Utah Data Center Investment Tracker
Utah carries 11 named site commitments worth at least $13.0B in disclosed capital, set against 12 projects blocked, delayed or restricted, 1 cancelled or blocked and 9 delayed or under moratorium, as of October 8, 2026.
Who is investing in data centers in Utah?
Named data center sites in Utah
Each row is one site-level commitment with its capital provider, the figure the source states, and the status the source gives it. Capital is shown as one compact figure; the verbatim wording is in the row's sources.
| Site | Capital provider | Place | Capital | MW | Status | Sources |
|---|---|---|---|---|---|---|
QTS Eagle Mountain data center campus (SLC1) Backfill (not previously recorded). Construction began September 2025; third building topped out April 2026 (ABC4 17 April 2026; Layton and QTS release 20 April 2026) |
QTS Realty Trust (Blackstone) with Blackstone (QTS owner), Layton Construction (general contractor) |
Eagle Mountain, Utah County | $6.0B | n.a. | under construction | |
Eagle Mountain campus Expansion announced 14 September 2026 |
Meta Platforms with Rocky Mountain Power, Lydian Energy |
Eagle Mountain | ≥$3.0B | n.a. | expansion | |
Novva West Jordan campus |
Novva Data Centers | West Jordan | $2.0B | 175 | construction | |
CyrusOne US Army data center site, Utah announced spring 2026 |
CyrusOne with US Army |
n.a. | ~$2.0B | n.a. | announced | |
Project Beehive nuclear-powered data center campus Reported 30 September 2026 (NPR exclusive, from company documents); BLM application under completeness review; single outlet |
Valar Atomics with Bureau of Land Management (right-of-way application under review), State of Utah (about 650 acres of state land sought) |
Near Price, Carbon County | n.a. | 9,600 | proposed | |
Stratos Project AI data center campus (MIDA project area) MIDA project area approved April 2026; county approval May 2026; scale-back pledge August 2026; referendum lawsuit pending |
O'Leary Digital (Kevin O'Leary) with Military Installation Development Authority (MIDA), Box Elder County |
Hansel Valley, north of the Great Salt Lake, Box Elder County | n.a. | 9,000 | approved | |
Tract Pole Canyon technology tract |
Tract | n.a. | n.a. | 1,700 | announced | |
Volition data center, former Fingerhut warehouse (4000 E. U.S. 6), Spanish Fork Canyon Code amendment approved 21 September 2026 (3-2); reported 22 to 24 September 2026 |
Volition | Spanish Fork, Utah County | n.a. | 250 | proposed | |
Jurassic Spark data center and power campus Site selection reported in county minutes spring 2026; pipeline right-of-way agreement May 2026; reported 24 September 2026; single-outlet report (Salt Lake Tribune with Grist) |
Altigen with Carbon County (pipeline right-of-way) |
Wellington (east of), Carbon County | n.a. | n.a. | proposed | |
Salt Lake City facilities (two) |
Voltage Park | Salt Lake City | n.a. | n.a. | operating | |
US Army hyperscale program at Dugway Proving Ground (CyrusOne) initial operating capability FY2029 |
KKR with U.S. Army, GIP |
Dugway | n.a. | n.a. | announced |
Blocked, delayed or restricted in Utah
Every project in Utah on the atlas's capital-at-risk record: the action taken, who took it, and the announced capital affected. Restarts and reversals are recorded with the same weight as blocks.
| Project | Developer | Jurisdiction | Action | Capital | Sources |
|---|---|---|---|---|---|
40,000-acre / 9 GW campus other 2026 |
n.a. | Utah | Approved; referendum underway needing 5,422 signatures in 45 days |
n.a. | |
B+F Timpanogos Tech data center (1507 S. 180 East, East Bay) denied Denied unanimously 10 March 2026 |
B+F Timpanogos Tech | Provo City Council | The Provo City Council voted unanimously on Tuesday 10 March 2026 to deny the developer's request to apply the city's data center overlay zone to the property, the first application under that overlay. The planning commission had recommended approval on 11 February 2026. Council members cited noise, environmental and energy cost concerns and said they want results from an economic development study first. |
n.a. | |
Box Elder County data center moratorium (Stratos exempt) moratorium Approved 10 June 2026; 180 days, Stratos exempt |
n.a. (county-wide land use action) | Box Elder County | Box Elder County commissioners approved a 180-day halt on new data center development on 10 June 2026 to study guidelines and address concerns raised by the Stratos controversy. The county stated the ordinance does not permanently prohibit data centers but establishes a temporary planning period for research, analysis, public participation and policy development. The Stratos project, described as a data center with up to 9 gigawatts of power generating capacity and already approved, is exempt from the moratorium. The Military Installation Development Authority approved the Stratos project area in April 2026 and the project area was later reduced. The record here is that the county's pause did not reach the capacity already entitled. |
n.a. | |
Cache County temporary data center moratorium moratorium Approved unanimously 23 June 2026; 180 days |
n.a. | Cache County Council | The Cache County Council unanimously approved Ordinance 2026-32 at its 23 June 2026 meeting, establishing a temporary moratorium on proposed data centers in unincorporated areas. The ordinance cites a compelling public interest in protecting grid capacity, water resources and zoning integrity. Council Chair Sandi Goodlander said no utility-scale data center developer had approached the county. The vote followed controversy over a data center campus in neighboring Box Elder County. |
n.a. | |
Clearfield 180-day data center moratorium moratorium Approved 4-0 on 8 September 2026; 180 days |
n.a. (city-wide land use action) | City of Clearfield | The Clearfield City Council voted 4-0 on 8 September 2026 to freeze all data center development in the city for 180 days, although no such project had been proposed there. City staff proposed the moratorium to study land use and infrastructure questions before a developer applies; the city's code does not currently define a data center. Mayor Mark Shepherd pointed to the grandiose scale of the Stratos campus taking shape in Box Elder County during the discussion. Logan adopted a 180-day moratorium on data center and power plant development on 30 June 2026 and Iron County commissioners passed one on 26 May 2026. |
n.a. | |
Grand County data center moratorium moratorium Enacted July 2026 |
n.a. | Grand County | Grand County, Utah, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated July 2026. 180-day temporary land use regulation, unanimous: pauses acceptance, processing and approval of applications, permits and licenses for data centers, data center power plants and associated digital infrastructure. Pre-emptive. nothing was in the queue. The measure runs to 3 January 2027. |
n.a. | |
Iron County 180-day data center and solar moratorium moratorium Adopted unanimously 26 May 2026; ends 22 November 2026 |
n.a. | Iron County | The Iron County Commission unanimously adopted a 180-day moratorium on 26 May 2026 covering data centers, data center power plants and solar plants; it ends 22 November 2026 and cannot be extended. A replacement ordinance limiting water use, noise and light and raising permit fees goes to a Planning Commission hearing on 8 October 2026. |
n.a. | |
Logan 180-day data center and data center power plant moratorium moratorium Approved unanimously 30 June 2026; 180 days |
n.a. | Logan Municipal Council | At a special meeting on 30 June 2026, the Logan Municipal Council unanimously approved Ordinance 26-12, a 180-day temporary land use moratorium on data centers and data center power plants. The city will not accept, process, approve or issue any application or permit authorizing their construction during the pause. Council Chair Mike Johnson said the delay gives staff time to write regulations, and the city scheduled a 28 July open house for resident input. |
n.a. | |
Milford data center moratorium moratorium Enacted June 2026 |
n.a. | Milford | Milford, Utah, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated June 2026. Ordinance 04-2026: 180-day moratorium on data centers, data center power plants, and solar energy facilities; 5-0 unanimous. Council determined data centers are not appropriate land use within city limits. The measure runs to 13 December 2026. |
n.a. | |
Mona area data center approval process challenge under appeal Conditional use permit approved at a 15 April 2026 hearing; resident challenge reported 8 September 2026; appeal filed with Juab County Commission 15 September 2026 |
Not identified in reporting | Juab County | Residents of the Mona area are challenging how a proposed data center of roughly 3 million square feet, described in reporting as a $10 billion project and the largest in Juab County's history, was approved with little public input. County commissioners did not approve the project themselves: planning officials cleared it through a zone change and a conditional use permit, and the public hearing on 15 April 2026 lasted about four minutes with only the county, the selling landowners and the developers present. Residents say they learned of the project only recently and are asking how the zone change was presented to the public and how the conditional use permit was approved, and are demanding a public hearing before any further decision rather than after it is final. No approval has been rescinded and no litigation is recorded here; this is a live challenge to the process. The capital figure is left blank because the $10 billion is a press characterization, not a disclosed commitment. On Tuesday 15 September 2026 the community group Mona Cares filed an appeal asking the Juab County Commission to overturn the conditional use permit, arguing the county did not give residents adequate and actual notice. Commission Chair Clint Painter said the county followed state notice requirements and warned that reversing the approval could expose the county to costly developer lawsuits. Appeals are normally due within 30 days; the group argues the August posting of the meeting minutes supports accepting it. Whether the commission will accept the appeal had not been decided. |
n.a. | |
Salt Lake County pause pending data center rules (unincorporated areas) paused Resolution adopted 15 September 2026; rules expected spring 2027 |
n.a. | Salt Lake County Council | On Tuesday 15 September 2026 the County Council voted unanimously for a resolution directing staff to draft data center rules for unincorporated areas; no new data centers will be considered until the rules are adopted, expected next spring, with a council review of the draft ordinance by mid-February 2027. |
n.a. | |
Wayne County data center moratorium moratorium Enacted July 2026 |
n.a. | Wayne County | Wayne County, Utah, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated July 2026. Resolution 2026-04: immediate 180-day moratorium on all land use applications for data centers, data center power plants (explicitly including nuclear) and supporting digital infrastructure, unanimous. County code did not address data centers at all. The measure runs to 17 January 2027. |
n.a. |
Financing transactions tied to Utah sites
Transactions the atlas ties to a named site in Utah: joint ventures, project bonds, credit facilities, leases and power agreements. Amounts are as stated; overlapping commitments are never summed.
| Parties | Instrument | Amount | Date | Site | Sources |
|---|---|---|---|---|---|
Novva Data Centers + JPMorgan + Starwood Novva secured $2B of financing led by JPMorgan with Starwood participation for a 175 MW West Jordan, Utah campus. |
debt facility | $2.0B | not dated in source | Novva West Jordan campus |
What governs a data center in Utah
The policy layer for Utah lives in three companion references: the Utah Data Center Moratorium Tracker for every state measure and local moratorium on record, the Water Tracker for the water rules that touch a site, and the Grid Operator Watchlist for the large-load rules of the RTO or utility that decides whether it can energize.
States next door
Data centers in Utah
The US Data Center Map identifies 49 facilities run by 20 operators in Utah, each one placed from primary sources and listed by city and by operator, with this atlas record beside it.
Sources for Utah
Every source cited on this page, once each. The full atlas source register is at Capital Atlas sources.
- abc4.comABC4 Utah, 17 April 2026
- utahbusiness.comLayton Construction and QTS release (Utah Business), 20 April 2026
- datacenterdynamics.comDCD
- datacenters.atmeta.comMeta Data Centers
- msn.comKUTV via MSN
- msn.comABC4 via MSN
- novva.comNovva
- enr.comENR
- illinoistimes.comIllinois Times
- npr.orgNPR, 30 September 2026
- msn.comSalt Lake Tribune (via MSN)
- finance.yahoo.comBusiness Insider (via Yahoo Finance), 10 August 2026
- msn.comTheStreet (via MSN), 16 August 2026
- entrepreneur.comEntrepreneur, 11 May 2026
- ksl.comKSL.com, 1 October 2026
- tract.comTract
- msn.comThe Salt Lake Tribune (via MSN)
- sltrib.comThe Salt Lake Tribune
- fox13now.comFOX 13 Salt Lake City
- msn.comThe Salt Lake Tribune (via MSN), 24 September 2026
- voltagepark.comVoltage Park
- datacenterdynamics.comDCD
- army.milU.S. Army
- datacenterdynamics.comDCD
- floridadatacenters.orgFlorida Data Centers
- ksl.comKSL (12 March 2026)
- ksl.comKSL
- upr.orgUtah Public Radio
- cachevalleydaily.comCache Valley Daily
- sltrib.comThe Salt Lake Tribune
- standard.netStandard-Examiner
- ksl.comKSL
- moabtimes.commoabtimes.com
- upr.orgUtah Public Radio
- ironcountyut.govIron County ordinance
- ironcountyut.govIron County planning
- sltrib.comSalt Lake Tribune
- sltrib.comSalt Lake Tribune
- cachevalleydaily.comCache Valley Daily
- postregister.comPost Register
- utah.govutah.gov
- ksl.comKSL
- deseret.comDeseret News
- abc4.comABC4
- ksl.comKSL
- sltrib.comSalt Lake Tribune
- sltrib.comSalt Lake Tribune
- ironcountytoday.comironcountytoday.com
- latitudemedia.comLatitude Media
- kiowacountypress.netUtah News Dispatch via Kiowa County Press
Every state, one page each
Figures beside each state are named sites and blocked, delayed or restricted projects.
Seven references, one system
Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.