SAVRN Research · Living watchlist

Nationwide Data Center Delay Watchlist

A continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, local restrictions, litigation, federal and utility dockets, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Every entry links to its documented public source.

Updated 2026-09-28 Live · sources checked 52 min ago · 16 of 18 sources answered · 52 entries added in the last 7 days · last change 2026-10-03 Version 2.0.0 Coverage from 2024-01-01 Compiled by SAVRN Research
Scale model of a data center campus on a white plan: completed halls, cooling plant, and electrical substation rendered in copper, with queued future phases drawn as blueprint outline and a construction crane standing still
A data center campus rendered as a plan: completed structures shown built, queued phases shown as outline. The watchlist records which projects have moved and which are on hold.
Tracked projects
344
delayed, cancelled, or under review
Local restrictions
1150
county, city, township measures
Utility actions
272
PUC dockets and statements
Active lawsuits
63
filed or in progress
Stalled since Jan 2024
$170B+
across 20 states (Carbon Direct)
Q1 2026 delayed / cancelled
$130B
75 projects (Fortune)
ERCOT capacity at risk
49.8 GW
$8B–$15B revenue (BNEF)
Transformer lead time
128 wks
large power, average

National interconnection queue

Every ISO plus vertically integrated utilities with a public row-level queue, as of 2026-09-28. The full row-level queue is refreshed weekly. ERCOT Batch Zero row-level classifications are not yet published per Market Notice M-A080326-01.

32,382
Total queue rows
4,445 GW
Total capacity requested
46
Rows flagged data center
92
Large-load / DC studies
By status
Withdrawn15,338
IA signed8,099
Active4,163
Unknown2,003
Other1,978
Study706
Suspended95
By source, ISO and utility
PJM9,263
Alliant Energy6,968
MISO3,873
CAISO2,281
Dominion Energy VA2,178
NYISO2,148
ERCOT2,003
ISO-NE1,751
SPP1,028
Ameren Illinois146
AEP Indiana Michigan91
Consumers Energy88
Evergy Kansas88
AEP PSO80
AEP Ohio72
We Energies58
PacifiCorp56
AEP SWEPCO47
Evergy Missouri40
El Paso Electric39
AEP APCo34
MidAmerican Energy32
Ameren Missouri18

Would you like the weekly update?

Every week we re-verify every project on this watchlist and publish what moved. You get one email when it goes out.

Also send me

Receive a short introduction on days 3, 7 and 14, plus the updates you select. Unsubscribe in one click. Privacy ·

You're on the list. The next weekly update will land in your inbox when it publishes.
You are subscribed. Read the latest tracker

Browse a section below. Download the full dataset (JSON) or review all sources and citations.

Government releases

Official statements and regulatory notices from the Governor of Texas, ERCOT, the PUCT, and the Texas Legislature on the data center audit and large-load interconnection process. Newest first.

AuthorityDateRelease
Governor Greg Abbott 2026-08-13 Governor Abbott Announces Galaxy, Compass Datacenters and Montera Infrastructure Commit to Comply With His Data Center Standards
Developer commitment to the audit and compliance standards
Governor Greg Abbott 2026-08-12 Governor Abbott Announces Google, Rowan and CleanSpark Commit to Comply With His Data Center Standards
Developer commitment to the audit and compliance standards
Governor Greg Abbott 2026-08-12 Governor Abbott Announces Core Scientific, Vantage Data Centers and SB Energy Commit to Comply With His Data Center Standards
Developer commitment to the audit and compliance standards
Governor Greg Abbott 2026-08-11 Governor Abbott Announces Edge ConneX and Stream Data Centers Commit to Comply With His Data Center Standards
Developer commitment to the audit and compliance standards
Governor Greg Abbott 2026-08-10 Governor Abbott Announces Meta Commits to Comply With His Data Center Standards
Developer commitment to the audit and compliance standards
Governor Greg Abbott 2026-08-10 Governor Abbott Announces OpenAI Commits to Comply With His Data Center Standards
Developer commitment to the audit and compliance standards
Governor Greg Abbott 2026-08-07 Governor Abbott Announces Skybox, Digital Realty and MARA Commit to Comply With His Data Center Standards
Developer commitment to the audit and compliance standards
Governor Greg Abbott 2026-08-06 Governor Abbott Announces QTS Data Centers Will Meet Texas Standards
Developer commitment to the audit and compliance standards
Governor Greg Abbott 2026-08-03 Governor Abbott Directs Comprehensive Data Center Audit
August 3 directive to audit and verify all data center interconnections before approval
ERCOT 2026-08-03 Market Notice M-A080326-01, Update Regarding Batch Zero Timelines and Processes
Batch Zero pause, ERCOT will miss August 7 deadline and seek a good cause exception
Governor Greg Abbott 2026-07-24 Governor Abbott Announces PUC and ERCOT Actions Protecting Residential Ratepayers From Data Center Costs
PUC and ERCOT ratepayer protection actions on data center costs
Governor Greg Abbott 2026-07-23 East Texas Data Center Withdraws After Falling Short of Governor Abbott's Standards
First project withdrawal under the data center standards
ERCOT 2026-06-23 Market Notice M-B062326-01, Implementation of the Batch Zero Process, PGRR145 and NPRR1325
Establishes the Batch Zero large load interconnection study process
ERCOT 2026-06-23 Market Notice M-B062326-04, Ending the Large Load Interconnection Study process under PGRR115 and Batch Zero submission deadlines
Transition from the prior process to Batch Zero
Governor Greg Abbott 2026-06-10 Governor Abbott Directs PUC and ERCOT to Shield Texans From Data Center Infrastructure Costs
Initial directive that data centers fund their own infrastructure costs
PUCT 2026-03-12 Project 58481, Proposal for Publication of 16 TAC 25.194, large load interconnection standards
Proposed rule implementing SB6, including per megawatt security and nonrefundable interconnection fee
Texas Senate 2025-06-20 Senate Bill 6, 89th Legislature, large load interconnection, operation, and cost of service, signed by the Governor
Statute directing PUCT to set large load interconnection standards
No matches.

Methodology and scope

This watchlist tracks U.S. data center projects, operators, and jurisdictional actions that carry a documented public paper trail: securities filings, regulatory dockets, litigation, government statements, utility filings, and trade press. It is maintained as a neutral reference. Entries are recorded as observed; the tracker does not rank projects or advocate an outcome.

  • Status reflects the most recent public signal for each entry. Where a project continues on schedule, that is recorded as plainly as a delay.
  • Capacity is shown in megawatts where reported, and left blank where not disclosed.
  • Local restrictions, utility dockets, lawsuits, and federal actions are drawn from primary filings and reputable outlets, each linked to its source.
  • The ERCOT queue snapshot is extracted directly from the ERCOT GIS Report.
  • Signals are collected on a recurring basis and reconciled into a single source of truth before publication.

Every citation on one page: Sources and citations. Companion policy map: SAVRN Data Center Moratorium Tracker. Capital side: North American Data Center Capital Atlas. Founder essay: The Queue Was the Fiction.

The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.
Check this address →
What is the Nationwide Data Center Delay Watchlist?

It is a continuously maintained, primary-sourced record of U.S. data center projects, jurisdictional actions, public-company exposure, and securities filings affected by delay, moratorium, litigation, and grid constraint. Each entry links to its documented public source, and it is maintained as a neutral reference.

How is a project's status determined?

Status reflects the most recent public signal for each entry: halted, delayed, cancelled, pending review, litigation active, audit paused, under appeal, or withdrawn. Where a project continues on schedule, that is recorded as plainly as a delay.

How are delay days measured?

Delay days are measured against the original announced target where available, or against the first documented delay date.

How often is the watchlist updated?

Signals are collected on a recurring basis from SEC EDGAR and trade-press feeds and reconciled into the single source of truth before publication.

How is this different from the Data Center Moratorium Tracker?

The Moratorium Tracker maps state and local policy measures. This watchlist tracks named projects, operators, public-company exposure, and securities filings, with delay status and cause for each. The two are companion references.

Nationwide Data Center Delay Watchlist

Get these tracker updates by email

A short introduction on days 3, 7 and 14, plus updates for this tracker. Unsubscribe at any time.

We use your address to send the introduction and updates described above. See our Privacy Policy.

You’re on the list. Your subscription is saved.