCOT Batch Zero row-level classifications are not yet published per Market Notice M-A080326-01.

32,382
Total queue rows
4,445 GW
Total capacity requested
46
Rows flagged data center
92
Large-load / DC studies
By status
Withdrawn15,338
IA signed8,099
Active4,163
Unknown2,003
Other1,978
Study706
Suspended95
By source, ISO and utility
PJM9,263
Alliant Energy6,968
MISO3,873
CAISO2,281
Dominion Energy VA2,178
NYISO2,148
ERCOT2,003
ISO-NE1,751
SPP1,028
Ameren Illinois146
AEP Indiana Michigan91
Consumers Energy88
Evergy Kansas88
AEP PSO80
AEP Ohio72
We Energies58
PacifiCorp56
AEP SWEPCO47
Evergy Missouri40
El Paso Electric39
AEP APCo34
MidAmerican Energy32
Ameren Missouri18

Would you like the weekly update?

Every week we re-verify every project on this watchlist and publish what moved. You get one email when it goes out.

Also send me

Receive a short introduction on days 3, 7 and 14, plus the updates you select. Unsubscribe in one click. Privacy ·

You're on the list. The next weekly update will land in your inbox when it publishes.
You are subscribed. Read the latest tracker

Browse a section below. Download the full dataset (JSON) or review all sources and citations.

Tracked projects

Named data center projects with a documented delay, cancellation, withdrawal, or active review. Status reflects the most recent public signal.

ProjectLocationMWStatusCauseNotesSources
Diode Ventures Cedar Creek Lake
Diode Ventures
Cedar Creek Lake
TX · ERCOT
withdrawn
state moratorium
Pre-moratorium withdrawal, cited by Governor's office as example
Project Matador (Amarillo)
Fermi America (FRMI)
Amarillo / Potter County
TX · ERCOT
11,000 delayed
transformer supply
11 GW at build-out; 600 MW gas turbines procured; 1 GW target by end of 2026. Not affected by moratorium (BTM). Continuing construction.
GW Ranch (Fort Stockton)
Pacifico Energy
Fort Stockton
TX · ERCOT
5,000 delayed 5 GW off-grid gas + 1.8 GW battery. Bypasses ERCOT entirely. Not affected by moratorium.
Amazon 7.65 GW Gas Plant / Self-Contained Island
Amazon Web Services / partner (AMZN)
TX
TX · ERCOT
5,000 delayed 35 turbines, 5 GW campus delivery, operates as self-contained energy island off ERCOT. Announced days AFTER moratorium, no delay impact.
Stargate / Abilene (Phase 1)
Crusoe (MSFT,ORCL)
Abilene
TX · ERCOT
1,200 delayed 900 MW BTM gas microgrid + grid blend at 1.2 GW. Continuing. Additional 4.5 GW gas capacity secured by Crusoe.
Good Data Center Campus (Armstrong County)
Google (via developer) (GOOGL)
Armstrong County
TX · ERCOT
delayed Private natural gas turbines under state air permit. Not affected by moratorium.
Voltagrid Shackelford County
Voltagrid (ORCL)
Shackelford County
TX · ERCOT
700 delayed
gas pipeline delay
210 industrial gas gensets. 700 MW. Off-grid. Delayed to 2029 per SemiAnalysis due to gas pipeline permitting.
Oracle/OpenAI Texas Expansion (Original Plan)
Oracle (ORCL)
TX
TX · ERCOT
withdrawn
corporate realignmentfinancing
Oracle/OpenAI abandoned Texas expansion March 6, 2026 over financing negotiations. Pre-moratorium. Microsoft later stepped in.
CleanSpark Texas Operations (all)
CleanSpark (CLSK)
TX
TX · ERCOT
pending review
ERCOT moratorium
10-Q risk factor disclosure: 'evaluating scope and enforceability of August 3, 2026 letter'. Only known public SEC disclosure explicitly referencing the moratorium.
Lighthouse (Port Washington)
Vantage Data Centers / Oracle / OpenAI (ORCL)
Port Washington
WI · MISO
litigation active
environmental reviewlitigationcommunity opposition
$15B project. Sierra Club/Midwest Environmental Advocates lawsuit filed July 10, 2026 in Ozaukee County. Also April 2026 ballot referendum limited DC construction.
Spring Valley Technology Park
Active Infrastructure
Loudoun County / near Beaverdam Reservoir
VA · PJM
780 cancelled
zoning denialcommunity oppositionwater dispute
325-acre, 3.54M sq ft. Planning Commission voted unanimously to recommend denial. 500+ residents attended hearing.
Dulles Cloud South
Prince William County
VA · PJM
cancelled
zoning denialcommunity opposition
Nearly 2,000-acre campus. Board of County Supervisors voted unanimously to deny rezoning.
Mountain Road Technology Park
Tract
Hanover County
VA · PJM
cancelled
zoning denialwater disputecommunity opposition
Board of Supervisors voted 4-3 to deny rezoning. Water concerns (up to 90% of local supply).
Prince William 2,100-acre Campus (37 buildings)
Prince William County
VA · PJM
cancelled
zoning denialcommunity opposition
37 buildings, gigawatt-scale; killed on public-notice technicality (notices not run 6 days apart)
Project Blue (Amazon-linked)
Beale Infrastructure (AMZN)
Tucson
AZ · WECC
cancelled
zoning denialwater disputecommunity opposition
City Council voted 7-0 to end negotiations and halt annexation.
New Carlisle $13B Data Center
St. Joseph County / New Carlisle
IN · MISO
cancelled
community oppositionzoning denial
St. Joseph County Council rejected after 10-hour meeting.
Hobart Amazon Data Center
Amazon (AMZN)
Hobart
IN · MISO
litigation active
litigationcommunity opposition
Lawsuit filed to block fill permit alleging state law violations
Project Tango
Palm Beach County / Arden
FL · SERC
cancelled
community oppositionwater disputezoning denial
Palm Beach commissioners voted 5-1 to deny after 12+ hour meeting.
Pine Island Data Center Development
Pine Island
MN · MISO
litigation active
environmental reviewlitigation
TRO issued blocking construction pending MCEA challenge. Construction was to begin July 2026.
T5 @ Chicago IV
T5 Data Centers
Lake County / Grayslake
IL · PJM
litigation active
litigationcommunity oppositionzoning denial
Lawsuit filed July 31, 2026 alleging inconsistent with Comprehensive Plan. Initial status hearing Oct 30.
Markley Group Lowell Expansion
Markley Group
Lowell
MA · ISO-NE
litigation active
litigationenvironmental review
MA Superior Court blocked installation of 4 new diesel generators pending resident lawsuit.
Hexa Builders Monroe Township
Hexa Builders LLC
Monroe Township / Gloucester County
NJ · PJM
litigation active
zoning deniallitigation
Hexa filed $300M lawsuit against township for zoning ordinances banning DCs.
DC BLOX Nashville (Grassmere Park)
DC BLOX
Nashville / Grassmere
TN · SERC
litigation active
local moratoriumlitigation
Filed federal lawsuit Aug 11 challenging Nashville moratorium. Claims vested rights.
Imperial Valley $10B AI Data Center
Imperial Valley Computer Manufacturing LLC
Imperial
CA · CAISO
litigation active
litigationpermit denial
$10B project. Civil rights lawsuit filed against City of Imperial in fed court.
Natelli Investments Wake County 250MW
Natelli Investments
Wake County
NC · PJM
250 withdrawn
community oppositionzoning denial
Withdrew annexation and rezoning applications early 2026.
Hays County / San Marcos DC
Hays County / San Marcos
TX · ERCOT
cancelled
zoning denialwater disputecommunity opposition
San Marcos City Council voted 5-2 against zoning in February 2026.
Eagan Capital Expansion
Eagan Capital
Eagan
MN · MISO
litigation active
local moratoriumlitigation
Filed lawsuit June 15 against Eagan for moratorium exceeding city authority.
DataBank Orangetown Phase 2
DataBank
Orangetown / Orangeburg
NY · NYISO
delayed
environmental reviewcommunity opposition
Orangetown Planning Board voted unanimously to require EIS, delaying project indefinitely.
Boulder City BLM Site
Boulder City
NV · WECC
under appeal
water disputecommunity opposition
Boulder City Council voted unanimously to appeal BLM approval.
University of Michigan / Los Alamos Data Center
Ypsilanti
MI · MISO
delayed
water disputelocal moratorium
Ypsilanti Community Utilities Authority passed yearlong halt on water/sewer for DCs (April 2026)
Prince William Digital Gateway (PW Digital Gateway)
QTS Data Centers (Blackstone); Compass Datacenters (BX)
Gainesville, Prince William County
VA · PJM
1,700 cancelled
litigationzoning denialcommunity opposition
One of the world's largest planned data center clusters (34 buildings, 22M SF) next to Manassas National Battlefield Park was voided by courts over inadequate public notice for…
Dulles Cloud South (Dulles South data center project)
Gainesville, Prince William County
VA · PJM
cancelled
zoning denialcommunity opposition
Nearly 2,000-acre, 43M-SF proposal to rezone farmland/residential land to industrial for data centers was rejected 8-0 by the Prince William Board of Supervisors, following on…
Bristow Campus data center project
Stack Infrastructure
Bristow/Nokesville area, Prince William County
VA · PJM
delayed
community opposition
Board of Supervisors hearing on this Nokesville Road/Broad Run Creek campus was deferred amid community opposition; a supervisor said backers "know they don't have the votes."
PW Digital Gateway landowner tax litigation
QTS Data Centers (BX)
Gainesville, Prince William County
VA · PJM
litigation active
litigation
Landowners under contract to sell parcels to QTS for the Digital Gateway sued Prince William County over sharply increased tax assessments tied to the (litigation-blocked)…
Loudoun County data center application pause
Loudoun County
VA · PJM
pending review
local moratoriumcommunity opposition
Board of Supervisors voted to begin process of pausing all new data center applications, site plans and substations countywide (250 existing data centers, 53.3M SF) until new…
Hiddenwood Lane / Hiddenwood Assemblage rezoning (Aldie)
JK Technology Holdings / Aldie homeowner group
Aldie, Loudoun County
VA · PJM
withdrawn
community oppositionzoning denial
Group of Aldie homeowners on Hiddenwood Lane seeking industrial rezoning (756,000 SF data center potential) to sell out of an area surrounded by data centers indefinitely…
Innovation Gateway
Sterling, Loudoun County
VA · PJM
pending review
zoning denial
700,000 SF data center plus affordable-housing rezoning near the Innovation Station Metrorail stop; Planning Commission recommended denial (5-2) as incompatible with the Urban…
Oaklawn data center rezoning (Leesburg)
Oaklawn, LLC
Leesburg, Loudoun County
VA · PJM
cancelled
zoning denial
Leesburg Town Council denied 5-1-1 a rezoning to add up to 450,000 SF of data centers linked to affordable-housing units, citing inconsistency with the Zoning Ordinance and…
Mountain Road Technology Park (Tract)
Tract
Route 33/Mountain Road, Hanover County
VA · PJM
900 cancelled
zoning denialcommunity opposition
Hanover Board of Supervisors rejected the conditional-use permit and A1-to-M1 rezoning for a 900MW/430-acre campus on May 27, 2026, after the Planning Commission had earlier…
Chesterfield Tract data center park (Branders Road)
Tract
161 Branders Road, Chesterfield County
VA · PJM
withdrawn
zoning denialcommunity opposition
Tract withdrew its zoning request for a 744-acre rural campus after the Planning Commission unanimously recommended against it, citing inadequate infrastructure and sole access…
Chesterfield data center project (unnamed) paused amid county lawsuits
Chesterfield County
VA · PJM
litigation active
litigation
Local reporting confirms an active Chesterfield County data center project paused amid county-level lawsuits, following the Zoning Appeals Board's denial of an appeal on a…
Gigaland Data Center Campus
GigaLand LLC
Remington, Fauquier County
VA · PJM
800 withdrawn
zoning denialcommunity opposition
Fauquier Planning Commission voted to recommend denial of the original 800MW/2.2M-SF rezoning; the developer officially withdrew the application in July 2026 and plans a…
Remington Digital Campus
Remington, Fauquier County
VA · PJM
pending review
zoning denialcommunity opposition
Fauquier Planning Commission recommended denial of a separate campus near Remington Technology Park adjoining the Meadows of Remington neighborhood; a related private turbine…
Amazon Data Services Warrenton data center
Amazon Data Services (AMZN)
Warrenton, Fauquier County
VA · PJM
litigation active
litigationcommunity opposition
Citizens for Fauquier County and 10 residents sued in Fauquier Circuit Court to overturn the Town Council's special-use-permit approval for a 220,000 SF Amazon facility, alleging…
Bel Pre Tech Park (Brandy Station data center campus)
Culpeper Acquisitions LLC
Brandy Station, Culpeper County
VA · PJM
pending review
zoning denialcommunity opposition
County planners denied the 4.6M-SF, nine-building rezoning application near the historic Brandy Station battlefield; applicant requested Board of Supervisors consideration be…
Brandy Station data center proposal (David Martin parcel)
Brandy Station, Culpeper County
VA · PJM
withdrawn
zoning denialcommunity opposition
An 88-acre Brandy Station rezoning was withdrawn after an initial denial from the Culpeper County planning commission amid Brandy Station resident opposition.
Red Ace Data Center Campus
Culpeper County
VA · PJM
delayed
zoning denial
Application tabled by Culpeper County officials, per Data Center Dynamics reporting; no further detail on eventual outcome.
Stafford County stricter data center rules (GWV Data Center reclassification context)
Stafford County
VA · PJM
delayed
zoning denialcommunity opposition
Following a marathon public hearing, Stafford County adopted stricter data-center zoning rules that developers and residents split over, raising the bar for future rezoning…
Spotsylvania County data center special-use permit standards / statewide moratorium resolution
Spotsylvania County
VA · PJM
pending review
zoning denialcommunity oppositionstate moratorium
Spotsylvania supervisors split on requiring special-use permits for data centers (March 2025) and by August 2026 the Board backed a call for a statewide moratorium on data…
1500 Gateway Data Center Project
Penzance Development / 1500 Gateway Venture, LLC
City of Fredericksburg
VA · PJM
under appeal
zoning denialcommunity opposition
Fredericksburg Planning Commission unanimously rejected (7-0) the 2.1M-SF rezoning and Special Use Permit in December 2025, its second denial after an initial February 2025…
Emerald Lakes Estates data center (Great Bridge)
Doug Fuller / Emerald Lakes Estates
Great Bridge, City of Chesapeake
VA · PJM
cancelled
zoning denialcommunity opposition
Would have been Hampton Roads' first major data center; Chesapeake City Council unanimously denied the agricultural-to-light-industrial rezoning for a 350,000 SF facility on…
Chesapeake 8-month data center application pause
City of Chesapeake
VA · PJM
pending review
local moratoriumcommunity opposition
Chesapeake City Council voted to approve an 8-month hold on all new data center application decisions amid growing calls for a statewide Virginia moratorium.
Chesapeake data center zoning text amendment (Green Sea area)
City of Chesapeake
VA · PJM
delayed
zoning denialcommunity opposition
Chesapeake Planning Commission recommended against a data-center zoning text amendment in May 2025; a related zoning text amendment was indefinitely continued by the Planning…
Mt. Airy Planned Innovation, Research and Technology data center campus
VALCO (applicant); Thompson Family Office (landowner)
Ruther Glen/Jericho Road, Caroline County
VA · PJM
withdrawn
zoning denialcommunity opposition
Caroline County Board of Supervisors denied 5-1 a comprehensive-plan amendment for a 900-acre campus near the North Anna River; VALCO then withdrew its rezoning request. The…
Google Botetourt County data center campus
Google (GOOGL)
Botetourt County
VA · PJM
litigation active
litigationwater dispute
Western Virginia Water Authority stated it will not supply the 10-million-gallons/day Google sought; a FOIA lawsuit forced disclosure of secret water-use contracts (judge ordered…
Campbell County data center rezoning (MESH Capital site)
MESH Capital LLC
Concord District, Campbell County
VA · PJM
cancelled
zoning denialcommunity opposition
Campbell County Board of Supervisors voted 5-2 to reject removing 2000-era protective conditions from a 57-acre site marketed for up to three data centers, after dozens of…
Surry County data center moratorium
Surry County
VA · PJM
pending review
local moratorium
Surry County enacted an initial 60-day pause on data center approvals in June 2026, then extended it to a full two-year moratorium on July 21, 2026, while directing staff to…
Powhatan County data center zoning proposal (Route 60/Page Road)
Newport Equities / JMS Investments
Powhatan County
VA · PJM
delayed
community opposition
A community petition ("Preserve Powhatan") urged the Planning Commission to block a 120-acre data-center zoning proposal near the Chesterfield County line; the Board of…
Amazon Louisa County data center (third project, cancelled)
Amazon (AMZN)
Louisa County
VA · PJM
cancelled
community opposition
Amazon pulled a proposed third Louisa County data center project in July 2025 after strong community resistance, even as it continued building two other campuses in the county.
Amazon Louisa County data center campus (Northeast Creek overlay, active construction)
Amazon (AMZN)
Louisa County
VA · PJM
litigation active
litigation
Homeowner Austin Newsom sued Amazon for private nuisance over brown water, dust and construction noise at Amazon's second Louisa County campus; a federal judge allowed the…
Amazon Birchwood power plant data center campus
Amazon (AMZN)
Sealston, King George County
VA · PJM
litigation active
litigationzoning denial
Board of Supervisors moved in April 2024 to re-rezone the old Birchwood power plant site back to agricultural, threatening Amazon's planned 19-building, 7.25M SF campus; Amazon…
New Kent County data center-friendly technology overlay district
New Kent County
VA · PJM
cancelled
community opposition
Faced with widespread public disapproval at town-hall meetings, New Kent County supervisors spiked the plan to create a data-center-friendly overlay zone in July 2026,…
Plaza 500 data center campus / Edsall Data Center Substation 2232
Starwood Capital Group (Starwood Digital Ventures)
Lincolnia, Fairfax County
VA · PJM
pending review
community opposition
Alexandria City Council formally asked Fairfax County to deny the Edsall Road substation feeding this 226,469 SF Starwood data center near the Bren Mar neighborhood; Rep. Don…
Manassas National Battlefield adjacent data center litigation (American Battlefield Trust)
QTS / Compass Datacenters (BX)
Manassas/Gainesville, Prince William County
VA · PJM
cancelled
litigationenvironmental review
American Battlefield Trust sued to stop data center construction abutting Manassas National Battlefield Park; after a judge initially dismissed part of the suit (Nov 2024), the…
Brightseat Tech Park (former Landover Mall site)
Brightseat Associates LLC (Lerner Enterprises / The Tower Cos.)
Landover, Prince George's County
MD · PJM
820 pending review
local moratoriumcommunity opposition
Despite securing final approvals for 4.1M SF of data centers in Oct 2024, County Executive Aisha Braveboy ordered a temporary halt to all data center permitting on Sept 15, 2025…
Prince George's County Qualified Data Centers moratorium (Brandywine area)
Brandywine, Prince George's County
MD · PJM
pending review
local moratoriumcommunity opposition
Prince George's County Council initially voted against advancing data centers (Nov 2024) and enacted a countywide moratorium on "Qualified Data Centers" extended to expire June…
Quantum Frederick
Frederick County
MD · PJM
litigation active
litigationlocal moratoriumcommunity opposition
Maryland Supreme Court blocked a citizen-driven referendum bid seeking to overturn a county ordinance that expanded the ~1,600-acre Quantum Frederick campus by 1,000 acres to…
Charles County Zoning Text Amendment 25-187 (data center zoning enablement)
Charles County
MD · PJM
withdrawn
zoning denialcommunity opposition
Charles County Planning Commission twice recommended denial of ZTA 25-187, which would have permitted data centers in industrial zones, after hearings featuring "no data centers"…
Penzance Bedington data center campus
Penzance Management
Bedington, Berkeley County
WV · PJM
delayed
community opposition
Gov. Patrick Morrisey announced the $4B, 500+ acre Penzance data center near the Potomac River on Feb 26, 2026; more than 300 residents packed a March 20 county commission town…
Jefferson County (WV) data center moratorium
Jefferson County
WV · PJM
pending review
local moratoriumcommunity opposition
Jefferson County Board of Commissioners issued a 10-month moratorium (May 19, 2026) on new data center applications/rezonings, excepting sites already zoned via Planned…
Microsoft New Albany / Heath / Hebron Licking County data center campuses
Microsoft (MSFT)
New Albany, Heath, Hebron, Licking County
OH · PJM
delayed
community opposition
Microsoft paused all three Licking County data center sites (New Albany, Heath, Hebron; $1B combined, 700+ acres) in April 2025 while "evaluating sites in line with our…
Amazon Data Services Sunbury data center campus
Amazon (AMZN)
Sunbury, Delaware County
OH · PJM
pending review
local moratoriumcommunity opposition
Sunbury has an active data center development moratorium (through Jan 31); residents are gathering signatures for a city charter amendment capping data center peak load at 25MW…
Aligned Data Centers Pataskala facility
Aligned Data Centers
Pataskala, Licking County
OH · PJM
200 delayed
community opposition
Pataskala residents are collecting signatures for a municipal charter amendment capping data center peak load at 25MW, aimed squarely at blocking this proposed 200MW/89-acre…
Pennhurst data center (East Vincent Township)
Pennhurst Holdings LLC
East Vincent Township, Chester County
PA · PJM
under appeal
zoning denialcommunity oppositionlitigation
East Vincent Township officials unanimously rejected a 1.9M-SF data center on the historic Pennhurst State School site; the developer plans to appeal to the Chester County Court…
East Whiteland data center (Chesco)
East Whiteland Township, Chester County
PA · PJM
litigation active
litigationcommunity opposition
A controversial 1.6M-SF data center in East Whiteland faced community legal challenges over its approval; the project survived a court denial of the challengers' appeals in June…
North Coventry boutique data center (Envision Land Use)
Envision Land Use
North Coventry Township, Chester County
PA · PJM
cancelled
community oppositionzoning denial
North Coventry Township supervisors preemptively voted 3-2 to reject a proposed 120,000 SF data center near a PECO substation before a formal application was even filed,…
Chester County temporary data center moratorium
Chester County
PA · PJM
pending review
local moratorium
Chester County approved a temporary countywide moratorium on new data center project approvals to allow time for zoning study and regulation drafting.
King of Prussia data center campus (Brian O'Neill applications)
Brian O'Neill
Upper Merion Township, Montgomery County
PA · PJM
litigation active
litigationcommunity opposition
Developer Brian O'Neill sued Upper Merion Township; a Montgomery County judge issued an injunction (Aug 13, 2026) preventing the township from taking further action on his King…
Keystone Trade Center AI data center campus (Amazon/NorthPoint)
NorthPoint Development
Falls Township, Bucks County
PA · PJM
delayed
community opposition
Despite construction proceeding on the former U.S. Steel site (part of a $20B statewide Amazon investment), Falls Township residents organized a nearly 4,000-signature petition…
Northampton County proposed data center farm conversions
Northampton County
PA · PJM
delayed
community opposition
Northampton County residents packed public meetings voicing fierce opposition ("I don't want you") to proposed data centers taking over farmland; a local coordinated "No Data…
Homer City Energy Campus
Homer City Redevelopment / Homer City Generation
Homer City, Indiana County
PA · PJM
4,400 pending review
environmental review
Pennsylvania DEP fast-tracked and approved an air-quality permit (157 days vs. the projected 285) for this 4.4GW gas-fired data center campus at a former coal plant despite 500+…
New Hill Digital Campus
Natelli Holdings (Natelli Investments LLC)
New Hill/Apex, Wake County
NC · SERC
300 withdrawn
community oppositionzoning denial
Developer withdrew annexation and rezoning applications for a 300MW campus near the Shearon Harris Nuclear Plant after a 2,000+ signature petition and intense resident backlash…
Triangle Innovation Park West (TIP West)
Eco TIP West LLC (Kirk Bradley / Lee-Moore Capital)
Moncure, Chatham County
NC · SERC
750 litigation active
litigationlocal moratorium
Chatham County's 12-month moratorium on new data center/crypto-mine permits (adopted Feb 11, 2026) halted processing of TIP West's site plan; Eco TIP West sued the county in…
Chatham County data center and crypto-mine moratorium
Chatham County
NC · SERC
pending review
local moratorium
Chatham County commissioners unanimously approved a 12-month moratorium on new data center and cryptocurrency-mine permits (through February 2027) to draft new zoning rules and…
Gates County data center moratorium
Gates County
NC · SERC
pending review
local moratorium
Gates County's board of commissioners unanimously approved a one-year pause on new data center approvals amid growing statewide North Carolina opposition to hyperscale projects.
Person County Microsoft data center
Microsoft (MSFT)
Person County
NC · SERC
delayed
community opposition
Person County residents publicly demanded answers from Microsoft over a planned local data center; Microsoft hosted a community meeting in June 2026 amid rising central-NC…
Hexa Builders Monroe Township data center (Black Horse Pike redevelopment)
Hexa Builders LLC
Williamstown, Monroe Township, Gloucester County
NJ · PJM
litigation active
zoning deniallocal moratoriumlitigationcommunity opposition
After winning preliminary approval for two warehouses in January 2026, Hexa amended its application to swap in a 1M-SF data center; Monroe Township passed ordinances in April…
Former Newton Airport site data center proposal
Andover Township, Sussex County
NJ · PJM
litigation active
local moratoriumlitigation
A developer sued Andover Township in state Superior Court (filed July 10, 2026) to overturn its data-center ban, alleging officials enacted the prohibition preemptively before…
James City County data center special-use review policy
James City County
VA · PJM
pending review
zoning denial
James City County supervisors moved to require special-use permit review for all data centers rather than by-right development, directing staff to draft a formal policy…
Frederick County (VA) countywide data center ban consideration
Frederick County
VA · PJM
pending review
local moratoriumcommunity opposition
Frederick County supervisors moved to consider a countywide ban on new data centers, following sustained opposition from Winchester-area residents citing six proposed projects;…
DC Blox Indianapolis (Warren Township)
DC Blox
Warren Township, Indianapolis (Marion County)
IN · MISO
approved but citywide moratorium pending
community oppositionproposed moratorium
One of three Indianapolis data centers drawing the most community opposition (energy, water, noise). Approved in July 2026 and would be exempt from the moratorium the City-County…
Metrobloks Martindale-Brightwood
Metrobloks
Martindale-Brightwood, Indianapolis (Marion County)
IN · MISO
approved but citywide moratorium pending
community oppositionproposed moratorium
Approved in May 2026 despite opposition; cited as one of three Indianapolis projects driving the citywide moratorium push.
Sabey Data Center (Decatur Township)
Sabey Data Centers
Decatur Township, Indianapolis (Marion County)
IN · MISO
approved but citywide moratorium pending
community oppositionproposed moratorium
Metropolitan Development Commission approved the $4B Sabey project in March 2026; one of the three flashpoint projects behind Indianapolis's moratorium debate.
Google Franklin Township Campus (withdrawn)
Google (GOOGL)
Franklin Township, Indianapolis (Marion County)
IN · MISO
withdrawn
community oppositionrezoning denial or withdrawal
Google withdrew a proposal to rezone hundreds of acres in Franklin Township for a data center campus after contested opposition to the rezoning.
New Carlisle $13B Data Center (St. Joseph County)
Amazon (reported) (AMZN)
New Carlisle, St. Joseph County
IN · MISO
rezoning denied
rezoning denialcommunity opposition
St. Joseph County Council voted 7-2 after a 10-hour, marathon meeting to deny rezoning ~1,000 acres of farmland off Chicago Trail. Opposition cited environmental impact,…
Hobart Amazon Data Center Campus
Amazon (AMZN)
Hobart (Lake County), Ross Township
IN · MISO
active litigation
litigationpermit challenge
Hobart Plan Commission approved a fill permit Nov 6, 2025 for a 725-acre Economic Redevelopment Area near wetlands by Deep River. Residents sued alleging permit issued without…
Microsoft Granger Data Center
Microsoft (MSFT)
Granger, St. Joseph County
IN · MISO
approved amid opposition
community opposition
Approved Microsoft project in St. Joseph County drew continued resident protests at an open house over energy, water, and jobs concerns even after approval, part of broader…
301 Digital Crossroads / CoreWeave (Hammond)
CoreWeave / Decennial Group (CRWV)
Hammond
IN · MISO
development agreement expired
missed milestonesfinancing delay
City of Hammond announced the expiration of the $7B Development Agreement at 301 Digital Crossroads after required milestones were not met by the June 30, 2026 deadline; two…
Clinton County Data Center / Precast Plant / Hydroponic Farm
Unnamed developer
Clinton County
IN · MISO
rezoning denied
rezoning denialunresolved commitments
Clinton County Board of Commissioners voted 3-0 to deny rezoning ~714.55 acres from A-1 agricultural to I-1 light industrial for a mixed data center, precast plant, and…
Boone County Unincorporated Data Center Moratorium
Boone County (unincorporated)
IN · MISO
moratorium in force
county moratorium
Boone County Board of Commissioners unanimously approved a one-year moratorium (effective June 16, 2026 to June 15, 2027) on new data center development in unincorporated Boone…
Madison County Data Center Moratorium (extended)
Madison County
IN · MISO
moratorium extended
county moratorium
Madison County commissioners unanimously extended a data-center moratorium to a full year to draft zoning rules, potentially including a permanent ban. Majority of residents at…
Meta New Albany Data Center (Socrates South / AEP substation dispute)
Meta (META)
New Albany, Licking County
OH · PJM
250 regulatory approval pending
regulatory reviewpower allocation dispute
Meta sought to draw 120-250MW from an idle AEP Ohio substation originally built for Intel's delayed chip fab (Intel now slated 2030-31, delayed from original date). AEP Ohio and…
Microsoft Licking County Data Center (construction paused)
Microsoft (MSFT)
Licking County
OH · PJM
construction paused
corporate reassessmentopenai relationship changetariff costs
Microsoft halted early-stage construction on a $1B Ohio site (three parcels; two reserved for farmland), citing reassessment of cloud/AI infrastructure needs, evolving…
Amazon Data Services Sunbury Campus
Amazon (AMZN)
Sunbury, Delaware County
OH · PJM
proposed amid local moratorium and ballot fight
local moratoriumballot initiative threat
Sunbury has a data-center development moratorium in place until Jan 31 (2027); residents fear council could approve the $2B Amazon facility once it expires and are collecting…
Conserve Ohio Statewide Data Center Ban Ballot Initiative
Statewide (Ohio)
OH · PJM
signature gathering
ballot initiative threatstatewide moratorium push
Ohio Ballot Board approved a proposed constitutional amendment to prohibit large data center construction; Conserve Ohio needed 413,487 signatures from 44+ counties by July 1,…
Lighthouse Campus (Port Washington), Oracle/Vantage/OpenAI
Oracle / Vantage Data Centers (ORCL)
Port Washington, Ozaukee County
WI · MISO
1,000 active litigation
litigationenvironmental review challengeregulatory collateral dispute
Nearly 1GW Stargate-partnership campus. Wisconsin PSC's April 2026 order required hyperscale operators (incl. Oracle) to post financial security before power service; estimated…
Microsoft Mount Pleasant AI Campus (Foxconn site)
Microsoft (MSFT)
Mount Pleasant, Racine County
WI · MISO
construction partially paused
corporate reassessmentdesign changes
Built on former Foxconn site; total footprint ~1,121 acres across three parcels (215, 115, 791 acres); Microsoft now owns ~1,900 acres in Mount Pleasant. Microsoft paused…
Microsoft Kenosha Data Center (proposed)
Microsoft (MSFT)
Kenosha, Kenosha County
WI · MISO
under council consideration
community opposition
Residents packed multiple public forums urging Kenosha Common Council to slow consideration, citing water extraction, 24/7 noise, air quality tied to a linked 1,186 MW…
QTS DeForest / Vienna Annexation ($12B, cancelled)
QTS Data Centers (BAM)
DeForest / Town of Vienna, Dane County
WI · MISO
cancelled
withdrawalvillage infeasibility finding
QTS's $12B proposal required annexing 1,600 acres from the Town of Vienna into DeForest. On Jan 27, 2026 village staff determined the project 'not feasible in DeForest' after ~7…
Pine Island Data Center (Google)
Ryan Companies (developer) (GOOGL)
Pine Island, Goodhue County
MN · MISO
2,700 construction halted by court
litigationenvironmental review inadequate
Could require up to 2,700MW. MCEA sued in October 2025 alleging environmental review only covered a generic 'technology center'/'light industrial' use, not disclosing Google as…
Eagan Capital Expansion (Data Center Moratorium Suit)
Eagan Capital
Eagan, Dakota County
MN · MISO
active litigation
litigationcity moratorium
Eagan's development-pause ordinance (20MW+ new / 9MW+ expansion) is challenged by Eagan Capital, arguing the moratorium exceeds the city's authority; lawsuit filed to void the…
Farmington Technology Park (Tract)
Tract
Farmington, Dakota County
MN · MISO
708 active litigation
litigationenvironmental review challenge
Denver-based Tract's 340-acre, up-to-12-building, 2.5M-sq-ft campus (~$5B at full buildout) on former golf-course/school land. Residents sued on technical and later environmental…
Meta Rosemount Data Center (UMore Park)
Jimnist LLC (Meta subsidiary) (META)
Rosemount, Dakota County
MN · MISO
final decision paused
environmental review pending
Planning Commission approved the site plan, but the City Council paused final action until after Dec 20 pending completion of a required 5-year Alternative Urban Areawide Review…
Minneapolis Citywide Data Center Development Pause
Minneapolis, Hennepin County
MN · MISO
moratorium in force
city moratorium
Minneapolis City Council approved a five-month pause on new data center development (excludes downtown centers under 350,000 sq ft) to study environmental, energy, and…
Elk River Proposed Data Center
Elk River, Sherburne County
MN · MISO
planning commission recommended denial
planning commission denial recommendation
Elk River's planning commission recommended against a proposed data center despite advocates citing an estimated $800,000 in additional city revenue.
Inver Grove Heights Proposed Data Center (Qlevr, former Travel Tags building, Carmen Avenue East)
Qlevr
Inver Grove Heights (Dakota County)
MN · MISO
pending review
local moratoriumlitigation
Qlevr, which proposes a 54,000 square foot data center in the former Travel Tags building, sued the city after it adopted a one-year data center moratorium, saying its…
University of Michigan / Los Alamos High-Performance Computing Facility
University of Michigan / Los Alamos National Laboratory
Ypsilanti Township, Washtenaw County
MI · MISO
100 opposed planned
community oppositioncity council resolution against
144.5-acre site on Textile Road near Ford Lake Dam; $1.2B taxpayer-supported project planned to start construction 2027, operational by 2031. Ypsilanti City Council unanimously…
Saline Township 'The Barn', OpenAI/Oracle Stargate Campus
Related Digital (ORCL)
Saline Township, Washtenaw County
MI · MISO
1,400 rezoning denied then litigation settled
rezoning deniallitigation
Part of OpenAI/Oracle's Stargate initiative; ~1,400MW from DTE Energy; 575 acres of farmland proposed for rezoning within a ~1,000-acre campus (two-thirds to remain open space).…
Alterra Development Marshall Data Center (Brooks Industrial Park)
Alterra Development
Marshall, Calhoun County
MI · MISO
1,000 moratorium delay
city moratoriumcommunity opposition
Alterra purchased 270 acres in Brooks Industrial Park near wetlands/a lake; original concept (gas plant + data center, ~1,000MW/1GW) later dropped the gas plant, cutting energy…
Microsoft / Franklin Partners Covenant Business Park (Lowell-area township)
Microsoft / Franklin Partners (MSFT)
Township adjacent to Lowell (Kent County)
MI · MISO
rezoning paused
community oppositionplanning commission postponement
Estimated $500M-$1B investment over 3-5 years. Site needs rezoning from industrial PUD to light industrial. A December 2025 planning commission public hearing was…
West Michigan Hyperscale Proposals (Solon, Lowell, Gaines Townships)
Solon, Lowell, and Gaines Townships (Kent County)
MI · MISO
opposed proposed
community oppositiontransparency concerns
Residents protested outside The Right Place's Developer Day (June 9-11, 2026) over multiple hyperscale proposals across three townships; criticism centered on private…
Gotion Green Township Battery/Data Plant (abandoned)
Gotion
Green Township, near Big Rapids
MI · MISO
abandoned
litigationcommunity oppositionchina ties backlash
Gotion abandoned its planned Green Township facility after legal challenges, environmental issues, and backlash over the company's China ties; Michigan had committed a $715M…
T5 @ Chicago IV (Grayslake)
T5 Data Centers
Grayslake, Lake County
IL · PJM
1,550 active litigation
litigationwetlands permit suspended
Up to 472 acres within the $750M, 641-acre Cornerstone mixed-use development; ~1.55GW electrical demand from ComEd. Village Board approved between Sept 2024-May 2025. On July 31,…
Project Vector / Endeavour Energy DeKalb Data Center
Endeavour Energy
DeKalb
IL · PJM
opposed pending council vote
community opposition
Also referred to as the 'Edged data center'; ~560 acres along Route 23; Planning and Zoning Commission backed the project after a crowded hearing, but a Change.org petition drew…
South Elgin Data Center (Whiterose Partners / Kenyon Brothers)
Whiterose Partners / Kenyon Brothers Co.
South Elgin, Kane County
IL · PJM
48 opposed effectively stalled
community oppositionpetition campaign
20-acre, 200,000-sq-ft, 48MW proposal at Kenyon Road/Route 25 requiring annexation, rezoning, and special-use permit. A petition gathered 4,800 signatures within 48 hours; a July…
Aurora Data Center and Warehouse Moratorium
Aurora, Kane/DuPage Counties
IL · PJM
moratorium in force
city moratorium
Aurora City Council enacted a 180-day moratorium (Sept 25, 2025) on new data center and warehouse development to research standards and draft zoning rules; applications can be…
Project Cardinal (Yorkville)
Yorkville, Kendall County
IL · PJM
active litigation
litigationpublic notice violation alleged
1,037-acre planned campus, approved earlier in 2026. Residents (Preserve Our Yorkville & Community LLC) sued in April alleging the city failed to give required public notice,…
Project Steel (Yorkville, Eldamain Corridor)
Yorkville, Kendall County
IL · PJM
active litigation
litigationpublic notice violation alleged
Second Yorkville lawsuit, filed by residents including Teska Family Farm, along the Eldamain Corridor; land was annexed/rezoned from residential to manufacturing; suit alleges…
Meyer Project / Yorkville Nexus V LLC Rezoning (withdrawn)
Green Door Capital
Yorkville, Kendall County
IL · PJM
withdrawn
rezoning denialno secured tenantcouncil opposition
~130-acre rezoning request (91 acres west, 37 acres east) south of Project Steel; Planning and Zoning Commission rejected in January 2026; City Council vote postponed in March;…
DC Blox Nashville Zoo-Area Data Center
DC Blox
Nashville, Davidson County
TN · SERC
active litigation
litigationcity moratoriumeminent domain threat
DC Blox filed a federal lawsuit against Metro Nashville after the city stopped processing permits under its temporary data-center moratorium (in effect through December 2026),…
Hillwood Industrial/Data Center Development (Wilson County)
Hillwood
Wilson County
TN · SERC
rezoning rejected moratorium recommended
rezoning denialcounty moratorium recommended
Texas-based Hillwood's proposed 1,380-acre, 10.35M-sq-ft industrial development (no data-center tenant named) near I-40 was rejected by Wilson County commissioners roughly 18…
xAI Colossus 1 & 2 (Memphis)
xAI / SpaceX
Memphis, Shelby County
TN · SERC
active litigation
litigationenvironmental review orderunpermitted power plant
NAACP sued xAI on April 14, 2026 alleging air pollution from unpermitted gas turbines powering Colossus 1/2 in a majority-Black Memphis community; DOJ intervened on xAI's side…
Serverfarm Clarksville ($6.6B)
Serverfarm
Clarksville, Montgomery County
TN · SERC
under construction amid scrutiny
community oppositiontransparency concerns
$6.6B project beside Johnson Regional Medical Center advancing (cranes visible, hillside cleared as of January 2026) despite growing community scrutiny over communication, water…
Douglas County I-20 Data Center Permit Denial (11-building/3-warehouse application)
Douglas County (near I-20 / Carroll County line)
GA · SERC
permit denied
permit denialcommunity oppositioncounty moratorium
Douglas County commissioners voted 4-1 to deny a proposed data center permit near the Carroll County line/I-20 after a packed, contentious commission meeting. Separately, a…
Project Sail (Coweta County)
Prologis / Atlas Development (PLD)
Coweta County (Sargent community, near Newnan)
GA · SERC
900 approved active litigation
county moratoriumlitigationcommunity opposition
Nine-building, 4.34M-sq-ft, ~900MW campus on 829 acres of protected rural conservation land near Georgia Power's Plant Yates. First surfaced Dec 31, 2024; Coweta commissioners…
Project Pegasus (Coweta County)
American Real Estate Partners (backed)
Coweta County
GA · SERC
delayed amid moratorium
county moratoriumcommunity opposition
Second Coweta County data-center proposal (Virginia-based American Real Estate Partners-backed developers) caught in the same 2025 county moratorium and zoning rewrite that…
Newton County Data Center Application Moratorium
Newton County (incl. Covington, Social Circle, Porterdale)
GA · SERC
moratorium in force
county moratorium
Newton County Board of Commissioners unanimously enacted a 30-day moratorium on new data-center applications to update ordinances amid a rapid influx of requests (does not affect…
QTS Atlanta Data Center Expansion (Howell Station, tax break withdrawn)
QTS Data Centers (BAM)
Atlanta, Fulton County (Howell Station)
GA · SERC
tax incentive withdrawn
public outcrytax break withdrawal
Development Authority of Fulton County had considered a $45M tax break for a QTS expansion near the Howell Station neighborhood; the request was withdrawn amid public outcry even…
Project Tango (Palm Beach County)
Palm Beach County (near Arden / Loxahatchee)
FL · FRCC
denied without prejudice
permit denialcommunity opposition
Palm Beach County commissioners denied the hyperscale AI data center 'without prejudice' after nearly 12 hours of debate, meaning the developer may revise and resubmit; site…
XF Group Sarasota County Hyperscale Data Center Freeze
XF Group
Sarasota County (Cattlemen Road)
FL · FRCC
moratorium in force
county moratorium
Sarasota County commissioners voted July 8, 2026 to halt acceptance, review, and approval of hyperscale data centers (50MW+) until at least July 2027 along Cattlemen Road;…
MIA-1 Data Center (Iron Mountain, Westview)
Iron Mountain (IRM)
Westview, unincorporated Miami-Dade County
FL · FRCC
16 under construction amid opposition
community oppositiontransparency concerns
16MW, 150,000-sq-ft, $150M facility on a 3.4-acre industrial site in a predominantly Black community. Approved by-right under existing industrial zoning classified as a…
Alachua Phoenix Commercial Park (rumored data center)
Alachua, Alachua County
FL · FRCC
rumored no application filed
community oppositionmeeting postponed
104-acre Phoenix Commercial Park site east of San Felasco Tech City was listed as a 'high megawatt data center development site' and later relisted as an 'industrial…
Meade County 138-Acre Data Center Rezoning (denied)
Meade County (near Brandenburg)
KY · SERC
rezoning denied
rezoning denialcommunity opposition
138-acre site along Joe Prather Highway; Planning and Zoning Commission voted unanimously against rezoning from agricultural to light industrial and the Fiscal Court agreed with…
Lexington-Fayette Former Lexmark Property Data Center Moratorium
Lexington-Fayette Urban County
KY · SERC
moratorium in force
city moratoriumcommunity opposition
Lexington-Fayette Urban County Government unanimously passed a moratorium on new data center development at a proposed site on the former Lexmark property, effective through…
Burgin / Mercer County Proposed Data Center (draft ordinance pending)
Burgin, Mercer County
KY · SERC
under review no zoning process
community oppositionno local zoning framework
Residents allege developers targeted Burgin because it lacked a formal planning/zoning process; the Mercer County Joint Planning and Zoning Commission was set to discuss a draft…
Meta Hyperion & Evest Data Centers (Richland Parish)
Meta / Entergy (META)
Richland Parish
LA · SERC
5,000 regulatory disclosure dispute
regulatory transparency disputeratepayer cost concerns
Combined Hyperion and Evest campuses represent Meta's >5GW power request, described as the largest in Louisiana history; Entergy proposing 10 new gas plants (3 approved 2025, 7…
xAI Southaven Data Center & Gas Turbine Plant (noise/class action)
xAI / SpaceX (MZX Tech LLC)
Southaven, DeSoto County
MS · SERC
active litigation
litigationunpermitted power plantnoise nuisance
One of three xAI data centers in the Memphis metro built with 57 temporary gas turbines and a permit for 41 additional permanent turbines. Three Southaven residents filed a…
Downtown Kansas City High-Rise Data Center (Quality Hill / Western Newspaper Union Building)
Revitalization Unlimited
Kansas City, Jackson County
MO · SPP
permit denied
permit denialhistoric preservation conflictcommunity opposition
Miami-based developer Revitalization Unlimited proposed a 384-foot, 20-story data center atop the historic Western Newspaper Union building in Quality Hill; Kansas City Plan…
St. Charles County Data Center Moratorium
St. Charles County
MO · SPP
moratorium in force
county moratoriumcommunity opposition
St. Charles County Council unanimously approved a six-month moratorium on new data centers after overwhelming public opposition; County Executive Steve Ehlmann said more research…
Google Stillwater Data Center Campus (up to 6 buildings)
Google (GOOGL)
Stillwater, Payne County
OK · SPP
under construction amid water concerns
community oppositionwater capacity constraints
Google building up to six data centers; first two buildings expected to use ~2.7M gallons/day, rising to 8.1M gallons/day if all six are built (against ~7M gallons/day current…
Project Anthem (East Tulsa)
East Tulsa, Tulsa County
OK · SPP
phase vote delayed
city moratorium partial exemptionplanning commission delay
Tulsa City Council voted unanimously (Mar 25, 2026) for a nine-month citywide data-center construction moratorium; Project Anthem's first and second phases were exempted, but the…
Sand Springs Meta-Backed Data Center
Meta (reported) (META)
Sand Springs, Tulsa County
OK · SPP
opposed proposed
community oppositiontransparency concerns
Tribal advocates and residents protested secrecy around a Meta-backed Sand Springs data center proposal; hundreds attended public meetings opposing the project.
Project Pilot / Beale Infrastructure De Soto Campus
Beale Infrastructure (Mount Sunflower Properties LLC)
De Soto, Johnson County
KS · SPP
approved expanded amid opposition
community oppositionnoise regulation review
Kansas' first hyperscale data center; ~300-acre site near the Panasonic EV battery plant on the former Flint Commerce Center/Ad Astra Park site. De Soto City Council approved the…
Apple Waukee Data Center (extension)
Apple (AAPL)
Waukee, Dallas County
IA · MISO
delayed extension requested
multi year construction delaydesign changes
$1.3B facility (400,000 sq ft) originally due to complete by August 2022; Apple requested a five-year extension to August 2027, citing need for more design/build time. Only…
Linn County Unincorporated Area Data Center Moratorium
Linn County (unincorporated, near Cedar Rapids)
IA · MISO
moratorium in force
county moratorium
Linn County Board of Supervisors approved an 18-month moratorium (2-1 vote, through Jan 1, 2028) for unincorporated county areas to update its data-center ordinance, conduct a…
MidAmerican Energy Salix Data Center Exploration
MidAmerican Energy (BRK.A)
Salix, Woodbury County
IA · MISO
early stage amid county moratoriums
county moratorium neighboring
MidAmerican Energy annexed nearly 1,000 acres of farmland into Salix to explore data center development, even as neighboring Plymouth, Sioux, and Woodbury counties adopted…
NorthMark Strategies / Valara Holdings Computing Center (former Kohler plant)
NorthMark Strategies (Valara Holdings)
Spartanburg County
SC · SERC
450 permitting challenged
regulatory reviewenvironmental petition
$2.8B conversion of a former Kohler kitchen/bath plant (also a longtime bitcoin-mining site) into a computing center. State regulators initially approved ~50MW; company sought to…
Stream Data Centers Marion County (abandoned)
Stream Data Centers
Marion County
SC · SERC
400 abandoned
utility interconnection timingwithdrawal
Dallas-based Stream Data Centers dropped a planned 400MW, 400-acre, ~600,000-sq-ft campus in an industrial park near Marion, SC, citing 'utility timing constraints', MPD Electric…
Greenwood County Data Center Moratorium
Greenwood County
SC · SERC
moratorium in force
county moratorium
Greenwood County Council advanced a one-year moratorium on data centers in a 4-3 vote.
Nebius Data Center (Oxmoor Valley, Birmingham)
Nebius (NBIS)
Birmingham, Jefferson County (Oxmoor Valley)
AL · SERC
active litigation
litigationzoning approval challenge
Under construction off Lakeshore Parkway. Jefferson County Circuit Judge ruled July 11, 2026 that Oxmoor Valley residents' lawsuit against the city's approval process can…
Bessemer Proposed Data Center (Little Blue Creek)
Bessemer, Jefferson County
AL · SERC
zoning request paused active litigation
litigationcouncil agenda removalenvironmental concerns
Proposed site near ecologically sensitive Little Blue Creek and Five Mile Creek (habitat for the endangered watercress darter). Bessemer City Council removed the zoning item from…
Jones Eagle / Jones Digital DeWitt Crypto Data Center
Jones Eagle LLC / Jones Digital
DeWitt, Arkansas County
AR · SPP
active litigation temporary block
litigationstate law ownership ban
Owner Qimin 'Jimmy' Chen (naturalized US citizen born in China) challenged Arkansas Act 636 (2023) and Act 174 (2024), which bar data-center/crypto-mining property ownership by…
AVAIO Data Center Project (Pulaski County)
AVAIO
Pulaski County
AR · SPP
moratorium exemption rejected
quorum court rejectioncounty moratorium dispute
Pulaski County Quorum Court rejected a proposed data-center moratorium that would have carved out an exemption specifically for the AVAIO project; separately, Little Rock's own…
Grant County Data Center FOIA Dispute
Grant County
AR · SPP
active litigation records dispute
litigationpublic records dispute
Public-records (FOIA) litigation over a proposed Grant County data center; part of a broader pattern of Arkansas Democrat-Gazette records lawsuits seeking data-center contract…
Imperial Data Center (Imperial Valley Computer Manufacturing / IVCM)
Imperial Valley Computer Manufacturing, LLC (developer Sebastian Rucci)
Imperial County (near city of Imperial)
CA · CAISO
delayed
local moratoriumwater disputecommunity opposition
Would be largest data center in California at ~1M sq ft; promoted as producing 2,500 construction jobs and $28.7M/yr tax revenue; county supervisors first approved parcel merger…
GI Partners Santa Clara Data Center (2805 Bowers Avenue)
GI Partners
Santa Clara
CA · CAISO
delayed
litigationpermit denial
Four-story data center; site cost $79M. Delayed ~5 months versus planned construction timeline before City Council approval on Aug 29, 2024.
Coachella Valley Technology Campus
Stronghold Power Systems
Coachella (Riverside County)
CA · CAISO
cancelled
local moratoriumcommunity opposition
Six data centers proposed across 450 acres of agricultural land; was to anchor a new city-run utility agency; council unanimously voted to terminate the Stronghold agreement…
Eight Form El Segundo Data Center (750 N. Nash Street)
Eight Form
El Segundo (Los Angeles County)
CA · CAISO
withdrawn
community opposition
Proposed replacing a 15-year-old Hyatt Place hotel with 160-foot, five-story data center plus dedicated electrical substation.
Monterey Park Data Center (HMC StratCap)
HMC StratCap
Monterey Park (Los Angeles County)
CA · CAISO
cancelled
community opposition
247,000 sq ft facility that would have used ~3x electricity of entire 60,000-person city; would have sat under 500 feet from nearest home; ban can only be overturned by another…
Behring AI Campus / Data Center (415 20th St.)
Behring Companies
Oakland
CA · CAISO
20 delayed
community opposition
~20,000 sq ft of an 83,000 sq ft, 4-story building; part of a larger complex with a proposed 39-story apartment tower above 19th St BART station.
San Jose Data Center Pipeline (multiple Equinix and other projects)
Multiple (incl. Equinix) (EQIX)
San Jose
CA · CAISO
pending review
state moratoriumlocal moratoriumcommunity opposition
Environmental groups Green Foothills flagged 'grandfathering' risk since developers may rush applications ahead of new standards; active CEQA EIR review process for Equinix…
High-Speed Rail Corridor Data Center Deals (Merced/Madera)
California High-Speed Rail Authority (co-development partners TBD)
Merced / Madera / Kern County
CA · CAISO
pending review
water dispute
CEO Ian Choudri says hyperscalers in talks for Central Valley sites including Kern County; Madera mayor Cecilia Gallegos said city would reject data centers over water use.
Project Blue (Tucson)
Beale Infrastructure (originally Amazon Web Services-linked; AWS later withdrew) (AMZN)
Pima County / Tucson
AZ · WECC
litigation active
community opposition
Biggest development ever proposed in Pima County/southern Arizona; developer is San Francisco-based Beale Infrastructure; despite Tucson rejection and Amazon's exit, project is…
Chandler AI Data Center (Sinema-lobbied project)
Unnamed New York developer
Chandler
AZ · WECC
cancelled
zoning denial
Chandler already hosts 10 data centers and adopted 2022 rules limiting where they can be built; vote drew national progressive praise as a rare rejection of major tech-industry…
NTT Mesa Data Center
NTT (9432.T)
Mesa
AZ · WECC
delayed
water disputecommunity opposition
NTT spent $300M on land in southeast Mesa (Pecos/Crismon roads) in March 2025; requesting minor modifications to city allowances.
Casa Grande 480-Acre Data Center Campus (Willis/Barnes parcels)
Undisclosed (landowners Dale Willis and Vernon Barnes; law firm representation)
Casa Grande (Pinal County)
AZ · WECC
under appeal
zoning denialtax incentive change
No end user/tenant publicly identified; waiver includes 800 net acre-foot water cap, on-site power requirement, noise limits, decommissioning rules, $5M community contribution.
Tract Goodyear/Buckeye Data Center
Tract
Goodyear and Buckeye (Maricopa County)
AZ · WECC
withdrawn
zoning denialcommunity opposition
Company announced a replacement project near Buckeye airport in August 2024 with similar characteristics after securing mayoral support.
Boulder City BLM Data Center (Townsite Solar 2 / Eldorado Valley)
Townsite Solar 2, LLC
Boulder City (Clark County)
NV · WECC
halted
litigationenvironmental review
On September 1, 2026 the U.S. Department of the Interior's Board of Land Appeals granted a stay of the Bureau of Land Management decision that allowed Townsite Solar 2, LLC to…
Tract Northern Nevada Land Portfolio (Storey County/Reno area)
Tract
Storey County / Washoe County
NV · WECC
litigation active
litigation
Tract has purchased more than 12,000 acres across northern Nevada; company says it never sought subsidized costs and committed nearly $1B toward NV Energy infrastructure. Related…
Reno Data Center Pipeline (city-wide moratorium)
Multiple developers
Reno
NV · WECC
halted
local moratorium
Initial 30-day moratorium adopted per city rules, then extended after a 9-hour public meeting with 5+ hours of comment; some council members want to study a permanent ban.
Boardman Transmission Line / Amazon Data Center Support Infrastructure
Amazon Web Services (AMZN)
Boardman (Morrow County)
OR · WECC
litigation active
litigation
Decision on Boardman data center delayed in 2023 by new testimony; transmission line dispute continued into 2026 with regulatory challenges.
Hillsboro Data Center Pipeline (city moratorium)
Multiple developers
Hillsboro (Washington County)
OR · WECC
halted
local moratoriumwater disputetax incentive change
Hillsboro is one of Oregon's largest tech hubs (Intel/Silicon Forest); existing facilities may continue operating.
Cascade Locks Data Center (Roundhouse Digital Infrastructure)
Roundhouse Digital Infrastructure
Cascade Locks (Hood River County)
OR · WECC
cancelled
community opposition
Cited as an early precedent case for electoral backlash against data center approvals nationally.
Umatilla County Eastern Oregon Data Center Moratorium Petition
Multiple (Amazon and others) (AMZN)
Umatilla County / Morrow County
OR · WECC
pending review
state moratoriumlocal moratoriumcommunity opposition
Part of broader statewide push including a legislature-considered one-year moratorium on data center tax breaks that Gov. Kotek has expressed support for.
Seattle Data Center Pipeline (citywide moratorium)
Multiple developers
Seattle
WA · WECC
halted
community opposition
Notable given Seattle is home to Amazon and Microsoft; part of a wider wave of Washington state municipal moratoria.
Spokane Data Center Pipeline (citywide moratorium)
Multiple (incl. Avista large-load customer) (AVA)
Spokane
WA · WECC
halted
local moratorium
Data Center Coalition warned the moratorium sends a bad signal to a $1B+ minimum investment industry and could push Spokane out of site-selection conversations.
Federal Way Data Center Moratorium
Undisclosed
Federal Way
WA · WECC
halted
local moratorium
Part of broader Puget Sound-region wave of municipal pauses.
Grant County PUD Data Center Load Growth Cap
Multiple (Microsoft and others in Quincy/Moses Lake corridor) (MSFT)
Grant County (Quincy/Moses Lake)
WA · WECC
delayed
community opposition
Quincy is historically Microsoft's flagship 'data centers gone right' market; new caps signal a shift even in the most data-center-friendly Washington jurisdiction.
Broomfield Data Center Pipeline (18-month moratorium)
Multiple developers
Broomfield
CO · WECC
10 halted
local moratorium
Threshold set at 10 MW; part of a wave of Front Range municipalities enacting pauses in 2026.
Project Taurus (Colorado Springs)
Raeden
Colorado Springs (El Paso County)
CO · WECC
50 delayed
community oppositionlitigation
On September 17, 2026 the Colorado Springs City Council voted 7-2 to postpone its decision on the appeal of the Project Taurus development plan modification until April 13, 2027,…
Douglas County / Parker Flexential Data Center
Flexential
Douglas County (Parker)
CO · WECC
litigation active
tax incentive change
Tax rebate value approximate ($19M); denial and rebate approval reflect a split regulatory record in the same county within months.
Aurora Data Center Pipeline (moratorium debate)
Multiple (incl. Microsoft Aurora AI Campus) (MSFT)
Aurora
CO · WECC
delayed
local moratorium
Councilwoman Amy Wiles championed a pause; council ultimately opted for regulation over outright ban, but process caused delay for pipeline projects including the Microsoft…
Lex Developments Pocatello Data Center ($2.6B)
Lex Developments
Pocatello (Bannock County)
ID · WECC
under appeal
litigation
Proposed at a former polysilicon plant site; Idaho Conservation League highlighted unprecedented cumulative energy use concerns, comparing water use to an 18-hole golf course or…
Meta Kuna Data Center Expansion Pause
Meta (META)
Kuna (Ada County)
ID · WECC
delayed
corporate realignment
Original $800M facility reached 'peak construction' before expansion was paused; 2023 Idaho law nearly stripped Kuna's urban renewal incentive tied to the project.
Stratos Project (Box Elder County)
Undisclosed developer (backed by Kevin O'Leary)
Box Elder County
UT · WECC
7,000 litigation active
local moratoriumzoning denialcommunity opposition
Roughly 20,000-acre hyperscale campus near the Great Salt Lake requiring an estimated 7 GW of power - more than double Utah's current statewide energy use; celebrity investor…
West Jordan Facebook Data Center (historical, cancelled)
Facebook (Meta) (META)
West Jordan
UT · WECC
cancelled
tax incentive change
Historical precedent case frequently cited in current Utah data center debates; included for completeness though outside the post-Jan 2024 window as background context.
Project Jupiter (Santa Teresa / Doña Ana County)
Yucca Growth Infrastructure (developer); Oracle and OpenAI (end users) (ORCL)
Santa Teresa (Doña Ana County)
NM · WECC
litigation active
litigationzoning denialcommunity oppositionfinancing
Bonds ($165B) issued for Oracle/OpenAI development before Planning & Zoning Commission had voted on zoning, per plaintiff allegations; judge dismissed pro se resident's second…
Project Zenith (Roswell)
Undisclosed
Roswell (Chaves County)
NM · WECC
pending review
community opposition
County framework would only apply to projects seeking public incentives; privately financed projects exempted.
Meta Los Lunas Expansion (Phase 3)
Meta (META)
Los Lunas (Valencia County)
NM · WECC
pending review
water disputecommunity opposition
Original Meta investment estimated at $3.3B in Los Lunas; expansion phase raised renewed local water-use scrutiny.
New York Statewide Hyperscale Data Center Moratorium (Executive Order 62)
Multiple developers statewide
Statewide
NY · NYISO
halted
state moratoriumlocal moratorium
First state to enact such a moratorium; affects pending projects including STAMP (Genesee County), Tonawanda, and Niagara Falls proposals; legislature had separately passed its…
STAMP Data Center (Stream U.S. Data Centers / Genesee County)
Stream U.S. Data Centers (via Genesee County Economic Development Center)
Town of Alabama, Genesee County (STAMP industrial park)
NY · NYISO
250 litigation active
litigationstate moratoriumlocal moratoriumzoning denial
2.2M sq ft facility; $1.46B in requested state/local sales tax breaks ($716M state + $716M local); Hochul had previously called it a 'local decision' she wouldn't override (March…
Wildflower Yaphank Data Center
Wildflower
Yaphank, Town of Brookhaven (Suffolk County)
NY · NYISO
halted
local moratorium
Long Island Power Authority said it does not anticipate service issues, with infrastructure costs borne by the developer; Suffolk County Water Authority says no water application…
Lysander Data Center Moratorium
Undisclosed
Lysander (Onondaga County, Syracuse area)
NY · NYISO
halted
local moratorium
Part of the broader Syracuse-area wave of caution following major Micron/semiconductor-adjacent development pressure in the region.
Islip Data Center Moratorium Consideration
Undisclosed
Islip (Suffolk County)
NY · NYISO
pending review
local moratorium
Reflects a cascading pattern of Long Island towns adopting pauses in mid-2026.
Markley Group Lowell Data Center Generator Expansion
Markley Group
Lowell
MA · ISO-NE
litigation active
litigationcommunity opposition
This is a litigation update on the previously tracked Markley Group Lowell Expansion entry - court-ordered construction pause specifically targeting diesel backup generator…
Westfield Data Center ($4B)
Undisclosed developer
Westfield
MA · ISO-NE
delayed
community opposition
Case highlights retroactive political risk even for previously-approved projects as statewide sentiment on data centers shifts.
Atlas Capital Group Bloomfield Data Center
Atlas Capital Group
Bloomfield (Hartford County)
CT · ISO-NE
pending review
zoning denial
Proposed 900,000 sq ft data center plus 127,000 sq ft substation (over 1M sq ft total) at 132 Griffin Road North; among the first major hyperscale-scale proposals in Connecticut.
New Haven Data Center Moratorium Proposal
Multiple (regulatory, no single named project)
New Haven
CT · ISO-NE
pending review
local moratorium
Precautionary, policy-level pause rather than a response to one specific project; part of statewide CT data center policy debate.
Nottingham Business Park Data Center
Nottingham Business Park LLC (developer Thomas Moulton)
Nottingham
NH · ISO-NE
withdrawn
community opposition
One of the largest small-town grassroots petition campaigns against a single data center project nationally.
Verrus Data Center (Mill Creek Corporate Center)
Verrus
Salem (Marion County)
OR · WECC
pending review
local moratoriumzoning denialcommunity opposition
Same statewide wave as Hillsboro's 120-day moratorium, enacted the same week; large crowds filled the Salem Public Library auditorium for the hearing.
Smithfield Data Center (Hanton City Investments)
Hanton City Investments LLC
Smithfield
RI · ISO-NE
litigation active
zoning denial
A test case for whether an in-process application filed shortly before a newly passed local ban can be grandfathered in.
Bates Mill Data Center (Lewiston)
Undisclosed developer
Lewiston
ME · ISO-NE
cancelled
state moratoriumlocal moratorium
Proposed inside a historic mill building; project's secrecy (unnamed backers) fueled resident suspicion and contributed to rejection.
Diode Ventures Cedar Creek Lake Data Center
Diode Ventures
Henderson County (Cedar Creek Lake / Cedar Creek Reservoir)
TX · ERCOT
withdrawn
water disputecommunity opposition
Update/confirmation of previously tracked entry - confirms formal withdrawal date and cause; Cedar Creek Lake is a major regional drinking-water and recreation reservoir, which…
Blueprint Data Centers Taylor Facility
Blueprint Data Centers
Taylor (Williamson County)
TX · ERCOT
litigation active
litigationcommunity opposition
135,000 sq ft facility; case highlights title/deed-restriction risk as an emerging litigation vector for Texas data center siting distinct from zoning or environmental claims.
Meta Temple Data Center
Meta (META)
Temple (Bell County)
TX · ERCOT
delayed
corporate realignment
Part of the same Meta redesign wave that paused the Kuna, Idaho facility.
Project Patriot / Knox Ranch (Granbury)
Bilateral Energy
Granbury (Hood County)
TX · ERCOT
litigation active
litigationcommunity opposition
One of several Hood County data center disputes (see also Comanche Circle/Sailfish and Project Red/Yellow entries) reflecting a concentration of Central Texas litigation around…
Comanche Circle / Sailfish Investors Data Center
Sailfish Investors (developer Ryan Hughes)
Hood County
TX · ERCOT
delayed
community opposition
Included here as a delay/opposition case even though ultimately approved, given the scale of community pushback documented in local coverage; distinct 2,100-acre parcel from the…
Project Red and Project Yellow (Hood County)
National CRE Holdings and Greenland Capital
Hood County
TX · ERCOT
under appeal
litigation
Two related data center proposals in Hood County, adding to the county's concentration of contested projects alongside Comanche Circle and Project Patriot/Knox Ranch.
Wichita Falls Data Center Rezoning (Data Nova X)
Data Nova X (originally proposed under different developer branding)
Wichita Falls
TX · ERCOT
cancelled
zoning denialcommunity opposition
Rezoning rejection halted the project as proposed; local coverage noted skepticism over the developer's rebranding partway through the approval process.
RCM Hill LLC Data Center (Hill County)
RCM Hill LLC
Hill County
TX · ERCOT
litigation active
litigationlocal moratorium
Notable as a case where litigation pressure from the developer side successfully forced a county to reverse its own moratorium.
Highlander SM One LLC Data Center (San Marcos)
Highlander SM One LLC
San Marcos (Hays County)
TX · ERCOT
cancelled
zoning denialcommunity opposition
Distinct developer/parcel from the already-tracked Hays County/San Marcos data center entry; this project was rejected outright twice rather than approved.
Skybox Datacenters San Angelo Project
Skybox Datacenters
San Angelo (Tom Green County)
TX · ERCOT
delayed
community opposition
City-owned land angle distinguishes this from typical private-parcel disputes; raised transparency and public-benefit questions locally.
Red Oak Data Center Rezoning (Compass Datacenters)
Compass Datacenters
Red Oak (Ellis County)
TX · ERCOT
delayed
zoning denialcommunity opposition
Included as a documented opposition/delay case with a notable community-benefit concession, even though the rezoning was ultimately approved.
Texas Statewide Data Center Interconnection Audit (ERCOT Batch Zero)
Multiple (up to ~300 projects statewide, including Sherman/Grayson County pipeline)
Statewide (ERCOT footprint, incl. Sherman/Grayson County)
TX · ERCOT
halted
interconnection queue
Sherman/Grayson County is a major semiconductor and data-infrastructure growth corridor (Texas Instruments, GlobiTech) directly affected by the pause; this is a statewide…
HB 259 - Large Energy Use Facilities
Alaska (statewide)
AK
cancelled
interconnectioncommunity oppositionfinancing
Alaska HB 259 (introduced January 2026 by Rep. Donna Mears) would require large energy facilities (peak demand ≥20 MW) to enter community benefit agreements with the host…
Crow Holdings Development / CHI Acquisitions LP City of Fayetteville
Crow Holdings Development / CHI Acquisitions LP
City of Fayetteville
GA
cancelled
community opposition
Crow Holdings Development and CHI Acquisitions LP officially withdrew their appeal on March 18, 2026 to build a 300,000 sq ft data center on 37.4 acres on Highway 85 North near…
HB 1063
Georgia (statewide)
GA
cancelled
interconnectionfinancing
Requires electric utilities and new data centers (100+ MWH peak annual demand) to agree on contract terms that shield other power customers from construction and operation costs.…
SB 34
Georgia (statewide)
GA
denied
interconnection
Georgia SB34 would have prohibited data center fuel generation and transmission costs from being included in residential electricity rates, requiring commercial data centers to…
POWER Act (SB4016) + Tax Pause
Illinois (statewide)
IL
cancelled
waterfinancing
Illinois: The POWER Act (SB 4016/HB 5513), sponsored by Rep. Robyn Gabel (Evanston) and Sen. Ram Villivalam, establishes comprehensive statewide standards for data center…
SB 400
Kansas (statewide)
KS
cancelled
water
Kansas SB 400 would require data centers to use closed-loop cooling systems (no water evaporation) and authorize municipalities, local district attorneys, and the state attorney…
SB 526
Kansas (statewide)
KS
cancelled
community oppositionfinancing
SB 526 adds a zoning requirement to Kansas's existing SB 98 data center sales tax exemption program, mandating that data centers must be located on land zoned for industrial or…
LD 307 Moratorium Amendment
LiquidCool (seeking exemption for Loring data center)
Maine (statewide)
ME
26 denied
water
Governor Janet Mills VETOED LD 307 on April 24, 2026, "An Act to Establish the Maine Data Center Coordination Council and Place a Temporary Limitation on Certain Data Centers."…
Google / Meta / Metrobloks Missouri (statewide legislation)
Google / Meta / Metrobloks
Missouri (statewide legislation)
MO
cancelled
interconnectionwater
Missouri has multiple data center bills (proposed by Google / Meta / Metrobloks). HB 3362 and HB 3364 (Reps. Colin Wellenkamp, Scott Miller, Mike Costlow), titled the 'AI…
HB 4424
Oklahoma (statewide)
OK
cancelled
watercommunity oppositionfinancing
HB 4424, filed by House Speaker Kyle Hilbert (R-Bristow), ends data center eligibility for Oklahoma's property tax exemption program, which covers facility property taxes for the…
SB 1488
Oklahoma (statewide)
OK
cancelled
watercommunity opposition
SB 1488, introduced by Sen. Kendal Sacchieri (R-Blanchard), would establish a moratorium on new data centers in Oklahoma until November 2029 while the Corporation Commission…
Fairwater Wisconsin (Mount Pleasant) (referenced)
Wisconsin Legislature (SB 729 Data Center Accountability Bill)
WI
denied
interconnection
Sen. Jodi Habush Sinykin (D-Whitefish Bay) and Rep. Angela Stroud (D-Ashland) introduced the first Wisconsin bill to hold data centers accountable. SB 729 / LRB 5432 would create…
Microsoft (Mount Pleasant data center), Meta (Beaver Dam data center) Wisconsin (statewide moratorium bill)
Microsoft (Mount Pleasant data center), Meta (Beaver Dam data center)
Wisconsin (statewide moratorium bill)
WI
cancelled
watercommunity oppositionfinancing
Wisconsin SB 1061 would have imposed a moratorium on new data center construction until the state established a data center planning authority, prohibited cost-shifting to…
Crane Data Centers Pierce Township Campus (near former Beckjord plant)
Crane Data Centers
Pierce Township (Clermont County)
OH · PJM
300 halted
local moratoriumcommunity opposition
Crane Data Centers, based in San Francisco, presented a concept for a 300 MW campus of three buildings of roughly 200,000 to 300,000 square feet on about 300 acres of wooded,…
Legacy Investing North Loop Data Center (former Star Tribune Heritage Printing Facility)
Legacy Investing
Minneapolis (Hennepin County)
MN · MISO
20 withdrawn
community opposition
Virginia-based Legacy Investing terminated its purchase agreement for the vacant former Star Tribune printing plant in the North Loop, where it had proposed a 20 MW data center…
MCNI Concord Township Data Center Rezoning
MCNI (LLC)
Concord Township, Hancock County (near Garner)
IA · MISO
delayed
zoning denialcommunity opposition
The Hancock County Planning and Zoning Commission unanimously denied MCNI's request to rezone about 724 acres from agricultural to industrial for a potential data center after a…
DC Rapids LLC Data Center (former papermill site)
DC Rapids LLC
Wisconsin Rapids (Wood County)
WI · MISO
pending review
permit denialcommunity opposition
The Wisconsin Rapids Plan Commission voted 7-0 on September 16, 2026 to recommend denial of DC Rapids LLC's conditional use and site review applications to redevelop the former…
Harrington Logistics Building Data Center (Maguire Hayden)
Maguire Hayden
Harrington (Kent County)
DE · PJM
24 halted
zoning denialcommunity opposition
The Harrington City Council unanimously rejected on August 17, 2026 the zoning change needed to allow a proposed 24 MW data center at the former Harrington Logistics cold storage…
Project Oak (Walt Sanders Road data center campus)
Coweta County (Walt Sanders Road, near Newnan)
GA · SERC (Georgia Power)
halted
zoning denialcommunity opposition
The Coweta County Board of Commissioners unanimously denied a rezoning request to amend conditions on an industrially zoned 255-acre site that limited it to office and warehouse…
LightHouse Data Centers campus at 300 Jones Road (former paper mill site)
LightHouse Data Centers (property acquired by a Lightstone Group affiliate)
Spartanburg County
SC · SERC (Duke Energy Carolinas)
60 halted
permit deniallocal moratoriumcommunity opposition
County planning staff rejected the development application on June 26, 2026 for five items not in compliance with the Unified Land Management ordinance. On August 25, 2026 the…
Project Tomahawk (Parvin Road and FM 1385)
White Rose Partners
Prosper (Collin and Denton Counties)
TX · ERCOT
withdrawn
zoning denialcommunity opposition
White Rose Partners sought rezoning of about 37 acres at Parvin Road and FM 1385 for a 225,000 square foot data center estimated at about $580 million. On September 1, 2026 the…
Inver Grove Heights Proposed Data Center
Inver Grove Heights, Dakota County
MN · MISO
final vote delayed
council vote delaycommunity opposition
City council delayed a final vote after a packed, contentious meeting erupted in boos over the delay.
Meta Alabama
Meta
Alabama
AL
cancelled
interconnectioncommunity opposition
In Alabama, SB 354 would impose a one-year moratorium on construction of new large-scale solar power facilities, Prompted by opposition to a 4,500-acre solar project in Stockton…
Green Digital LLC City of Harrison
Green Digital LLC
City of Harrison
AR
cancelled
local moratoriumcommunity opposition
Harrison passed a moratorium on data centers and crypto mining on May 25, 2023 after hundreds of residents objected to a Green Digital LLC crypto facility (a subsidiary with…
Project Range
Tract
Maricopa County
AZ
1,800 cancelled
zoning denialwatercommunity opposition
Tract withdrew its $14B 'Project Range' application for a 30-building, 5.6M sq ft data center campus on ~1,000 acres near Yuma and Perryville roads in unincorporated Maricopa…
NE Edge Waterford / East Lyme
NE Edge
Waterford / East Lyme
CT
300 denied
zoning denialinterconnectioncommunity opposition
CT Siting Council denied Dominion Energy's petition to modify Millstone Power Station boundaries for NE Edge's 1.5M sq ft hyperscale data center (300MW, ~15% of reactor output).…
Sentinel Grove Technology Park / Project Jarvis
Epic Estates 68 LLC / Timberline Real Estate Partners
St. Lucie County
FL
1,000 cancelled
community opposition
In St. Lucie County, Florida, The developer of Sentinel Grove Technology Park (Project Jarvis), a proposed 1,218-acre, 15-million-square-foot, $13.5B data center campus at 1GW…
Atlas Development LLC Adairsville area (Bartow County)
Atlas Development LLC
Adairsville area (Bartow County)
GA
cancelled
zoning denialcommunity opposition
In Adairsville area, Georgia, Atlas Development sought to rezone 588 acres from agricultural for a $4.5 billion, six-building, 2.27M sq ft data center campus called 'Project…
Brennan Investment Group Barrington Hills
Brennan Investment Group
Barrington Hills
IL
cancelled
waterfinancing
Brennan Investment Group withdrew its $2 billion data center proposal for land south of Penny Road and west of Pond Gate Drive in Barrington Hills, Illinois, a suburb northwest…
Cloud Centers Lisle
Cloud Centers
Lisle
IL
50 cancelled
community opposition
In Lisle, Illinois, Cloud Centers proposed a 256,000 sq ft, 50MW data center on the former Lockformer toxic-contaminated site (18 acres). Over 300 residents packed a public…
Karis Data Center (Nokia/Lucent Campus)
Karis Critical
Naperville
IL
36 denied
zoning denialcommunity opposition
Naperville, Illinois, City Council voted 6-1 to deny Karis Critical's proposal for a 145,000 sq ft data center on the former Nokia/Lucent campus (36 MW, $250M, 40 acres). A…
Western Hospitality Partners Pekin
Western Hospitality Partners
Pekin
IL
denied
watercommunity opposition
In Illinois, Hundreds of residents packed a city council meeting to challenge a data center proposed on the Lutticken Farm along the Mahomet Aquifer, Which serves nearly 1…
Brassie Golf Course Data Center
Provident Realty Advisors
Town of Chesterton
IN
cancelled
watercommunity opposition
Provident Realty Advisors proposed a $1.3B data center on the 200-acre former Brassie Golf Course site along Pearson Road. The plan called for eight buildings at 150,000 sq ft…
Project Flo
Google
Franklin Township (Indianapolis)
IN
400 cancelled
interconnectionwatercommunity opposition
Google withdrew its 468-acre 'Project Flo' data center in Franklin Township, Indianapolis on September 22, 2025, hours before the City-County Council was expected to vote it…
Provident Realty Advisors Town of Burns Harbor
Provident Realty Advisors
Town of Burns Harbor
IN
cancelled
zoning denialcommunity opposition
Provident Realty Advisors, after being rejected in Chesterton, proposed a seven-building, 102-acre data center campus at the corner of S. Babcock and Haglund Roads on the…
Poe Companies / PowerHouse Data Centers (approved project) Louisville
Poe Companies / PowerHouse Data Centers (approved project)
Louisville
KY
400 denied
local moratoriuminterconnectioncommunity opposition
One 525MW data center project in southwest Louisville has been cleared to proceed, built by Poe Companies and PowerHouse Data Centers (starting at 100MW, expanding to 400MW).…
Project Lincoln: OC Data Center
Western Hospitality Partners
Oldham County
KY
600 cancelled
local moratoriuminterconnectioncommunity opposition
Western Hospitality Partners proposed 'Project Lincoln: OC Data Center,' a $6B, 600MW facility initially planned for 267 acres at 3557 North Highway 53. Due to fierce opposition…
Thomas A. Hobbs Living Trust (applicant) Meade County
Thomas A. Hobbs Living Trust (applicant)
Meade County
KY
cancelled
zoning denialinterconnectionwatercommunity opposition
Thomas A. Hobbs Living Trust requested rezoning of a 138-acre site along Joe Prather Highway (25025 Joe Prather Hwy, Ekron) from Agricultural/Residential to Light Industrial for…
Servistar Realties Westfield
Servistar Realties
Westfield
MA
delayed
financing
A $3-4 billion, 2.7M sq ft hyperscale data center campus proposed at 199 Servistar Industrial Way. State legislature passed a 20-year sales tax exemption. By Dec 2025, developers…
Amazon AWS / Natelli Holdings Calvert County
Amazon AWS / Natelli Holdings
Calvert County
MD
denied
local moratoriumwater
Calvert County Board of Commissioners voted 2-3 against a proposed 24-month moratorium on data center permits. Commissioner Hart had proposed the moratorium after Amazon AWS…
Meta Howell Township
Meta
Howell Township
MI
cancelled
local moratoriumcommunity opposition
Township enacted a unanimous six-month moratorium on Nov. 20, 2025 after ~2 hours of public comment. Trustee Bob Wilson confirmed Meta was behind the project, estimating a $9B…
Amazon/AWS City of Becker
Amazon/AWS
City of Becker
MN
600 cancelled
interconnectionfinancing
Amazon planned a multibillion-dollar data center near the Xcel Sherco coal-fired power plant in Becker, proposing 250 diesel backup generators. In March 2025, the Minnesota PUC…
Geronimo Power Nobles County
Geronimo Power
Nobles County
MN
denied
zoning denialpermitcommunity opposition
Nobles County (MN) Board of Commissioners voted 3-2 on April 21, 2026 to deny a zoning change that would have allowed Geronimo Power's proposed $4 billion, ~640-acre data center…
Oppidan / Connect Data Centers Apple Valley
Oppidan / Connect Data Centers
Apple Valley
MN
denied
watercommunity opposition
Oppidan/Connect Data Centers' Apple Valley Technology Park proposal (seven buildings on former sand/gravel mining site, five as data centers) faced community opposition over…
Oppidan City of North Mankato
Oppidan
City of North Mankato
MN
500 cancelled
litigationwater
Oppidan halted its data center project citing lengthy permitting for diesel generators. MCEA (Minnesota Center for Environmental Advocacy) sued the city in August 2025, alleging…
Harper Road Technology Park
Diode Ventures
City of Peculiar
MO
750 cancelled
zoning denialcommunity opposition
Peculiar originally added a 'data center' definition to its light industrial zoning, enabling Diode Ventures' proposed $1.5B Harper Road Technology Park, a 500-acre campus with…
Nebius Independence
Nebius
Independence
MO
1,200 denied
litigationcommunity oppositionfinancing
Independence City Council approved $6.26 billion in tax breaks over 20 years for Nebius on March 2, 2026, including a 98% real property tax abatement, 90% personal property tax…
Atlas Power / Sabey Data Center Properties Butte
Atlas Power / Sabey Data Center Properties
Butte
MT
250 cancelled
interconnectionwatercommunity opposition
Sabey Data Centers proposed two 500,000 sq ft buildings (1M sq ft total) on over 600 acres at Montana Connections Industrial Park in Butte, MT (Silver Bow County), requiring 325…
Mooresville data center
Tract
Mooresville
NC
1,500 cancelled
zoning denialwatercommunity opposition
Denver-based Tract proposed the $30B Mooresville Technology Park on 400 acres of undeveloped land owned by Teresa Earnhardt, widow of NASCAR champion Dale Earnhardt. The project…
Project Delta
Engineered Land Solutions
Stokes County
NC
cancelled
local moratoriumzoning deniallitigationwatercommunity opposition
Stokes County Board of Commissioners approved (3-2 vote) in January 2026 the rezoning of approximately 1,845 acres of residential-agricultural land along the Dan River for heavy…
Champion Farm Data Center Campus
Province Group
Perry Township
OH
cancelled
zoning denialcommunity opposition
Province Group formally withdrew its zoning application for a data center campus in Perry Township/Perry Village as of July 2025. The developer had signed an agreement to…
PRSM Preble County
Patrick Scanlon (developer)
Preble County
OH
denied
zoning denialcommunity opposition
Preble County Planning Commission unanimously (11-0) denied rezoning of 300 acres of farmland for a data center. The developer withdrew his application in October after residents…
Mvskoke Technology and Innovation Park
Undisclosed
Muscogee (Creek) Nation
OK
cancelled
zoning denialcommunity opposition
Jordan Harmon and Mackenzie Roberts (both Muscogee Nation citizens) organized town halls after plans emerged to build a massive AI data center on 5,500 acres of Muscogee Nation…
Project Atlas
Beale Infrastructure
Coweta
OK
400 cancelled
interconnectioncommunity opposition
In Coweta, Oklahoma, Beale Infrastructure's $800M Project Atlas proposed 295 acres for an Amazon/AWS data center with 400MW capacity. The Planning Commission voted 4-1 to deny…
Intel / Stack Infrastructure Hillsboro (SB 1586)
Intel / Stack Infrastructure
Hillsboro (SB 1586)
OR
cancelled
state moratoriumcommunity opposition
SB 1586, which would have brought 373 acres of rural land into Hillsboro's UGB for tech industries, was shelved. Separately, Councilor Kipperlyn Sinclair's data-center moratorium…
Cleveland Cliffs Steel Plant Data Center
Brian O'Neill (developer)
Conshohocken / Plymouth Township
PA
cancelled
community opposition
A developer attempted to convert the Cleveland Cliffs steel plant on 66 acres of Plymouth Township's riverfront corridor into a data center for undisclosed Big Tech tenants. Over…
Kriger / Alpesh 'Al' Patel Blakely
Kriger / Alpesh 'Al' Patel
Blakely
PA
1,500 cancelled
zoning denialinterconnection
Developers proposed a data center campus offering up to 1.5GW of capacity on 209 acres in Blakely Borough, requiring power equivalent to the entire output of the nearby…
NorthPoint Development Hazle Township
NorthPoint Development
Hazle Township
PA
denied
zoning denialinterconnectioncommunity opposition
Hazle Township, Pennsylvania, Board of Supervisors unanimously rejected NorthPoint Development's 1,280-acre, 15-building 'Project Hazelnut' data center campus in Luzerne County…
Pennhurst Data Center
Penn Hurst Holdings DE LLC
East Vincent Township (Pennhurst)
PA
denied
zoning denialpermitcommunity opposition
East Vincent's planning commission recommended rejection of a proposed 1.9 million sq ft data center at the former Pennhurst State School and Hospital for the second time.…
Project Spero
TigerDC (HG Tiger DC I LLC)
Spartanburg County (NorthMark/Project Spero)
SC
400 cancelled
interconnectionwatercommunity oppositionfinancing
TigerDC formally withdrew its $3 billion 'Project Spero' AI data center from Tyger River Industrial Park after Spartanburg County Council unanimously voted down two…
Applied Digital Toronto
Applied Digital
Toronto
SD
430 cancelled
zoning denialcommunity oppositionfinancing
Applied Digital confirmed its proposed $5B, 430MW data center campus near Toronto, SD is 'unlikely to go forward' after the legislature rejected tax incentives. The CEO stated…
Sioux Falls Hyperscale Data Center
Gemini Data Center SD LLC (Gemini Capital)
Lincoln County
SD
500 denied
local moratoriuminterconnectioncommunity opposition
Lincoln County Commissioner Joel Arends proposed a one-year moratorium on hyperscale data centers requiring 100+ MW, calling it an opportunity to 'press pause and further…
Bitcoin Mining Data Center
Red Dog Technologies
Franklin County
TN
35 denied
zoning denialcommunity opposition
Franklin County Commission denied rezoning for Red Dog Technologies' proposed Bitcoin mining data center near Tullahoma. Residents said noise would be unbearable and damage…
CloudBurst Data Centers / Highlander SC One LLC Hays County
CloudBurst Data Centers / Highlander SC One LLC
Hays County
TX
1,200 denied
local moratoriuminterconnectionwatercommunity opposition
Water advocates identified 5 data centers proposed for the Hays County, Texas, region during historic drought (proposed by CloudBurst Data Centers / Highlander SC One LLC)…
Comanche Circle
Sailfish Development
Hood County
TX
denied
local moratoriumwatercommunity opposition
Hood County (40 miles SW of Fort Worth) has received at least five data center applications (proposed by Sailfish Development). Commissioners voted down a proposed moratorium…
Highlander SC One LLC San Marcos
Highlander SC One LLC
San Marcos
TX
380 denied
zoning denialwater
San Marcos, Texas, City Council voted 5-2 at 2:14 AM on February 18, 2026 to deny zoning amendments for a $1.5 billion, 380 MW data center by Highlander SC One LLC (Fort Worth)…
Texas Solar Works Lubbock
Texas Solar Works
Lubbock
TX
cancelled
zoning denialcommunity opposition
Planning and Zoning Commission voted 4-3 to reject a 936-acre hyperscale AI data center zoning change from Low Density Single Family to General Industrial, requested by Hugo Reed…
Amazon/AWS Louisa County
Amazon/AWS
Louisa County
VA
cancelled
zoning denialwatercommunity opposition
Amazon Web Services withdrew a conditional use permit application for a 7.2 million-square-foot data center campus on 1,370 acres in Louisa County's Mineral area (south of Davis…
Balico Pittsylvania County
Balico
Pittsylvania County
VA
3,500 cancelled
zoning denialinterconnectioncommunity opposition
The Pittsylvania County Board of Supervisors voted to deny a massive 2,200-acre datacenter campus proposal that would have included 84 datacenter buildings and a 3,500MW natural…
Doug Fuller / Emerald Lakes Estates Chesapeake
Doug Fuller / Emerald Lakes Estates
Chesapeake
VA
denied
zoning denialcommunity opposition
Chesapeake City Council unanimously rejected a proposal to rezone 22.6 acres of agricultural land for a 350,000 sq ft data center. The Planning Commission had voted 6-1 against…
HB 503
Virginia (HB 503)
VA
denied
interconnection
Prohibits Virginia utilities from recovering costs of transmission lines and energy generation serving data centers over 100 MW from residential ratepayers. Aimed at addressing…
Hunting Hawk Technology Center
HHHunt
Hanover County
VA
900 cancelled
zoning denialwatercommunity opposition
In Hanover County, Virginia, HHHunt's proposed Hunting Hawk Technology Park, a 10-building, 400-acre data center campus near the Wyndham community capable of supporting up to 900…
SB 393 - Virginia's Great Outdoors Act
Virginia (SB 393)
VA
denied
community oppositionfinancing
Virginia SB 393, the Virginia's Great Outdoors Act (companion HB 641), was defeated in February 2026. The bill would have created a $250M/year dedicated funding stream for land…
Tract Capital / Winchester Gateway LLC Frederick County
Tract Capital / Winchester Gateway LLC
Frederick County
VA
cancelled
zoning denialcommunity opposition
In June 2025, the Frederick County Board of Supervisors voted by consensus against moving forward with applications for two large data centers: the proposed 644-acre Meadow Brook…
Menomonie Data Center
Balloonist LLC
Menomonie
WI
750 cancelled
zoning denialwater
Menomonie signed an NDA with Balloonist LLC in February 2024, over a year before announcing the $1.6B data center proposal in July 2025. Over the following six months, residents…
Project Nova
Microsoft
Village of Caledonia
WI
900 cancelled
interconnectioncommunity opposition
Microsoft cancelled its 244-acre, 900 MW Caledonia data center (Project Nova) after a 2,000-signature petition and strong community opposition forced a rethinking of the plan.…
Stargate / The Barn
Related Digital / Oracle
Saline Township Planning Commission
MI
1,400 denied
zoning denialpermitwatercommunity opposition
After an August 5, 2025 first public hearing dominated by opposition, the Saline Township Planning Commission tabled Related Digital's 'conditional rezoning' application for 575…
Duke Energy gas turbine proposal near Amazon data center
Duke Energy
Hamlet, NC
NC
denied
permit
NC regulators denied Duke Energy’s $584 million gas turbine proposal near Hamlet, citing unanswered questions about data center demand and who would pay for the project. The…
Project Taurus
Raeden
Colorado Springs
CO
delayed
local moratorium
Colorado Springs City Council voted to postpone a decision on the Project Taurus data center near Garden of the Gods after a daylong hearing with public comment. The delay…
American Tower Corporation Pike Township (Indianapolis withdrawal)
American Tower Corporation
Pike Township (Indianapolis withdrawal)
IN
4 cancelled
zoning denialcommunity opposition
American Tower Corporation withdrew its rezoning petition for a proposed 20,000-square-foot data center near W. 79th Street and Township Line Road in Pike Township, Indianapolis,…
Headwaters Site Development LLC Fauquier County (Catlett Station)
Headwaters Site Development LLC
Fauquier County (Catlett Station)
VA
cancelled
watercommunity opposition
Headwaters Site Development LLC withdrew its rezoning application for a $400M, four-building data center on 67 acres at Catlett Road and Gaskins Lane in Fauquier County on July…
Prologis Kosciusko County (Leesburg)
Prologis
Kosciusko County (Leesburg)
IN
denied
zoning denialwatercommunity opposition
Kosciusko County, Indiana, Area Plan Commission unanimously denied (8-0) Prologis's rezoning request for 554 acres of farmland near Leesburg from agricultural to industrial for a…
Oppidan Hampton
Oppidan
Hampton
MN
cancelled
other
Oppidan, an Excelsior-based developer, paused its data center project in Hampton after citing that the state would take too long to permit backup generators. Minnesota's…
NOVEC Prince William County (Diamond Hill substation)
NOVEC
Prince William County (Diamond Hill substation)
VA
300 denied
zoning denialinterconnectioncommunity opposition
Prince William County, Virginia, Planning Commission voted 5-3 on March 11, 2026 to deny the Diamond Hill substation, a proposed 300 MW electric utility substation with a…
Penzance Development / 1500 Gateway LLC Fredericksburg
Penzance Development / 1500 Gateway LLC
Fredericksburg
VA
600 cancelled
zoning denialinterconnectioncommunity oppositionfinancing
Penzance Development / 1500 Gateway LLC proposed a 600 MW data center on 84 acres in Fredericksburg, Virginia. Residents of the Great Oaks Lane neighborhood objected to the…
B+F Timpanogos Tech City of Provo
B+F Timpanogos Tech
City of Provo
UT
denied
zoning denialinterconnectioncommunity opposition
The Provo City, Utah, Council voted unanimously (7-0) on March 11, 2026 to deny a zoning change for a proposed AI data center at 1507 S. 180 East in the East Bay area. Developer…
Google / Microsoft Minnesota (Statewide)
Google / Microsoft
Minnesota (Statewide)
MN
cancelled
other
Bipartisan bill HF4077/SF4379 to ban local government officials from signing NDAs with data center developers is advancing through both chambers. The Senate version passed two…
JRE Strategies LLC Ardmore
JRE Strategies LLC
Ardmore
OK
10 cancelled
interconnectioncommunity opposition
JRE Strategies LLC withdrew its data center proposal after the Ardmore, Oklahoma, Planning Commission voted 7-0 against rezoning 6.74 acres from single-family residential to…
Project Accelerate
Crosland Southeast / Crow Holdings / Engineered Land Solutions
Matthews
NC
cancelled
community opposition
Developers proposed a 123-acre data center campus (Project Accelerate) near I-485 and East John Street in Matthews, North Carolina, Mecklenburg County (by Crosland Southeast /…
Rocklocker LLC Kalkaska County
Rocklocker LLC
Kalkaska County
MI
1,000 cancelled
interconnectionwatercommunity opposition
Rocklocker LLC (headed by Traverse City geologist Matt Rine) proposed a gigawatt-scale hyperscale data center on 1,440 acres of state-owned land near Island Lake and South River…
PW Digital Gateway
QTS Realty Trust / Compass
Prince William County
VA
denied
litigationwatercommunity opposition
Circuit Court Judge Kimberly Irving voided the December 2023 rezoning of 2,133 acres for the Prince William Digital Gateway, a multi-gigawatt data center hub by QTS Realty Trust…
Brian O'Neill Properties Plymouth Township
Brian O'Neill Properties
Plymouth Township
PA
cancelled
interconnectionwatercommunity opposition
Developer Brian O'Neill sought a zoning exception to convert the shuttered 66-acre Cleveland-Cliffs steel mill near Conshohocken into a 2M sq ft, 10-building AI data center in…
Project Scott
Provident Realty Advisors
Archbald Borough
PA
denied
zoning denialcommunity opposition
Council voted down Provident Realty Advisors' application to build a giant data center after months of growing outcry. About 200 residents showed up wearing yellow shirts.…
Apple Valley Technology Park
Oppidan Investment Company / Rockport LLC
Apple Valley
MN
denied
zoning denialwatercommunity opposition
Apple Valley, Minnesota, Planning Commission recommended denial on March 18, 2026 of three key components of the Apple Valley Technology Park data center project: the Preliminary…
Green Chile Project (gas pipeline for Project Jupiter)
Energy Transfer / Transwestern Pipeline Company
Dona Ana County (Project Jupiter pipeline)
NM
denied
zoning denialpermitinterconnectioncommunity opposition
On March 20, 2026, New Mexico Commissioner of Public Lands Stephanie Garcia Richard denied Energy Transfer's application to build a segment of a 17-mile natural gas pipeline…
Project Washington
Starwood Digital Ventures
Delaware (Coastal Zone Appeal)
DE
1,200 denied
zoning denial
Delaware Coastal Zone Industrial Control Board unanimously upheld DNREC Secretary's decision that 'Project Washington' data center is not allowed under the Coastal Zone Act. The…
Meyer Property Data Center
Yorkville Nexus V LLC / Green Door Capital
Yorkville
IL
cancelled
zoning denialcommunity opposition
Yorkville Nexus V LLC / Green Door Capital WITHDREW the 91-acre Meyer Property data center rezoning application on April 14-15, 2026, following the city council's April 1 tabling…
Project Hutto
Zydeco Development
Hutto
TX
70 cancelled
zoning denialinterconnectionwatercommunity opposition
On April 17, 2026, Zydeco Development withdrew its rezoning application for a proposed 950,000-square-foot data center at the southeast corner of County Road 119 and Limmer Loop…
KRAMBU, Inc. Bonner (Missoula County)
KRAMBU, Inc.
Bonner (Missoula County)
MT
3 cancelled
watercommunity opposition
KRAMBU, an Idaho-based company, applied to install an AI data center at Bonner Mill Industrial Park at the confluence of the Clark Fork and Blackfoot rivers (the 'A River Runs…
PSEG Frederick / Carroll / Baltimore Counties
PSEG
Frederick / Carroll / Baltimore Counties
MD
delayed
interconnection
Maryland's PPRP recommended a new October deadline for PSEG to complete its application for the controversial 67-mile transmission line across three counties. Opponents believe…
Outrigger Industrial Washington City Council, IN
Outrigger Industrial
Washington City Council, IN
IN
withdrawn
local moratoriumwater
Washington City Council voted unanimously to cease all dealings with Outrigger Industrial after the developer failed to answer questions about a proposed 1,000,000-gallon/day…
Beale Infrastructure Gardner, KS
Beale Infrastructure
Gardner, KS
KS
withdrawn
community oppositionfinancing
Beale Infrastructure pulled its data center proposal after Gardner city council declined tax incentives and ~200 residents from three counties opposed at the council meeting.…
Oracle; OpenAI; Crusoe; Microsoft; NVIDIA Abilene, TX (Oracle/OpenAI drop flagship Stargate Abilene expansion; Meta in talks for Crusoe capacity)
Oracle; OpenAI; Crusoe; Microsoft; NVIDIA
Abilene, TX (Oracle/OpenAI drop flagship Stargate Abilene expansion; Meta in talks for Crusoe capacity)
TX
withdrawn
interconnectioncommunity opposition
DCD reported that Oracle/OpenAI dropped plans to expand the flagship Abilene Stargate site further. Meta is in talks (with NVIDIA's help) to pick up Crusoe capacity. Additional…
Lakeland Equity Group Cleveland City Council (1-yr moratorium proposed; Lakeland Equity permit rejected), OH
Lakeland Equity Group
Cleveland City Council (1-yr moratorium proposed; Lakeland Equity permit rejected), OH
OH
denied
local moratoriumpermitinterconnection
Council Member Charles Slife proposed a 1-year data center moratorium to update zoning and define DC scales. Separately, the city rejected the construction permit application for…
Lex Developments Pocatello
Lex Developments
Pocatello
ID
denied
permitwater
A Pocatello hearing examiner denied a conditional-use permit for a data center on the former Hoku polysilicon site (about $2.26B projected), citing insufficient water and design…
Inch & Co. / Eastern Land & Resources South Annville Township
Inch & Co. / Eastern Land & Resources
South Annville Township
PA
withdrawn
community opposition
A $1.7B data center project (5 x 150,000 sq ft; developer 1235 Martina Drive Owner LLC / Inch & Co. / Eastern Land & Resources) was scrapped in South Annville Township after…
Brewster Land Company Dorrance Township
Brewster Land Company
Dorrance Township
PA
denied
litigation
The Dorrance Township zoning hearing board unanimously denied a challenge (by Brewster Land Company) arguing the township's ordinance unlawfully excluded data centers; an appeal…
AVAIO Digital Pulaski County Quorum Court (data center moratorium ordinance, failed on clerk miscount), AR
AVAIO Digital
Pulaski County Quorum Court (data center moratorium ordinance, failed on clerk miscount), AR
AR
denied
local moratoriuminterconnectioncommunity opposition
The Pulaski County Quorum Court appeared to pass a one-year data center moratorium on May 26, 2026 (with an exemption carved out for AVAIO Digital's planned Wrightsville…
EdgeConneX (via East Village Dothan LLC) Douglas County Commission
EdgeConneX (via East Village Dothan LLC)
Douglas County Commission
GA
denied
zoning denialpermitcommunity opposition
Douglas County Commission voted 4-1 to deny a ~700+ acre, 4.4M sq ft data center campus rezoning. Hyperscaler unconfirmed. The 6-building campus, partly within the Dog River…
Powers Ferry Place
Prime Group Holdings
Marietta City Council
GA
18 delayed
local moratoriumzoning denialcommunity opposition
After a Planning Commission 4-3 recommendation to approve, Marietta City Council tabled Prime Group Holdings' Powers Ferry Place rezoning -- a proposal to convert part of a…
Karis Critical Hoffman Estates
Karis Critical
Hoffman Estates
IL
cancelled
other
Karis Critical withdrew its rezoning request for the 186-acre Plum Farms property (residential/commercial to manufacturing, to potentially enable a data center) after sustained…
DAMAC Digital Edgerton (DAMAC data center denied; 6-month moratorium also denied), KS
DAMAC Digital
Edgerton (DAMAC data center denied; 6-month moratorium also denied), KS
KS
denied
local moratoriumpermitinterconnectioncommunity opposition
Two-part Edgerton (KS) action: on June 11, 2026 the Planning Commission DENIED (3-2) Dubai-based DAMAC Digital's ~$860M data center (a conversion of a ~400,000-sq-ft warehouse at…
Project Aquila
RCM Hill, LLC
Hill County (RCM Hill files $100M federal suit challenging data center moratorium), TX
TX
1,235 cancelled
litigationinterconnectioncommunity opposition
On May 28, 2026, RCM Hill, LLC sued Hill County, County Judge Shane Brassell, and Commissioners Jim Holcomb and Larry Crumpton in U.S. District Court (Western District of Texas,…
Sanders Lane / Lage Assemblage I LLC Prince William County Board of Supervisors (Dulles South Innovation Center denial)
Sanders Lane / Lage Assemblage I LLC
Prince William County Board of Supervisors (Dulles South Innovation Center denial)
VA
denied
zoning denialpermitcommunity opposition
Prince William County Board of Supervisors voted 8-0 to deny the ~1,940-acre, 43M sq ft Dulles South Innovation Center comprehensive-plan amendment after a 5-hour public hearing…
North Carolina
NC
NC
paused
local moratoriumzoning denial
The article discusses where data center development is paused or banned in western North Carolina.
Iowa Transparency Bill
Iowa (statewide)
IA
cancelled
interconnectionwater
Iowa HF 2447, proposed by Rep. Cindy Golding (R-Cedar Rapids), creates new reporting requirements and utility rate structures for data centers. Data centers must file quarterly…
Gigaland Fauquier County (Gigaland)
Gigaland
Fauquier County (Gigaland)
VA
600 withdrawn
zoning denialcommunity opposition
GigaLand withdrew its original datacenter application in Fauquier County, Virginia, after significant community opposition, but resubmitted a scaled-down proposal in early 2026,…
Pennsylvania
PA
PA
cancelled As opposition to data centers grows, researchers are exploring the use of Pennsylvania’s abandoned mine lands for potential data center sites. The article discusses the…
Nevada
A Texas-based company
Henderson
NV
withdrawn
other
A Texas-based company has withdrawn from a proposed hyperscale data center and natural gas plant project on federal land near Henderson, Nevada. The project's status is now…
Chicago
Chicago
IL
paused
other
The proposed data center project in Chicago is being paused, which may have financial implications for taxpayers.
No matches.

Methodology and scope

This watchlist tracks U.S. data center projects, operators, and jurisdictional actions that carry a documented public paper trail: securities filings, regulatory dockets, litigation, government statements, utility filings, and trade press. It is maintained as a neutral reference. Entries are recorded as observed; the tracker does not rank projects or advocate an outcome.

  • Status reflects the most recent public signal for each entry. Where a project continues on schedule, that is recorded as plainly as a delay.
  • Capacity is shown in megawatts where reported, and left blank where not disclosed.
  • Local restrictions, utility dockets, lawsuits, and federal actions are drawn from primary filings and reputable outlets, each linked to its source.
  • The ERCOT queue snapshot is extracted directly from the ERCOT GIS Report.
  • Signals are collected on a recurring basis and reconciled into a single source of truth before publication.

Every citation on one page: Sources and citations. Companion policy map: SAVRN Data Center Moratorium Tracker. Capital side: North American Data Center Capital Atlas. Founder essay: The Queue Was the Fiction.

The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.
Check this address →
What is the Nationwide Data Center Delay Watchlist?

It is a continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Each entry links to its documented public source, and it is maintained as a neutral reference.

How is a project's status determined?

Status reflects the most recent public signal for each entry: halted, delayed, cancelled, pending review, litigation active, audit paused, under appeal, or withdrawn. Where a project continues on schedule, that is recorded as plainly as a delay.

How are delay days measured?

Delay days are measured against the original announced target where available, or against the first documented delay date.

How often is the watchlist updated?

Signals are collected on a recurring basis from SEC EDGAR and trade-press feeds and reconciled into the single source of truth before publication.

How is this different from the Data Center Moratorium Tracker?

The Moratorium Tracker maps state and local policy measures. This watchlist tracks named projects, operators, public-company exposure, and securities filings, with delay status and cause for each. The two are companion references.

Nationwide Data Center Delay Watchlist

Get these tracker updates by email

A short introduction on days 3, 7 and 14, plus updates for this tracker. Unsubscribe at any time.

We use your address to send the introduction and updates described above. See our Privacy Policy.

You’re on the list. Your subscription is saved.