SAVRN Research · Living watchlist

Nationwide Data Center Delay Watchlist

A continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, local restrictions, litigation, federal and utility dockets, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Every entry links to its documented public source.

Updated 2026-09-28 Live · sources checked 53 min ago · 16 of 18 sources answered · 52 entries added in the last 7 days · last change 2026-10-03 Version 2.0.0 Coverage from 2024-01-01 Compiled by SAVRN Research
Scale model of a data center campus on a white plan: completed halls, cooling plant, and electrical substation rendered in copper, with queued future phases drawn as blueprint outline and a construction crane standing still
A data center campus rendered as a plan: completed structures shown built, queued phases shown as outline. The watchlist records which projects have moved and which are on hold.
Tracked projects
344
delayed, cancelled, or under review
Local restrictions
1150
county, city, township measures
Utility actions
272
PUC dockets and statements
Active lawsuits
63
filed or in progress
Stalled since Jan 2024
$170B+
across 20 states (Carbon Direct)
Q1 2026 delayed / cancelled
$130B
75 projects (Fortune)
ERCOT capacity at risk
49.8 GW
$8B–$15B revenue (BNEF)
Transformer lead time
128 wks
large power, average

National interconnection queue

Every ISO plus vertically integrated utilities with a public row-level queue, as of 2026-09-28. The full row-level queue is refreshed weekly. ERCOT Batch Zero row-level classifications are not yet published per Market Notice M-A080326-01.

32,382
Total queue rows
4,445 GW
Total capacity requested
46
Rows flagged data center
92
Large-load / DC studies
By status
Withdrawn15,338
IA signed8,099
Active4,163
Unknown2,003
Other1,978
Study706
Suspended95
By source, ISO and utility
PJM9,263
Alliant Energy6,968
MISO3,873
CAISO2,281
Dominion Energy VA2,178
NYISO2,148
ERCOT2,003
ISO-NE1,751
SPP1,028
Ameren Illinois146
AEP Indiana Michigan91
Consumers Energy88
Evergy Kansas88
AEP PSO80
AEP Ohio72
We Energies58
PacifiCorp56
AEP SWEPCO47
Evergy Missouri40
El Paso Electric39
AEP APCo34
MidAmerican Energy32
Ameren Missouri18

Would you like the weekly update?

Every week we re-verify every project on this watchlist and publish what moved. You get one email when it goes out.

Also send me

Receive a short introduction on days 3, 7 and 14, plus the updates you select. Unsubscribe in one click. Privacy ·

You're on the list. The next weekly update will land in your inbox when it publishes.
You are subscribed. Read the latest tracker

Browse a section below. Download the full dataset (JSON) or review all sources and citations.

Jurisdictional actions

State, local, and federal moratoriums, executive orders, audits, and legislation affecting data center approval or interconnection.

JurisdictionActionDateStatusSources
TX
state · Governor Greg Abbott / PUCT / ERCOT
Comprehensive verification and audit of all data centers in ERCOT interconnection process
ERCOT reported to the Commission that it had reviewed 290 dynamic models and that approximately 18 percent were acceptable on first review. Six large loads representing approximately 1,959…
Timing: The PUCT signed an Order Granting Good Cause Exceptions on August 20, 2026 in Project No. 59142, excusing ERCOT from the August 7, 2026 Batch Zero classification deadline and allowing conditionally classified large loads into the August 1 and November 1, 2026 Quarterly Stability Assessments. ERCOT's filed schedule is: conditional classification by August 31, 2026, requests for information across…
2026-08-03 audit in progress
NY
state · Governor Kathy Hochul (Executive Order 62) / DEC
Statewide pause on discretionary DEC permits for data centers ≥50 MW until Generic Environmental Impact Statement completes
Timing: ~1 year (until GEIS complete)
2026-07-14 audit paused
Indianapolis / Marion County
local · City-County Council
Pause on all new data center construction city-wide through Dec 31, 2027
Timing: Through Dec 31, 2027
2026-08-10 audit paused
Nashville / Metro Davidson
local · Metro Nashville Council
Moratorium on certain data center permits and appeals until at least December 1, 2026
Being challenged in federal court by DC BLOX
2026-07-21 litigation active
Loudoun County
local · Board of Supervisors
Board voted 6-1 to direct staff to prepare moratorium options for Sept 15 meeting; Dillon's Rule constrains authority
Home to Data Center Alley, 250+ existing DCs. Virginia state law may not permit local moratorium.
2026-07-23 pending review
Seattle
local
One-year moratorium on new data centers 2026-06-09 audit paused
Spokane
local
One-year moratorium on new data centers 2026-06-23 audit paused
Broomfield
local
18-month pause on data centers 2026-07-07 audit paused
Prince George's County
local
Two-year pause on hyperscale data centers 2026-07-07 audit paused
Eagan
local
Moratorium on new data centers >20MW / expansions >9MW until Feb 17, 2027
Being challenged in court by Eagan Capital (filed June 15, 2026)
2026-02-17 litigation active
AZ
state · Arizona Legislature (budget)
Three-year moratorium on data center sales tax exemption
Timing: Through June 30, 2029
2026-07-01 audit paused
VA
state · General Assembly (Bill)
HB 1515, Moratorium on new DCs (1 MW+) until interconnection requests fulfilled or July 2028
Continued/still in committee
2026-01-XX pending review
Denmark (Energinet)
national
3-month grid connection pause 2026-05-04 audit paused
Ireland (EirGrid)
national
Freeze ended Dec 2025; new connections must bring own on-site power 2025-12-XX delayed
federal · FERC
Show-cause orders to six RTOs (PJM, MISO, SPP, CAISO, ISO-NE, NYISO), 60 days to justify or reform large-load tariffs across 5 reform areas 2026-06-18 pending review
Texas (statewide)
state · Gov. Greg Abbott / ERCOT / PUCT
Governor Abbott directed a comprehensive audit of up to 300 pending large-load data center interconnection projects, pausing new approvals until ERCOT and PUCT complete energy and water usage review
BNEF estimates the audit could delay 49.8 GW of data center load and cost projects up to $15 billion; Texas also enacted SB 6 (2025) creating large-load curtailment and cost-allocation…
Timing: Pending audit completion
2026-08-03 audit paused
New York (statewide)
state · Gov. Kathy Hochul / Executive Order No. 62
Executive Order 62 establishes the nation's first statewide temporary moratorium on new large (50MW+) hyperscale data center permitting while NYSDEC develops a Generic Environmental Impact Statement and siting framework
Follows earlier legislative effort (S.9144/A.10141, 20MW threshold, 3-year pause) that stalled in committee; NYSDEC permitting for large data centers is paused under the EO.
Timing: Until GEIS/permitting framework complete
2026-07-14 pending review
Arizona (statewide)
state · Gov. Katie Hobbs / Arizona Legislature
Arizona froze new data center sales-tax exemption applications for three years amid a state budget fight over cost of tax incentives
Sparked a rush of incentive applications before the freeze deadline; existing exemptions unaffected.
Timing: 3 years
2026-06-13 pending review
Virginia (statewide)
state · Virginia General Assembly / Del. Shin (HB 1515)
HB 1515 would prohibit localities from granting final approval for new data centers until pending AI data center interconnection requests are fulfilled or July 1, 2028; continued to 2027 session in House Rules Committee
Virginia is a Dillon's Rule state; localities cannot impose moratoria on their own, so this would be the first statewide legislative pause. More than 60 data center bills considered in the…
Timing: Through July 1, 2028 (if enacted)
2026-02-06 pending review
Maine (statewide)
state · Maine Legislature / Gov. Janet Mills
LD 307 would have imposed an 18-month moratorium on data centers over 20MW pending a coordination council review; passed legislature but vetoed by Gov. Mills on April 24, 2026; override vote failed 20-11 in Senate (short of two-thirds)
Mills signed executive order creating 15-member Maine Data Center Advisory Council to deliver recommendations by early 2027. Local moratoria (Scarborough, Brunswick, Warren, Hot…
Timing: 18 months (vetoed, not enacted)
2026-04-24 litigation active
Georgia (statewide)
state · Georgia General Assembly / Public Service Commission
HB 1059 proposed statewide ban on new data center permits until impact study completes; died in committee. Separately, Georgia PSC unanimously approved a rule requiring new Georgia Power customers above 100MW (chiefly data centers) to pay their own site-specific and upstream…
Multiple GA counties/cities enacted their own moratoria (Cherokee County, Chamblee, Garden City, Newton County, DeKalb County, Athens-Clarke County, Camden County, Rockdale County).
Timing: N/A (PSC rate rule enacted; legislative ban died)
2026-01-26 pending review
Ohio (statewide)
state · Ohio ballot petitioners / Ohio General Assembly
Proposed constitutional amendment to ban data centers over 25MW; petitioners gathered ~70,000 of 413,488 signatures required by July 1, 2026 deadline and failed to qualify for ballot; separately Substitute HB 646 (dedicated rate class, halved sales-tax exemption, closed-loop…
At least 20+ Ohio municipalities/townships enacted their own moratoria independently (see Franklin, Delaware, Licking County entries).
Timing: Ballot effort failed; backers plan retry in 2027
2026-04-03 litigation active
Michigan (statewide)
state · Michigan Legislature
Statewide moratorium bills (HB 5594-5596, SB 1018-1020) reintroduced for a 1-year/365-day pause on data center construction alongside a Senate Democratic regulatory package; none enacted
Gov. Whitmer has called a moratorium 'an automatic non-starter.'
Timing: 365 days (if enacted)
2026-06-24 pending review
Pennsylvania (statewide)
state · Governor Josh Shapiro (Executive Order 2026-05)
Governor Shapiro signed Executive Order 2026-05, Protecting Pennsylvania Consumers from Data Center Impacts, conditioning state permit review for data centers over 25 MW on a binding commitment to the GRID Requirements and on local approval, and removing data centers from the…
Signed August 18, 2026. The Department of Environmental Protection must develop a template Consent Order and Agreement that developers of any data center with peak demand over 25 MW must…
Timing: Effective immediately; remains in effect until amended or rescinded by the Governor
2026-08-18 enacted
Vermont (statewide)
state · Vermont Legislature (S.205)
S.205 would impose a moratorium on data centers above 10MW until July 1, 2030, the longest pause window of any 2026 state bill
In committee as of mid-2026; Vermont has minimal existing data center capacity, so bill is largely preventive.
Timing: Until July 1, 2030
2026-01-01 pending review
Oklahoma (statewide)
state · Oklahoma Legislature (Sen. Standridge Sacchieri, SB 1488)
SB 1488 would pause new data center construction statewide until November 1, 2029 while a study commission examines rural, ratepayer, and water impacts
In committee as of mid-2026.
Timing: Until Nov. 1, 2029
2026-01-22 pending review
South Dakota (statewide)
state · Gov. Larry Rhoden / SD Legislature
SB 135 ('Data Center Bill of Rights for Citizens') and HB 1038 signed into law, not a moratorium, but requires 10MW+ facilities to pay for their own grid upgrades, disclose water/energy projections, and preserves local home-rule authority over siting/moratoria
First enacted state-level data center restriction in the country (though framed as disclosure/cost-allocation rather than an outright pause).
Timing: Permanent (enacted law)
2026-03-24 pending review
Florida (statewide)
state · Florida Legislature / Governor
SB 484 (Chapter 2026-65) signed into law effective July 1, 2026: affirms local land-use authority over large-load data centers, sets minimum utility tariff/service requirements, restricts certain water-use permits, and orders a state study of large-scale data centers
Enables the wave of Florida county moratoria (Sarasota, Palm Beach).
Timing: Permanent (enacted)
2026-07-01 pending review
Texas (statewide)
state · Texas Legislature / Gov. Abbott (SB 6)
SB 6 signed into law setting planning, interconnection, and cost-allocation rules for large electric loads including data centers, allowing ERCOT to curtail large loads during grid emergencies
Predecessor/complement to the Aug. 2026 audit/pause; establishes legal basis for curtailment during the audit.
Timing: Permanent (enacted)
2025-06-01 pending review
Loudoun County
county · Loudoun County Board of Supervisors
Phase 1 zoning rewrite eliminated by-right AI data center development countywide; every new data center now requires a Special Exception (SPEX) permit with public hearings. Board separately voted 6-1 (July 22, 2026) to direct staff to study a full pause on processing all data…
County attorney says formal moratoria are not legal in VA except narrow circumstances; grandfathering for applications filed before Feb 12, 2025 more than 500ft from residential areas.…
Timing: Phase 2 standards expected ~March 2027
2025-03-18 pending review
Prince William County
county · Prince William County Board of Supervisors
Board initiated zoning text amendment (DPA2026-00006) on March 3, 2026 to eliminate by-right AI data center approval within the Data Center Opportunity Zone Overlay District (DCOZOD) and require a Special Use Permit (SUP) for all data centers; also closed the overlay to future…
Follows controversial PW Digital Gateway rezoning approved without a water-use study; Board also unanimously denied rezoning for the ~2,000-acre Dulles Cloud South campus and abandoned…
Timing: Pending final adoption
2026-03-03 pending review
Hanover County
county · Hanover County Board of Supervisors
Board voted 4-3 to deny rezoning and conditional-use permit for Tract's 430-acre Mountain Road Technology Park data center campus, citing water use, noise, and speculative nature of the project
Hanover Planning Commission had earlier voted to deny the HHHunt-affiliated rezoning on Jan 15, 2026; Board also launched a broader public review of data center policy.
Timing: N/A (project rejected)
2026-05-28 litigation active
Fairfax County
county · Fairfax County Board of Supervisors
Adopted Zoning Ordinance Amendment ZO 112.1-2024-9 imposing 200ft residential setback for buildings (300ft for equipment), a 1-mile Metrorail-station buffer requiring special exception, mandatory pre/post-construction noise studies, and building design standards for AI data…
Projects with site plans submitted before July 16, 2024 grandfathered (e.g., Plaza 500 in Bren Mar). 4.4M sq ft of data centers under construction in Fairfax as of early 2024.
Timing: Permanent (enacted ordinance)
2024-09-11 pending review
Prince George's County
county · Prince George's County Council (Chair Oriadha)
County Council approved a 2-year moratorium on new hyperscale data center development following a countywide task force review; extended the pause in early July
Timing: 2 years
2026-07-08 pending review
Sarasota County
county · Sarasota County Commission
County blocked hyperscale data center applications for at least one year, with commissioners stating 'no, not now, never' regarding large AI data centers
Sarasota County cities subsequently united in opposition to the fast-growing AI data center industry.
Timing: At least 1 year
2026-07-09 pending review
Palm Beach County
county · Palm Beach County Board of County Commissioners
County halted new AI/large-scale data center applications under a moratorium directive, while carving out an exception allowing the pending 'Project Tango' application to proceed to a decision
Zoning board separately recommended a formal one-year pause on new large-scale data centers.
Timing: ~1 year (pending ULDC revisions)
2026-07-07 pending review
Chesterfield County
county · Chesterfield County Board of Supervisors
Board indicated it will not approve any more data centers in the county, effectively pausing new approvals amid growing local opposition
One county data center project reportedly halted amid legal dispute.
Timing: Indefinite
2026-06-01 pending review
Warrenton (Fauquier County)
city · Warrenton Town Council
Town Council took up data center regulation in 2025 amid opposition to an Amazon data center and transmission line proposal near Warrenton
Timing: Ongoing review
2025-01-01 pending review
Manassas / Prince William County
county · Virginia Court of Appeals
Court of Appeals ruling blocked construction of 37 data centers proposed adjacent to Manassas National Battlefield Park, halting the Digital Gateway-linked project
Prince William supervisors subsequently abandoned defense of the related Digital Gateway rezoning.
Timing: Pending further appeal
2026-04-07 litigation active
Fauquier County
county · Fauquier County Board of Supervisors
County approved a policy curbing new data centers; officials also caused Amazon to 'indefinitely postpone' its proposed AWS data center in the county
Timing: Ongoing
2025-06-01 pending review
Culpeper County
county · Culpeper County Board of Supervisors
County put new 'guardrails' on data centers even while approving the Red Ace Data Center campus (69.19 acres rezoned rural to light industrial); Piedmont Environmental Council urged a full ban in the draft zoning code
Timing: Ongoing
2025-01-01 pending review
Berkeley County
county · Berkeley County Council / residents
Local residents organized opposition to a proposed $4 billion data center in Berkeley County; county officials (site of WV's first 'high impact' data center) sought clarity on tax-split rules amid growth concerns
No formal moratorium yet identified, but active organized opposition and legislative scrutiny.
Timing: Ongoing
2026-03-23 pending review
Front Royal / Warren County
city · Front Royal Town Council / Warren County
Front Royal adopted a moratorium in June 2026 and declared no data centers are permitted in the town's industrial areas, effectively ruling out data centers town-wide
Timing: Indefinite
2026-06-01 pending review
Chesapeake
city · Chesapeake City Council
City Council approved an 8-month pause on data center applications, paired with a Comprehensive Plan amendment process
Council had earlier rejected an AI data center rezoning in June 2025 over environmental/disruption concerns.
Timing: 8 months
2026-07-22 pending review
Montgomery County
county · Montgomery County Executive / Council
County Executive paused new data center permit applications for 6 months by executive order in June 2026; County Council advancing a bill to extend the pause to 18 months and cap facility size
Timing: 6 months (proposed extension to 18 months)
2026-06-01 pending review
Frederick County
county · Frederick County Council
Frederick County adopted a data center application pause similar to Montgomery County's
Timing: Not specified
2026-06-01 pending review
Baltimore (city)
city · Baltimore City Council
City Council passed a one-year moratorium on new data center development pending a zoning study
Timing: 1 year
2026-05-12 pending review
Baltimore County
county · Baltimore County Council
Baltimore County adopted a data center application pause similar to Montgomery and Frederick counties
Timing: Not specified
2026-06-01 pending review
Washington County
county · Washington County Board of Commissioners
Western Maryland county approved a yearlong data center moratorium
Timing: 1 year
2026-07-01 pending review
Calvert County
county · Calvert County Board of Commissioners
County board passed a 6-month moratorium on new data centers
Timing: 6 months
2026-08-01 pending review
Indianapolis
city · Indianapolis City-County Council
Council approved a data center moratorium pausing approval of new data centers through the end of 2027, overriding Mayor Hogsett's earlier veto/endorsement position; awaits Metropolitan Development Commission sign-off
Development committee had advanced it 10-3 before full council vote.
Timing: Through end of 2027
2026-08-10 pending review
Boone County
county · Boone County Commissioners
Commissioners approved a moratorium on new data center development
Timing: Not specified
2026-06-15 pending review
Hobart
city · Hobart residents / Circuit Court
Residents/opponents filed suit challenging an Amazon data center project in Hobart, Indiana
See lawsuits.json for docket detail.
Timing: N/A (litigation)
2025-01-01 litigation active
Nashville (Metro Davidson County)
city · Metro Council (BL2026-1448)
Metro Council passed data center zoning and permit regulations that ban some data centers, pause the rest, and add new regulations, after a record-setting council meeting
Related to DC BLOX v. Nashville litigation (see lawsuits.json).
Timing: Not specified (permanent zoning changes plus pause)
2026-07-21 pending review
Wilson County
county · Wilson County Commission
County commission approved a six-month moratorium on data centers to study impacts on water and power
Timing: 6 months
2026-07-14 pending review
McMinnville
city · McMinnville City Council
City adopted a new pause on data center applications
Timing: Not specified
2026-01-01 pending review
Federal Way
city · Federal Way City Council
City passed a one-year data center moratorium
Timing: 1 year
2026-01-01 pending review
Broomfield
city · Broomfield City Council
City Council passed an 18-month temporary ban on new or expanded data centers of 10MW or more
Timing: 18 months
2026-07-08 pending review
Denver
city · Denver City Council
City Council unanimously passed a one-year moratorium on new data center construction
Proposal first introduced March 31, 2026.
Timing: 1 year
2026-05-18 pending review
Aurora
city · Aurora City Council
City Council rejected a proposed six-month data center moratorium and instead approved new siting rules and water regulations
Aurora had earlier paused data center/warehouse development approvals temporarily in Sept. 2025.
Timing: N/A (moratorium rejected; regulations adopted instead)
2026-08-11 pending review
Boulder County
county · Boulder County Commissioners
Commissioners declared a moratorium on new data center (and detention center) development while updating land-use code (docket DC-26-0003)
Timing: Pending land-use code update
2026-08-10 pending review
Lochbuie
city · Lochbuie Board of Trustees
Town enacted a five-year data center moratorium, the longest local pause identified in Colorado
Timing: 5 years
2026-01-01 pending review
Douglas County
county · Douglas County Commissioners
Commissioners kept data centers and crypto mines on hold pending new regulations, without adopting a formal moratorium
Timing: Pending regulation development
2026-04-25 pending review
Minneapolis
city · Minneapolis City Council
City Council gave final approval to a data center development pause
Timing: Not specified
2026-06-25 pending review
Inver Grove Heights
city · Inver Grove Heights City Council
City adopted a new pause on data center development
Timing: Not specified
2026-01-01 pending review
Ypsilanti Township / Ypsilanti Community Utilities Authority
utility · Ypsilanti Community Utilities Authority (YCUA)
YCUA board approved a 12-month moratorium on supplying water/sewer service to new data centers (Resolution No. 2026-08)
Ypsilanti City Council separately voted in support of the YCUA moratorium.
Timing: 12 months
2026-04-16 pending review
Flint
city · Flint City Council
City adopted a new pause on data center development
Timing: Not specified
2026-01-01 pending review
Chandler
city · Chandler City Council (Ordinance No. 5033)
City Council adopted Ordinance No. 5033 establishing zoning restrictions on data centers after years of resident complaints about noise and resource use
Predates the 2024-2026 wave but remains in force and is frequently cited as a model.
Timing: Permanent (enacted ordinance)
2022-01-01 pending review
Casa Grande
city · Casa Grande City Council
City Council approved data center waivers/exceptions to local rules amid state-level tax incentive pause, drawing debate over possible damages liability
Timing: Not specified
2026-08-03 pending review
Tucson
city · Tucson City Council
City Council voted 7-0 to end negotiations and halt annexation for Project Blue, a 290-acre Amazon-linked data center campus (developer Beale Infrastructure), citing water supply and ratepayer concerns
Developer subsequently pursued the site in unincorporated Pima County instead.
Timing: N/A (project halted)
2026-01-01 pending review
Ravenna
city · Ravenna City Council
City Council unanimously adopted a one-year moratorium on new data centers, heading off a proposed facility on State Route 14
Part of a wave of Northeast Ohio moratoria.
Timing: 1 year
2026-01-01 pending review
Lordstown (village)
city · Lordstown Village Council (Ordinance 1-2026)
Village Council passed an emergency 180-day moratorium on new data center permits after first enacting and then repealing an outright ban amid a developer's Ohio Supreme Court challenge; council later moved to extend the moratorium
Underlying dispute reached the Ohio Supreme Court.
Timing: 180 days (extended)
2026-01-01 litigation active
Franklin County (Prairie Township / Washington Township)
county · Prairie Township Trustees / Washington Township Trustees
Prairie Township enacted a 6-month moratorium on data center zoning applications; Washington Township separately paused new data centers to assess fire safety and emergency readiness
Franklin County also convened a dedicated Data Center Moratorium Work Group.
Timing: 6 months (Prairie Twp.)
2026-04-01 pending review
Sunbury (Delaware County)
county · Sunbury City Council
City Council passed a moratorium on data centers effective until 2027; residents separately petitioned to place a charter amendment banning data centers on the November 2026 ballot
Neighboring Pataskala pursuing a similar fall ballot measure.
Timing: Through 2027
2026-04-16 pending review
St. Albans Township (Licking County)
county · St. Albans Township / Licking County Planning Commission
Township officials sought to ban data center complexes; Licking County Planning Commission approved St. Albans Township's plan to ban data centers
Microsoft separately paused its own $1bn data center plans in Licking County.
Timing: Not specified
2026-01-01 pending review
Sugar Grove (Kane County)
county · Sugar Grove Village Board / Kane County officials
Officials considering a moratorium on data centers in unincorporated Kane County; Sugar Grove weighing a data center crackdown
Aurora, IL city council separately approved new data center regulations.
Timing: Under consideration
2026-04-06 pending review
Lake County (unincorporated)
county · Lake County Board
County Board voted to temporarily ban new data centers in unincorporated Lake County; a subsequent proposed 8-month moratorium cleared its first procedural step in August 2026
Linked to Grayslake/T5 litigation (see lawsuits.json).
Timing: 8 months (subsequent proposal)
2026-06-20 pending review
McHenry County
county · McHenry County Board
County considering data center regulatory requirements amid regional Chicagoland backlash against new projects
Timing: Under consideration
2026-06-01 pending review
Chatham County
county · Chatham County Board of Commissioners
County enacted a 12-month moratorium on data centers and cryptocurrency mining
A developer sued Chatham County over the moratorium (see lawsuits.json).
Timing: 12 months
2026-02-18 litigation active
Apex (Wake County)
city · Apex Town Council
Town Council approved a yearlong pause on data center projects amid opposition to the proposed New Hill Digital Campus
Developer subsequently withdrew the New Hill Digital Campus application.
Timing: 1 year
2026-03-11 pending review
Wendell (Wake County)
city · Wendell Board of Commissioners
Town adopted a temporary moratorium on data centers while it rewrites zoning rules
Timing: Pending zoning rewrite
2026-03-01 pending review
Boone
city · Boone Town Council
Town approved a data center development moratorium
Timing: Not specified
2026-03-23 pending review
Woodfin (Buncombe County)
city · Woodfin Town Council
Council asked staff to draft a temporary moratorium on data centers as the Land Development Ordinance (LDO) is updated
Timing: Pending LDO update
2026-01-01 pending review
Hot Springs (Madison County)
city · Hot Springs Town Council
Town imposed a data center moratorium as small towns weigh costs of development
Timing: Not specified
2026-07-23 pending review
Stokes County
county · Stokes County Planning Board
Planning Board backed a pause on data center development
Timing: Not specified
2026-07-10 pending review
Cherokee County
county · Cherokee County Commission
County approved a data center moratorium
Timing: Not specified
2026-07-22 pending review
Chamblee
city · Chamblee City Council
City Council approved a pause on data center applications
Timing: Not specified
2026-07-22 pending review
DeKalb County
county · DeKalb County Commission
Commission extended its data center moratorium by six months amid public health concerns; extended again through June 23, 2026 and later through September
Commission also voted against an amendment that would have created permanent data center regulations, opting to continue the pause instead.
Timing: Multiple extensions (through Sept. 2026)
2025-12-16 pending review
Rockdale County
county · Rockdale County Commission
County re-extended its data center moratorium multiple times, most recently through September 8, 2026
Timing: Through Sept. 8, 2026 (re-extended)
2026-01-01 pending review
Garden City
city · Garden City Council
City put the brakes on data centers with a new local restriction
Timing: Not specified
2026-06-16 pending review
Athens-Clarke County
county · Athens-Clarke County Commission
County extended its temporary moratorium on new data centers through June 5, 2026
Timing: Through June 5, 2026 (extended)
2026-01-01 pending review
Camden County
county · Camden County Commission
County adopted a 9-month data center moratorium
Kingsland city manager recommended a parallel measure.
Timing: 9 months
2026-05-05 pending review
Monterey Park
city · Monterey Park City Council
City Council overwhelmingly voted to permanently ban new data centers, the first California city to do so
Timing: Permanent
2026-06-03 pending review
Patterson
city · Patterson City Council
City adopted a 45-day moratorium chilling talks of data center construction
Timing: 45 days
2026-01-01 pending review
Mendocino County
county · Mendocino County Board of Supervisors
Supervisors moved toward a data center moratorium
Timing: Under consideration
2026-07-01 pending review
City of Imperial
city · City of Imperial Council / local leaders
Local leaders challenged a million-square-foot hyperscale data center project in Imperial, California amid moratorium conflict; underlying dispute proceeded to federal litigation (IVCM v. City of Imperial, see lawsuits.json)
Timing: N/A (litigation)
2026-01-01 litigation active
Coachella
city · Coachella City Council
City Council unanimously approved a 45-day moratorium on new data center applications and voted to terminate the utility agreement behind the proposed Coachella Valley Technology Campus; moratorium later extended into 2027 while the city drafts a permanent ban
Timing: Extended into 2027
2026-01-01 pending review
Tulare County
county · Tulare County Board of Supervisors
County stalled data center developments with a moratorium that could be extended
Timing: Could be extended
2026-01-01 pending review
Linn County
county · Linn County Board of Supervisors
Board of Supervisors voted 2-1 to impose an 18-month moratorium on new applications to rezone land into the county's large-scale data center district, months after adopting a data center zoning ordinance (1,000-ft residential setbacks, mandatory water study/agreement, noise and…
Timing: 18 months
2026-01-01 pending review
Birmingham
city · Birmingham City Council
City Council enacted zoning rules for hyperscale data centers (500-ft setback from residential districts, closed-loop cooling capping water use, certified-mail notice to nearby owners), called Alabama's strictest data center ordinance
Leeds, Homewood, Cullman, and Fort Payne also adopted new pauses.
Timing: Permanent (enacted)
2026-01-01 pending review
Leeds
city · Leeds City Council
City adopted a new pause on data center development, part of a wave of four Alabama cities acting in 2026
See also Homewood, Cullman, Fort Payne.
Timing: Not specified
2026-01-01 pending review
New Jersey (statewide)
state · New Jersey Legislature / Governor
Data Center Fair Share Act signed into law, requiring 50MW+ facilities to commit to paying at least 85% of projected power costs for a decade
Timing: 10-year commitment period (permanent law)
2026-07-07 pending review
Monroe Township
city · Monroe Township Council
Township took regulatory action affecting data center development, subject of Hexa Builders litigation (see lawsuits.json)
Timing: N/A (litigation)
2025-01-01 litigation active
East Windsor Township
city · East Windsor Township Committee (Ordinance No. 2026-06)
Township adopted Ordinance No. 2026-06 establishing a data center moratorium
Timing: Not specified
2026-01-01 pending review
Neptune Township
city · Neptune Township Committee
Township banned data centers (and ICE detention facilities) via local ordinance
Timing: Permanent (enacted)
2026-07-13 pending review
Andover
city · Andover Township Committee
Sussex County town officially banned data centers after public pushback
Timing: Permanent (enacted)
2026-05-29 pending review
Oklahoma City
city · Oklahoma City Council
City Council approved a moratorium on new data centers, effective immediately and expiring Dec. 31, 2026, covering all new applications
Timing: Through Dec. 31, 2026
2026-04-21 pending review
Jackson County / Springfield
county · Jackson County Legislature / Springfield City Council
Jackson County and Springfield, Missouri both adopted new pauses on data center development
Timing: Not specified
2026-01-01 pending review
Manitowoc County
county · Manitowoc County Board
County Board voted unanimously to impose an 18-month data center moratorium
Timing: 18 months
2026-04-29 pending review
Dodge County
county · Dodge County Board
County adopted a new pause on data center development
Timing: Not specified
2026-01-01 pending review
Champaign County
county · Champaign County Board
County Board approved a 1-year data center moratorium
Timing: 1 year
2026-04-24 pending review
Valparaiso
city · Valparaiso City Council
Council voted 6-1 for a data center moratorium
Timing: Not specified
2026-07-15 pending review
Fort Worth
city · Fort Worth City Council
City Council unanimously voted to take first steps toward a data center moratorium
Timing: Under development
2026-08-12 pending review
Hill County
county · Hill County Commissioners Court
Hill County adopted a one-year moratorium on data center development, then rescinded it roughly three weeks later (June 5, 2026) amid a $100 million developer lawsuit, replacing it with a checklist of requirements for applicants
Developer filed a $100M suit challenging the moratorium.
Timing: Rescinded
2026-06-05 litigation active
Nottingham
city · Nottingham Town Meeting
Town approved a 12-month moratorium on data center development via town meeting vote
Timing: 12 months
2026-07-03 pending review
Gray
city · Gray Town Council
Gray joined a growing list of Maine towns adopting data center moratoriums, following Scarborough, Brunswick, and Warren after the statewide LD 307 override failed
Timing: Not specified
2026-08-06 pending review
Reading
city · Reading City Council
City adopted a 180-day pause on data centers
Timing: 180 days
2026-07-01 pending review
York County
county · York County Planning Commission
Planning Commission recommended data center moratorium/regulation
Timing: Not specified
2026-01-01 pending review
Pulaski County
county · Pulaski County Quorum Court
Data center moratorium measure remained unresolved after an earlier vote-count failure
Timing: Unresolved
2026-01-01 pending review
Reno
city · Reno City Council
City extended its existing data center moratorium into 2027
Timing: Through 2027
2026-01-01 pending review
Memphis
city · Memphis City Council
Memphis data center moratorium proposal begins City Hall process
Separately, DOJ moved to intervene and dismiss the NAACP's Clean Air Act suit over gas turbines powering xAI's Memphis Colossus 2 site on national-security grounds (see lawsuits.json).
Timing: Under process
2026-08-01 pending review
Waterloo
city · Waterloo City Council
City considering a three-month data center moratorium
Timing: 3 months (proposed)
2026-01-01 pending review
Denmark (national)
national · Danish national grid operator / government
Denmark paused new data center grid connections amid mounting power grid strain, with total connection requests reaching roughly 60GW
Denmark built one of Europe's cleanest grids; AI data center demand is straining that capacity.
Timing: Not specified
2026-05-04 pending review
Ireland (national)
national · Commission for Regulation of Utilities (CRU) / EirGrid
Ireland ended its multi-year moratorium on new power connections to data centers, publishing a final policy on data centre grid connections via CRU; EirGrid had previously pulled the plug on roughly 30 Irish data center projects during the pause
Data centers reportedly account for roughly 21% of Ireland's electricity consumption.
Timing: Ended (moratorium lifted)
2025-12-12 pending review
Amsterdam
city · Amsterdam Municipality
Amsterdam halted new data center construction citywide via a municipal moratorium, later easing restrictions gradually with Haarlemmermeer before formally resuming construction after roughly a year's pause
Dutch Data Center Association criticized the rules as 'symbol politics.'
Timing: ~1 year (lifted with restrictions)
2025-04-18 pending review
Germany (national)
national · German Bundestag / Energy Efficiency Act
Germany's Energy Efficiency Act mandates heat-reuse requirements as a data center siting gate and imposes broader energy efficiency restrictions on new data centers, described as the first regulated data center market in Europe
Timing: Permanent (enacted law)
2026-01-01 pending review
Singapore (national)
national · Infocomm Media Development Authority (IMDA) / Economic Development Board
Singapore lifted its longstanding data center moratorium via a pilot phase accepting new applications, subject to strict environmental sustainability standards and conditions
Precedent frequently cited as the model for 'lifting with conditions' after a construction pause.
Timing: Moratorium lifted; new conditional framework in place
2022-01-01 pending review
Delaware (statewide)
state · Governor Matt Meyer / Delaware General Assembly
Delaware enacted a four-bill energy consumer protection package aimed at large energy users including data centers, headlined by a bring-your-own-generation mandate requiring large energy-use facilities to produce or secure 100 percent of their required power
Signed August 26, 2026. HB 445 requires large energy-use facilities to produce or secure 100 percent of their required power, including a renewable energy component, so that new demand…
Timing: Permanent statutory change
2026-08-26 enacted
New Jersey (statewide, August 2026 package)
state · Governor of New Jersey / New Jersey Legislature
New Jersey enacted two more data center laws on the same day: mandatory semi-annual water and energy usage reporting to the Board of Public Utilities, and the End Data Center Tax Credits Act reducing credits available under the Next New Jersey Program
S3379 (second reprint), approved August 27, 2026 as P.L.2026, c.75, requires data center owners and operators to submit semi-annual water and energy usage reports to the Board of Public…
Timing: Permanent statutory change
2026-08-27 enacted
MI
state · Michigan
Environmental advocates push lawmakers to enact a statewide moratorium and establish better protections for communities regarding data centers.
As data center developments remain top of mind for Michigan residents, and with Election Day soon on the horizon, environmental advocates continue to push lawmakers to enact a statewide…
2026-09-14 proposed
NV
state · Nevada
Governor Joe Lombardo issues an executive order to welcome more AI data centers, offering trimmed tax breaks and making commitments to address public concerns.
The executive order emphasizes economic growth and fiscal diversification for Nevada. It responds to public wariness about data center development.
2026-09-18 in force
NV
state · Governor Lombardo
Signing executive order on data center development
The governor signed an executive order focused on data center development.
2026-09-18 in force
Ohio (statewide)
state · Governor Mike DeWine / Ohio Tax Credit Authority
Governor DeWine directed the Ohio Tax Credit Authority to pause consideration of new data center sales tax exemption requests while the General Assembly's joint data center committee reviews data center growth
Announced May 27, 2026. Pending requests were considered through the Tax Credit Authority's June 1, 2026 meeting, after which new data center sales tax exemption applications are not being…
Timing: Until the legislative review concludes (no end date set)
2026-05-27 in force
New York (statewide)
state · New York State Legislature (S10642 / A11560)
Legislature passed the Responsible Data Center Development Act, a one-year moratorium on Department of Environmental Conservation permits for new large data centers, with separate PSC rate classes for data centers of 20 MW or more
S10642 (Sen. Kristen Gonzalez) was substituted by A11560, which passed the Assembly and the Senate on June 4, 2026. The bill sets a one-year moratorium on DEC permits for new data centers…
Timing: One-year permit moratorium if signed
2026-06-04 pending
Oregon (statewide, state-owned land)
state · Governor Tina Kotek
Governor directed all state agencies to immediately pause unapproved requests for easements, rights-of-way, leases, rentals, land-use permits and sales or transfers of state-owned property for data center projects
Announced September 8, 2026. The directive applies only to state-owned land and property; the Governor's office said the state currently lacks authority to enact a statewide moratorium on…
Timing: Through July 1, 2027, or until statewide action by the Governor's Office or Legislature directs otherwise
2026-09-08 in force
Texas (statewide)
state · Governor Greg Abbott / Texas Water Development Board
Governor directed the Texas Water Development Board to enforce mandatory water use survey reporting against data centers and other major water users, penalize past and future noncompliance, refer violators to county or district attorneys, and notify TCEQ
The directive states that data centers must share the duty to protect Texas water and that the Texas Water Code requires a complete and accurate water use survey. Failing to return the…
Timing: Ongoing; first TWDB enforcement update due October 14, 2026
2026-09-14 in force
Virginia (statewide, Data Center Accountability Framework legislative proposals)
state · Governor Abigail Spanberger
Governor Spanberger unveiled a Data Center Accountability Framework proposing to eliminate by-right approval and require local authorization for data centers over 25 MW, alongside ratepayer, environmental and grid proposals, with Executive Order 22 implementing parts of it…
Announced September 18, 2026. Framework items include banning nondisclosure agreements for commercial data center projects; eliminating by-right approval and requiring local authorization…
2026-09-18 proposed
New York (statewide)
state · Governor Kathy Hochul / Empire State Development
Governor Hochul announced a statewide Community Investment Framework for data center deals, setting a recommended benchmark of $1 million in community investment per megawatt of power demand, and said she is pursuing legislation to repeal sales tax exemptions for large data…
Announced September 15, 2026 as the Community Investment Framework directed by Executive Order 62 of July 14, 2026, which created the statewide moratorium on new hyperscale data centers.…
Timing: Guidance in effect; tax exemption repeal requires legislation
2026-09-15 in force
New Hampshire (statewide)
state · Governor Kelly Ayotte
Governor Ayotte told the Executive Council she will include a statewide data center moratorium in her next budget bill (HB 2), and said she opposes a potential hyperscale data center at the former coal plant site in Bow
Stated at the Executive Council meeting in Durham on September 2, 2026, citing energy supply and electricity prices. The moratorium would not take effect before the next state budget, at…
Timing: Multi-year; would take effect no earlier than July 2027 when the next budget becomes law
2026-09-02 proposed
North Carolina (statewide)
state · North Carolina General Assembly / Governor Josh Stein (Session Laws 2026-41 and 2026-42)
North Carolina repealed the sales and use tax exemptions for electricity sold for use at certified data centers, effective July 7, 2026, and added quarterly reporting of tax paid on that electricity
Session Law 2026-41 repeals the electricity exemptions for Certified Datacenters under G.S. 105-164.13(55) and (55a), effective July 7, 2026 and applying to the first billing period that…
Timing: Permanent statutory change
2026-07-07 enacted
Illinois (statewide)
state · Governor JB Pritzker / Department of Commerce and Economic Opportunity
By directive of Governor Pritzker on June 5, 2026, the Department of Commerce and Economic Opportunity stopped processing applications for the Data Center Investment Program tax exemptions and credits as of July 1, 2026
DCEO's program page states that per the Governor's directive on June 5, 2026 it will no longer process applications for the data center incentive program as of July 1, 2026. The program…
Timing: From July 1, 2026; end date not stated by DCEO
2026-06-05 in force
Utah (statewide, state agencies)
state · Governor Spencer J. Cox (Executive Order 2026-03)
Governor Cox signed Executive Order 2026-03, Establishing a Higher Bar for Data Center Development in Utah, directing state agencies to apply a Data Center Framework that protects the Great Salt Lake and water resources, air quality and utility ratepayers in matters related to…
Signed May 29, 2026. The framework's eight principles are: protect the Great Salt Lake and other water resources by ensuring water consumption is not increased and water quality is…
Timing: Effective immediately until modified, rescinded or superseded
2026-05-29 enacted
Pennsylvania (statewide)
state · Gov. Josh Shapiro
Gov. Shapiro announced a major shift sharply limiting data center development and expanding the review process for new projects, taking a hard line against 'predatory' developers, after PA House/Senate bills (model ordinance, 18-month local moratorium authorization, Sen. Muth's…
PA Senate had separately advanced a bill allowing localities to enact up to 18-month data center moratoria.
Timing: TBD (new review process)
2026-08-17 pending review
MA
state · Gov. Maura Healey
Issued an executive order restricting data centers in Massachusetts.
The executive order is likely to halt data center growth in the state before it begins. The order was issued by Governor Maura Healey.
2026-09-09 in force
OH
state · Ohio
Candidates for governor have called for restrictions on data centers, proposing some form of moratorium unless certain conditions are met.
All candidates for governor have called for restrictions, but the Ohio legislature has not taken action. The specific conditions for the moratorium are not detailed in the text.
2026-09-22 proposed
VA
state · Virginia governor
Issued an executive order that prohibits non-disclosure agreements (NDAs) for data center projects, limits permitting processes, and calls for stricter environmental protections.
The executive order directly targets data center development by removing NDAs and tightening environmental regulations. It also introduces limits on the permitting process for such projects.
2026-09-18 in force
VA
state · Virginia Gov. Abigail Spanberger
Announced a new proposal to tighten restrictions on data center developments and promote clean energy.
The proposal is called the 'Data Center Accountability Framework.' It aims to reduce noise pollution and water use associated with data centers and encourage clean energy use.
2026-09-18 proposed
CA
state · Gov. Gavin Newsom
Signed bills requiring data centers to disclose energy and water use, pay more for grid infrastructure, and undergo environmental review.
The laws require data centers to publicly disclose their energy and water consumption. They also impose additional grid infrastructure fees and mandate environmental reviews for new…
2026-09-23 in force
CA
state · California
Governors take major actions on AI
An executive order by California Gov. Gavin Newsom looks to boost oversight of the tech, while Virginia Gov. Abigail Spanberger’s order tightens data center standards.
2026-09-23 in force
VA
state · Virginia
Virginia lawmakers call for study on AI use in Virginia colleges and more headlines
• “Virginia lawmakers call for study on AI use in Virginia colleges.”, WHRO • “Homeland Security agents may have illegally accessed Virginia voter rolls, whistleblower alleges.”, The…
2026-09-24 paused
TX
state · Texas Gov. Greg Abbott
Ordered a pause on environmental permits for new data centers until an audit of the waitlist is completed.
The order expands a previous moratorium on grid approvals to include environmental permits. The action comes amid political controversy over data center development in Texas.
2026-09-21 in force
TX
state · Gov. Greg Abbott
Broadens moratorium on data center approvals to include environmental permits
The governor expanded an existing moratorium to cover environmental permits. The action targets data center developments in the state.
2026-09-21 in force
NM
state · Deb Haaland (if elected)
Sign an executive order to pause all new large-scale data center proposals while state lawmakers craft guidelines
Haaland said the moratorium would take effect immediately upon taking office if elected. The order would remain in place until lawmakers develop guidelines for data center developments.
2026-09-17 proposed
TX
state · Texas
Formation of a coalition to advocate for responsible data center growth and to partner with state officials to create standards and guardrails.
The coalition aims to prevent moratoriums on new data center construction in seven states. The group plans to launch initial campaigns in Texas, Georgia, Ohio, Iowa, Pennsylvania, Indiana,…
2026-09-28 proposed
CA
state · California Governor Gavin Newsom
Issued an executive order addressing independent auditors and kill switches for AI systems.
The executive order was issued in response to the federal government's inaction on AI safety. It directly references ongoing debates in Washington and positions Newsom as a leader on AI…
2026-09-18 in force
MI
state
The State Senate leader is open to a data center moratorium.
The Senate leader expressed openness to a moratorium on new data centers.
2026-09-28 proposed
NM
state · Governor Haaland (if elected)
Announces intention to issue an executive order imposing a data center moratorium if elected.
The announcement indicates a potential moratorium on new data centers if the nominee is elected governor. The specific terms and duration of the moratorium were not detailed in the…
2026-09-28 proposed
No matches.

Methodology and scope

This watchlist tracks U.S. data center projects, operators, and jurisdictional actions that carry a documented public paper trail: securities filings, regulatory dockets, litigation, government statements, utility filings, and trade press. It is maintained as a neutral reference. Entries are recorded as observed; the tracker does not rank projects or advocate an outcome.

  • Status reflects the most recent public signal for each entry. Where a project continues on schedule, that is recorded as plainly as a delay.
  • Capacity is shown in megawatts where reported, and left blank where not disclosed.
  • Local restrictions, utility dockets, lawsuits, and federal actions are drawn from primary filings and reputable outlets, each linked to its source.
  • The ERCOT queue snapshot is extracted directly from the ERCOT GIS Report.
  • Signals are collected on a recurring basis and reconciled into a single source of truth before publication.

Every citation on one page: Sources and citations. Companion policy map: SAVRN Data Center Moratorium Tracker. Capital side: North American Data Center Capital Atlas. Founder essay: The Queue Was the Fiction.

The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.
Check this address →
What is the Nationwide Data Center Delay Watchlist?

It is a continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Each entry links to its documented public source, and it is maintained as a neutral reference.

How is a project's status determined?

Status reflects the most recent public signal for each entry: halted, delayed, cancelled, pending review, litigation active, audit paused, under appeal, or withdrawn. Where a project continues on schedule, that is recorded as plainly as a delay.

How are delay days measured?

Delay days are measured against the original announced target where available, or against the first documented delay date.

How often is the watchlist updated?

Signals are collected on a recurring basis from SEC EDGAR and trade-press feeds and reconciled into the single source of truth before publication.

How is this different from the Data Center Moratorium Tracker?

The Moratorium Tracker maps state and local policy measures. This watchlist tracks named projects, operators, public-company exposure, and securities filings, with delay status and cause for each. The two are companion references.

Nationwide Data Center Delay Watchlist

Get these tracker updates by email

A short introduction on days 3, 7 and 14, plus updates for this tracker. Unsubscribe at any time.

We use your address to send the introduction and updates described above. See our Privacy Policy.

You’re on the list. Your subscription is saved.