SAVRN Research · Living watchlist

Nationwide Data Center Delay Watchlist

A continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, local restrictions, litigation, federal and utility dockets, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Every entry links to its documented public source.

Updated 2026-09-28 Live · sources checked 51 min ago · 16 of 18 sources answered · 52 entries added in the last 7 days · last change 2026-10-03 Version 2.0.0 Coverage from 2024-01-01 Compiled by SAVRN Research
Scale model of a data center campus on a white plan: completed halls, cooling plant, and electrical substation rendered in copper, with queued future phases drawn as blueprint outline and a construction crane standing still
A data center campus rendered as a plan: completed structures shown built, queued phases shown as outline. The watchlist records which projects have moved and which are on hold.
Tracked projects
344
delayed, cancelled, or under review
Local restrictions
1150
county, city, township measures
Utility actions
272
PUC dockets and statements
Active lawsuits
63
filed or in progress
Stalled since Jan 2024
$170B+
across 20 states (Carbon Direct)
Q1 2026 delayed / cancelled
$130B
75 projects (Fortune)
ERCOT capacity at risk
49.8 GW
$8B–$15B revenue (BNEF)
Transformer lead time
128 wks
large power, average

National interconnection queue

Every ISO plus vertically integrated utilities with a public row-level queue, as of 2026-09-28. The full row-level queue is refreshed weekly. ERCOT Batch Zero row-level classifications are not yet published per Market Notice M-A080326-01.

32,382
Total queue rows
4,445 GW
Total capacity requested
46
Rows flagged data center
92
Large-load / DC studies
By status
Withdrawn15,338
IA signed8,099
Active4,163
Unknown2,003
Other1,978
Study706
Suspended95
By source, ISO and utility
PJM9,263
Alliant Energy6,968
MISO3,873
CAISO2,281
Dominion Energy VA2,178
NYISO2,148
ERCOT2,003
ISO-NE1,751
SPP1,028
Ameren Illinois146
AEP Indiana Michigan91
Consumers Energy88
Evergy Kansas88
AEP PSO80
AEP Ohio72
We Energies58
PacifiCorp56
AEP SWEPCO47
Evergy Missouri40
El Paso Electric39
AEP APCo34
MidAmerican Energy32
Ameren Missouri18

Would you like the weekly update?

Every week we re-verify every project on this watchlist and publish what moved. You get one email when it goes out.

Also send me

Receive a short introduction on days 3, 7 and 14, plus the updates you select. Unsubscribe in one click. Privacy ·

You're on the list. The next weekly update will land in your inbox when it publishes.
You are subscribed. Read the latest tracker

Browse a section below. Download the full dataset (JSON) or review all sources and citations.

Interconnection queue

Large-load and data center cluster studies from state utility commissions and utility filings, and the data-center-flagged rows in the national generation and large-load queues. Source and resource breakdowns for the full 32,382-row queue are in the panel above.

Large-load and data center cluster studies

UtilityStateStudyRequested MWFiledStatusSource
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 1; announced load 3,500 MW and initial in-service date Q2 2031. Project name, type, city,…
3,500 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 2; announced load 3,210 MW and initial in-service date Q2 2028. Project name, type, city,…
3,210 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 3; announced load 3,000 MW and initial in-service date Q4 2027. Project name, type, city,…
3,000 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 4; announced load 2,000 MW and initial in-service date Q2 2028. Project name, type, city,…
2,000 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 5; announced load 2,000 MW and initial in-service date Q2 2028. Project name, type, city,…
2,000 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 6; announced load 2,000 MW and initial in-service date Q2 2028. Project name, type, city,…
2,000 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 7; announced load 1,600 MW and initial in-service date Q2 2030. Project name, type, city,…
1,600 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 8; announced load 1,500 MW and initial in-service date Q4 2027. Project name, type, city,…
1,500 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 9; announced load 1,463 MW and initial in-service date Q4 2027. Project name, type, city,…
1,463 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 10; announced load 1,400 MW and initial in-service date Q2 2032. Project name, type, city,…
1,400 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 11; announced load 1,400 MW and initial in-service date Q2 2028. Project name, type, city,…
1,400 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 12; announced load 1,200 MW and initial in-service date Q2 2028. Project name, type, city,…
1,200 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 13; announced load 1,200 MW and initial in-service date Q2 2028. Project name, type, city,…
1,200 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 14; announced load 1,200 MW and initial in-service date Q4 2027. Project name, type, city,…
1,200 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 15; announced load 1,200 MW and initial in-service date Q4 2027. Project name, type, city,…
1,200 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 16; announced load 1,200 MW and initial in-service date Q4 2027. Project name, type, city,…
1,200 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 17; announced load 1,200 MW and initial in-service date Q4 2027. Project name, type, city,…
1,200 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 18; announced load 1,115 MW and initial in-service date Q2 2028. Project name, type, city,…
1,115 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 19; announced load 1,020 MW and initial in-service date Q4 2027. Project name, type, city,…
1,020 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 20; announced load 1,000 MW and initial in-service date Q2 2028. Project name, type, city,…
1,000 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 21; announced load 910 MW and initial in-service date Q4 2027. Project name, type, city, county,…
910 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 22; announced load 910 MW and initial in-service date Q4 2027. Project name, type, city, county,…
910 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 23; announced load 910 MW and initial in-service date Q4 2027. Project name, type, city, county,…
910 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 24; announced load 860 MW and initial in-service date Q2 2029. Project name, type, city, county,…
860 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 25; announced load 840 MW and initial in-service date Q2 2029. Project name, type, city, county,…
840 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 26; announced load 750 MW and initial in-service date Q4 2027. Project name, type, city, county,…
750 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 27; announced load 725 MW and initial in-service date Q4 2027. Project name, type, city, county,…
725 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 28; announced load 725 MW and initial in-service date Q4 2027. Project name, type, city, county,…
725 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 29; announced load 651 MW and initial in-service date Q4 2027. Project name, type, city, county,…
651 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 30; announced load 648 MW and initial in-service date Q4 2027. Project name, type, city, county,…
648 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 31; announced load 648 MW and initial in-service date Q4 2027. Project name, type, city, county,…
648 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 32; announced load 600 MW and initial in-service date Q2 2028. Project name, type, city, county,…
600 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 33; announced load 600 MW and initial in-service date Q4 2027. Project name, type, city, county,…
600 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 34; announced load 600 MW and initial in-service date Q4 2027. Project name, type, city, county,…
600 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 35; announced load 600 MW and initial in-service date Q4 2027. Project name, type, city, county,…
600 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 36; announced load 576 MW and initial in-service date Q4 2027. Project name, type, city, county,…
576 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 37; announced load 567 MW and initial in-service date Q2 2030. Project name, type, city, county,…
567 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 38; announced load 550 MW and initial in-service date Q4 2027. Project name, type, city, county,…
550 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 39; announced load 550 MW and initial in-service date Q4 2027. Project name, type, city, county,…
550 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 40; announced load 550 MW and initial in-service date Q2 2030. Project name, type, city, county,…
550 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 41; announced load 500 MW and initial in-service date Q4 2027. Project name, type, city, county,…
500 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 42; announced load 500 MW and initial in-service date Q2 2029. Project name, type, city, county,…
500 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 43; announced load 500 MW and initial in-service date Q4 2027. Project name, type, city, county,…
500 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 44; announced load 500 MW and initial in-service date Q2 2030. Project name, type, city, county,…
500 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 45; announced load 481 MW and initial in-service date Q2 2029. Project name, type, city, county,…
481 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 46; announced load 480 MW and initial in-service date Q4 2027. Project name, type, city, county,…
480 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 47; announced load 455 MW and initial in-service date Q4 2027. Project name, type, city, county,…
455 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 48; announced load 455 MW and initial in-service date Q4 2027. Project name, type, city, county,…
455 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 49; announced load 455 MW and initial in-service date Q4 2027. Project name, type, city, county,…
455 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 50; announced load 455 MW and initial in-service date Q2 2029. Project name, type, city, county,…
455 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 51; announced load 450 MW and initial in-service date Q4 2027. Project name, type, city, county,…
450 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 52; announced load 450 MW and initial in-service date Q4 2027. Project name, type, city, county,…
450 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 53; announced load 450 MW and initial in-service date Q2 2030. Project name, type, city, county,…
450 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 54; announced load 432 MW and initial in-service date Q4 2027. Project name, type, city, county,…
432 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 55; announced load 420 MW and initial in-service date Q4 2027. Project name, type, city, county,…
420 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 56; announced load 405 MW and initial in-service date Q4 2027. Project name, type, city, county,…
405 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 57; announced load 365 MW and initial in-service date Q4 2027. Project name, type, city, county,…
365 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 58; announced load 365 MW and initial in-service date Q4 2027. Project name, type, city, county,…
365 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 59; announced load 360 MW and initial in-service date Q4 2027. Project name, type, city, county,…
360 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 60; announced load 360 MW and initial in-service date Q2 2029. Project name, type, city, county,…
360 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 61; announced load 350 MW and initial in-service date Q2 2028. Project name, type, city, county,…
350 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 62; announced load 350 MW and initial in-service date Q4 2027. Project name, type, city, county,…
350 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 63; announced load 325 MW and initial in-service date Q2 2028. Project name, type, city, county,…
325 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 64; announced load 300 MW and initial in-service date Q4 2027. Project name, type, city, county,…
300 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 65; announced load 300 MW and initial in-service date Q2 2028. Project name, type, city, county,…
300 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 66; announced load 264 MW and initial in-service date Q4 2027. Project name, type, city, county,…
264 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 67; announced load 252 MW and initial in-service date Q2 2028. Project name, type, city, county,…
252 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 68; announced load 250 MW and initial in-service date Q4 2027. Project name, type, city, county,…
250 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 69; announced load 240 MW and initial in-service date Q4 2027. Project name, type, city, county,…
240 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 70; announced load 240 MW and initial in-service date Q2 2029. Project name, type, city, county,…
240 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 71; announced load 230 MW and initial in-service date Q2 2029. Project name, type, city, county,…
230 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 72; announced load 216 MW and initial in-service date Q2 2029. Project name, type, city, county,…
216 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 73; announced load 216 MW and initial in-service date Q2 2029. Project name, type, city, county,…
216 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 74; announced load 200 MW and initial in-service date Q4 2027. Project name, type, city, county,…
200 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 75; announced load 200 MW and initial in-service date Q4 2027. Project name, type, city, county,…
200 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 76; announced load 180 MW and initial in-service date Q2 2029. Project name, type, city, county,…
180 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 77; announced load 180 MW and initial in-service date Q2 2028. Project name, type, city, county,…
180 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 78; announced load 175 MW and initial in-service date Q2 2028. Project name, type, city, county,…
175 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 79; announced load 144 MW and initial in-service date Q2 2029. Project name, type, city, county,…
144 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 80; announced load 50 MW and initial in-service date Q4 2027. Project name, type, city, county,…
50 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 81; announced load 50 MW and initial in-service date Q2 2029. Project name, type, city, county,…
50 2026-05-15 pending
Georgia Power Company
large load request
GA 2026 Integrated Resource Plan Large Load Economic Development Report Q1 2026, Technical Review Pipeline
Docket 55378; 56002
Redacted technical-review large-load pipeline entry 82; announced load 45 MW and initial in-service date Q4 2027. Project name, type, city, county,…
45 2026-05-15 pending
Arizona Public Service
large load request
AZ ACC Data Center/Large Load Workshop Highlights
Docket E-00000A-25-0069
ACC workshop materials report APS's estimated large-customer peak-demand load at approximately 13.1 GW in 2026; APS has developed a prospective…
13,100 2026-04-20 pending
Salt River Project
large load request
AZ ACC Data Center/Large Load Workshop Highlights
Docket E-00000A-25-0069
ACC workshop materials state that SRP serves 59 large-load customers with nearly 7,000 MW combined load and has a prospective data-center queue;…
7,000 2026-04-20 approved
Xcel Energy, Colorado
other
CO Proposed Large Load Tariff
Xcel submitted a proposed Colorado large-load tariff for new customers or significant expansions of 50 MW or more; it requires interconnection and…
2026-04-02 pending
Dominion Energy Virginia
large load request
VA Large-Load Connection Queue Process Standards
Docket PUR-2026-00011
Dominion's aggregate large-load delivery-point queue was reported at about 70 GW, with approximately 45 GW under study and most requests tied to…
70,000 2026-02-02 pending
AEP Ohio
cluster study
OH AEP Ohio Schedule DCT Load Study, Cluster 1
Docket 24-508-EL-ATA
Aggregate formal-load-study cluster of new data-center projects totaling 5,454.5 MW. Individual customer names, MW values, and POIs were not…
5,454.5 2025-11-07 pending
AEP Ohio
cluster study
OH AEP Ohio Schedule DCT Load Study, Cluster 2
Docket 24-508-EL-ATA
Aggregate formal-load-study cluster of new data-center projects totaling 4,353.2 MW. Individual customer names, MW values, and POIs were not…
4,353.2 2025-11-07 pending
AEP Ohio
cluster study
OH AEP Ohio Schedule DCT Load Study, Cluster 3
Docket 24-508-EL-ATA
Aggregate formal-load-study cluster of new data-center projects totaling 3,215.0 MW. Individual customer names, MW values, and POIs were not…
3,215.0 2025-11-07 pending
Duke Energy Carolinas
integrated resource plan appendix
SC Carolinas Resource Plan revision for large site projects
Duke's revised forecast identifies 35 large site projects, including announced data centers, requiring 24.7 TWh/year by 2033. The public report does…
approved
ERCOT
cluster study
TX Batch Zero Interconnection Study Process for Large Loads
Docket PGRR145
ERCOT's Batch Zero process applies to large-load facilities of 75 MW or more. The public page gives process thresholds and deadlines but publishes…
pending
Xcel Energy
special contract
MN Meta / Amber Kestral enterprise data-center filing
Public reporting on an MPUC-related Xcel filing says the enterprise data-center project was expected to start at at least 10 MW and exceed 75 MW in…
pending
No matches.

Data center flagged queue rows

ProjectISO / utilityStateDeveloperMWResourceStatus
Giga Texas Data Center
Travis
ERCOT Giga Texas Energy, LLC 133 battery IA signed
Bullock Gas
Hill
ERCOT Bullock Data Center, LLC 1,400 gas study
Liberty Thermal Energy Center
Hill
ERCOT Liberty Data Center I, LLC 1,400 gas study
IRON MOUNTAIN WIND ENERGY
SAN BERNARDINO
CAISO CA 149.4 wind withdrawn
IRON MOUNTAIN SOLAR 1
RIVERSIDE
CAISO CA 49.5 solar withdrawn
IRON MOUNTAIN SOLAR 2
RIVERSIDE
CAISO CA 49.5 solar withdrawn
WARD VALLEY SOLAR ENERGY 2
SAN BERNARDINO
CAISO CA 250 solar withdrawn
MARTELLA SOLAR
KINGS
CAISO CA 20 solar withdrawn
North Country Data Center
St. Lawrence
NYISO NY North Country Data Center 435 other active
St Lawrence Data and Agricultural Center
St. Lawrence
NYISO NY ZeroC Data Centers, LLC 200 other study
SDC St. Lawrence
St. Lawrence
NYISO NY Sabey Data Center Properties, LLC 120 other study
Suffern Quarry Data Center
Rockland
NYISO NY Robert Delcalzo 200 other withdrawn
Hudson Valley Data Center
Rockland
NYISO NY Equity Suffern Developers, LLC 50 other withdrawn
Hudson Valley Data Center
Rockland
NYISO NY Robert Delcalzo 50 other study
New York State Artificial Intelligence Data Center
St. Lawrence
NYISO NY ZeroC Data Centers, LLC 300 other withdrawn
Olean Digital Data Center
Cattaraugus
NYISO NY Olean Digital LLC 300 other withdrawn
Greenidge 200 MW Data Center Project
Yates
NYISO NY Greenidge Generation, LLC 200 other study
New York State Artificial Intelligence Data Center
St. Lawrence
NYISO NY ZeroC Data Centers, LLC 300 other study
Wulf Compute Data Center II
Niagara
NYISO NY TeraWulf Brookings LLC 250 other study
1 Gig Data Center East Fishkill, NY
Dutchess
NYISO NY Donovan Drive Holdings LLC 1,000 other study
North East Data LLC Data Center
Niagara
NYISO NY North East Data LLC 500 other study
Brookhaven Data Center
Suffolk
NYISO NY Brookhaven Logistics Center, LLC 300 other withdrawn
Pontoon Bridge Road Data Center
St Lawrence
NYISO NY American Data Center Partners LLC 250 other study
Massena Development LLC Power Allocation
St; Lawrence
NYISO NY North Country Data Center LLC 200 other study
iPark 84 Data Center Interconnection
Dutchess
NYISO NY iPark East Fishkill LLC 150 other study
NYISO Load Interconnection Process - Data Center Inquiry
Horseheads
NYISO NY URI TALY 150 other study
Highwall Data Center
Clearfield
NYISO PA Highwall Energy, LLC 400 other study
Compass
Rockland
NYISO NY PPL Electric Utilities 0 other withdrawn
Cedar Lake Solar
St. Lawrence
NYISO NY Emeren US, LLC 8.4 hybrid withdrawn
Suffern Quarry Data Center
Rockland
NYISO NY Orange & Rockland 0 other withdrawn
Bethlehem Energy Center Uprate
Albany
NYISO NY GB II New York 875 gas withdrawn
Colora Tap
Cecil
PJM MD 465 gas other
Colora Tap
Cecil
PJM MD 465 gas other
Colora 34.5kV
Cecil
PJM MD 10 solar withdrawn
Hopewell-Surry 230kV
Surry
PJM VA 142.4 solar other
Dawson-South Justice 115kV
Alamance
PJM NC 60 solar other
Dawson-South Justice 115kV
Alamance
PJM NC 80 solar other
Dawson-South Justice 115kV
Halifax
PJM NC 20 solar withdrawn
Dawson-South Justice 115kV
Halifax
PJM NC 140 solar other
Colora 230 kV
Cecil
PJM MD 100.8 battery withdrawn
Colonial Trail 230 kV
Surry
PJM VA 160 battery withdrawn
Hopewell - Colonial Trail 230 kV
Surry
PJM VA 150 hybrid active
Colonial Trail - Surry 230 kV
Surry
PJM VA 80 solar withdrawn
New Halifax - Dawson 115 kV
Halifax
PJM NC 74.9 hybrid withdrawn
Dawson-South Justice 115kV
Halifax
PJM NC 140 solar withdrawn
Colora 230 kV
Cecil
PJM MD 100.8 battery withdrawn
No matches.

Methodology and scope

This watchlist tracks U.S. data center projects, operators, and jurisdictional actions that carry a documented public paper trail: securities filings, regulatory dockets, litigation, government statements, utility filings, and trade press. It is maintained as a neutral reference. Entries are recorded as observed; the tracker does not rank projects or advocate an outcome.

  • Status reflects the most recent public signal for each entry. Where a project continues on schedule, that is recorded as plainly as a delay.
  • Capacity is shown in megawatts where reported, and left blank where not disclosed.
  • Local restrictions, utility dockets, lawsuits, and federal actions are drawn from primary filings and reputable outlets, each linked to its source.
  • The ERCOT queue snapshot is extracted directly from the ERCOT GIS Report.
  • Signals are collected on a recurring basis and reconciled into a single source of truth before publication.

Every citation on one page: Sources and citations. Companion policy map: SAVRN Data Center Moratorium Tracker. Capital side: North American Data Center Capital Atlas. Founder essay: The Queue Was the Fiction.

The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.
Check this address →
What is the Nationwide Data Center Delay Watchlist?

It is a continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Each entry links to its documented public source, and it is maintained as a neutral reference.

How is a project's status determined?

Status reflects the most recent public signal for each entry: halted, delayed, cancelled, pending review, litigation active, audit paused, under appeal, or withdrawn. Where a project continues on schedule, that is recorded as plainly as a delay.

How are delay days measured?

Delay days are measured against the original announced target where available, or against the first documented delay date.

How often is the watchlist updated?

Signals are collected on a recurring basis from SEC EDGAR and trade-press feeds and reconciled into the single source of truth before publication.

How is this different from the Data Center Moratorium Tracker?

The Moratorium Tracker maps state and local policy measures. This watchlist tracks named projects, operators, public-company exposure, and securities filings, with delay status and cause for each. The two are companion references.

Nationwide Data Center Delay Watchlist

Get these tracker updates by email

A short introduction on days 3, 7 and 14, plus updates for this tracker. Unsubscribe at any time.

We use your address to send the introduction and updates described above. See our Privacy Policy.

You’re on the list. Your subscription is saved.