State Connections

Explore a state’s data center issues, find states with similar evidence, and assemble a sourced working brief.

View my comparison →
Orange is your starting state.
Blue states share the selected kind of evidence.

Source statuses are retained as recorded. Existing tracker records have not all been freshly reverified for this view.

Start with Connected states. Review why a state matches, then add it to your working group.

Who is working through similar issues?

Open a state to inspect its evidence. Add states to a potential working group.

Use the map or state selector above to explore each state's published evidence.

Utah: inspect the evidence.

Counts are records, not unique projects. Records can overlap across trackers.

40,000-acre / 9 GW campus Record-specific: Utah · other

Approved; referendum underway needing 5,422 signatures in 45 days

2026

Florida Data Centers ↗
B+F Timpanogos Tech data center (1507 S. 180 East, East Bay) Record-specific: Provo City Council · denied

The Provo City Council voted unanimously on Tuesday 10 March 2026 to deny the developer's request to apply the city's data center overlay zone to the property, the first application under that overlay. The planning commission had recommended approval on 11 February 2026. Council members cited noise, environmental and energy cost concerns and said they want results from an economic development study first.

Denied unanimously 10 March 2026

KSL (12 March 2026) ↗
Box Elder County data center moratorium (Stratos exempt) Record-specific: Box Elder County · moratorium

Box Elder County commissioners approved a 180-day halt on new data center development on 10 June 2026 to study guidelines and address concerns raised by the Stratos controversy. The county stated the ordinance does not permanently prohibit data centers but establishes a temporary planning period for research, analysis, public participation and policy development. The Stratos project, described as a data center with up to 9 gigawatts of power generating capacity and already approved, is exempt from the moratorium. The Military Installation Development Authority approved the Stratos project area in April 2026 and the project area was later reduced. The record here is that the county's pause did not reach the capacity already entitled.

Approved 10 June 2026; 180 days, Stratos exempt

KSL ↗ Utah Public Radio ↗
Cache County temporary data center moratorium Record-specific: Cache County Council · moratorium

The Cache County Council unanimously approved Ordinance 2026-32 at its 23 June 2026 meeting, establishing a temporary moratorium on proposed data centers in unincorporated areas. The ordinance cites a compelling public interest in protecting grid capacity, water resources and zoning integrity. Council Chair Sandi Goodlander said no utility-scale data center developer had approached the county. The vote followed controversy over a data center campus in neighboring Box Elder County.

Approved unanimously 23 June 2026; 180 days

Cache Valley Daily ↗ The Salt Lake Tribune ↗
Clearfield 180-day data center moratorium Record-specific: City of Clearfield · moratorium

The Clearfield City Council voted 4-0 on 8 September 2026 to freeze all data center development in the city for 180 days, although no such project had been proposed there. City staff proposed the moratorium to study land use and infrastructure questions before a developer applies; the city's code does not currently define a data center. Mayor Mark Shepherd pointed to the grandiose scale of the Stratos campus taking shape in Box Elder County during the discussion. Logan adopted a 180-day moratorium on data center and power plant development on 30 June 2026 and Iron County commissioners passed one on 26 May 2026.

Approved 4-0 on 8 September 2026; 180 days

Standard-Examiner ↗ KSL ↗
CyrusOne US Army data center site, Utah Record-specific: · announced

CyrusOne announced a ~$2B, 1,200-acre US Army data center site in Utah in spring 2026. ~$2B 1,200-acre site

announced spring 2026

Illinois Times ↗
Eagle Mountain campus Record-specific: Eagle Mountain · expansion

Meta's latest two-building expansion will add around 2 million square feet to the Eagle Mountain campus and bring total capital investment in the project to $1.5 billion, up from an original $750 million plan of 1,000,000 sq ft. On 14 September 2026 Meta announced a further expansion of the Eagle Mountain Data Center, taking its Utah investment to more than $3 billion, with more than 1,200 construction workers at peak and more than 300 jobs once complete. Meta cited more than 1.7 GW of new renewable energy across 13 Utah projects, 600 MWh of battery storage and support for a 150 MW Faraday Energy Storage project, and uses closed-loop liquid cooling with dry cooling On 14 September 2026 Meta announced a further expansion of its Eagle Mountain data center, bringing its total Utah investment to more than $3 billion with more than 1,200 peak construction jobs and more than 300 jobs after completion. Community commitments include a $600,000 grant for the Lake Mountain School District to buy three acres for an elementary school, $450,000 for the Walden Park observatory, and $1.5 million plus $50,000 a year to the Lake Mountain Education Foundation. Meta also cited the 150 MW Faraday Energy Storage battery project expected online later in 2026 more than $3 billion total Utah investment per Meta on 14 September 2026, up from the $1.5 billion previously recorded

Expansion announced 14 September 2026

DCD ↗ Meta Data Centers ↗ KUTV via MSN ↗ ABC4 via MSN ↗
Grand County data center moratorium Record-specific: Grand County · moratorium

Grand County, Utah, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated July 2026. 180-day temporary land use regulation, unanimous: pauses acceptance, processing and approval of applications, permits and licenses for data centers, data center power plants and associated digital infrastructure. Pre-emptive. nothing was in the queue. The measure runs to 3 January 2027.

Enacted July 2026

moabtimes.com ↗
Iron County 180-day data center and solar moratorium Record-specific: Iron County · moratorium

The Iron County Commission unanimously adopted a 180-day moratorium on 26 May 2026 covering data centers, data center power plants and solar plants; it ends 22 November 2026 and cannot be extended. A replacement ordinance limiting water use, noise and light and raising permit fees goes to a Planning Commission hearing on 8 October 2026.

Adopted unanimously 26 May 2026; ends 22 November 2026

Utah Public Radio ↗ Iron County ordinance ↗ Iron County planning ↗ Salt Lake Tribune ↗ Salt Lake Tribune ↗
Jurassic Spark data center and power campus Record-specific: Wellington (east of) · proposed

Altigen, which builds natural gas plants for data centers, selected about 1,200 acres east of Wellington, Utah for its 'Jurassic Spark' data center campus, per Carbon County Community Economic Development Board minutes. Commissioner Larry Jensen said the plan calls for a 250 MW gas plant initially, possibly growing to 3 GW. In May 2026 the county commission unanimously approved a preliminary agreement to take ownership of a pipeline right-of-way through BLM land for the project. Altigen did not comment. On-site natural gas plant, 250 MW initially and up to 3 GW; gas via a pipeline right-of-way across BLM land that the county agreed preliminarily to take ownership of in May 2026 Not disclosed Data center IT MW not disclosed; gas plant 250 MW initially, potentially 3 GW per Commissioner Larry Jensen

Site selection reported in county minutes spring 2026; pipeline right-of-way agreement May 2026; reported 24 September 2026; single-outlet report (Salt Lake Tribune with Grist)

The Salt Lake Tribune (via MSN), 24 September 2026 ↗
Logan 180-day data center and data center power plant moratorium Record-specific: Logan Municipal Council · moratorium

At a special meeting on 30 June 2026, the Logan Municipal Council unanimously approved Ordinance 26-12, a 180-day temporary land use moratorium on data centers and data center power plants. The city will not accept, process, approve or issue any application or permit authorizing their construction during the pause. Council Chair Mike Johnson said the delay gives staff time to write regulations, and the city scheduled a 28 July open house for resident input.

Approved unanimously 30 June 2026; 180 days

Cache Valley Daily ↗ Post Register ↗
Milford data center moratorium Record-specific: Milford · moratorium

Milford, Utah, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated June 2026. Ordinance 04-2026: 180-day moratorium on data centers, data center power plants, and solar energy facilities; 5-0 unanimous. Council determined data centers are not appropriate land use within city limits. The measure runs to 13 December 2026.

Enacted June 2026

utah.gov ↗
Mona area data center approval process challenge Record-specific: Juab County · under_appeal

Residents of the Mona area are challenging how a proposed data center of roughly 3 million square feet, described in reporting as a $10 billion project and the largest in Juab County's history, was approved with little public input. County commissioners did not approve the project themselves: planning officials cleared it through a zone change and a conditional use permit, and the public hearing on 15 April 2026 lasted about four minutes with only the county, the selling landowners and the developers present. Residents say they learned of the project only recently and are asking how the zone change was presented to the public and how the conditional use permit was approved, and are demanding a public hearing before any further decision rather than after it is final. No approval has been rescinded and no litigation is recorded here; this is a live challenge to the process. The capital figure is left blank because the $10 billion is a press characterization, not a disclosed commitment. On Tuesday 15 September 2026 the community group Mona Cares filed an appeal asking the Juab County Commission to overturn the conditional use permit, arguing the county did not give residents adequate and actual notice. Commission Chair Clint Painter said the county followed state notice requirements and warned that reversing the approval could expose the county to costly developer lawsuits. Appeals are normally due within 30 days; the group argues the August posting of the meeting minutes supports accepting it. Whether the commission will accept the appeal had not been decided.

Conditional use permit approved at a 15 April 2026 hearing; resident challenge reported 8 September 2026; appeal filed with Juab County Commission 15 September 2026

KSL ↗ Deseret News ↗ ABC4 ↗ KSL ↗ Salt Lake Tribune ↗
Novva West Jordan campus Record-specific: West Jordan · construction

Novva secured $2B of financing led by JPMorgan with Starwood participation for the 175 MW West Jordan, Utah campus, following an earlier $355M CIM Group equity round. $2B financing 175 MW campus

Date not recorded

Novva ↗ ENR ↗
Project Beehive nuclear-powered data center campus Record-specific: Near Price · proposed

Valar Atomics has applied to the Bureau of Land Management to use more than 9,000 acres of federal land near Price, Utah for Project Beehive, which would combine data centers with about 456 small nuclear reactors producing around 9.6 GW, a nuclear fuel production facility and waste storage, according to documents reviewed by NPR. Valar has also sought about 650 acres of state land for the project. BLM's Utah office confirmed it received the application and is reviewing it for completeness before NEPA review. The timeline calls for non-nuclear construction as early as the end of 2026, first reactors in 2028 and full completion by 2032. Valar did not respond to NPR. On-site small modular reactors (about 456 Valar 25 MWe units), plus a nuclear fuel production facility and waste storage on site Not disclosed About 456 small reactors of 25 MW electric each producing around 9.6 GW for the data centers, per the company proposal reviewed by NPR

Reported 30 September 2026 (NPR exclusive, from company documents); BLM application under completeness review; single outlet

NPR, 30 September 2026 ↗

Follow the issue to the utility and the customer.

Named organizations come from explicit record fields. Their presence is not confirmation of a serving-utility relationship, service availability, or customer eligibility.

Named parties in this state's evidence

Start from your position.

Screen an individual location ↗

Address-level utility verification and service agreements belong in the site screen. Private account data and individual household identities are not part of this public dataset.

Regional grid context and rules
Open the complete grid operator watchlist ↗

Explore generation and interconnection queues ↗ · Explore scarcity and market constraints ↗

Your comparison

See what your selected states have in common.

We bring together the shared issues and source records for the states you choose.

States appear side by side. Compare each topic, then open a cell for sources.

Add your own notes Optional

Notes are included when you open or save the comparison. Save a copy to keep them after leaving this page.

Sharing and data options

The link includes your states and issue filter. It does not include private notes. Source data downloads as JSON.

Your comparison

State comparison

Save a copy
Coverage, sources and how states are connected

All 50 states are selectable. A connection requires the same documented policy mechanism or the same structured tracker classification and status. The map is a discovery tool, not a legal-equivalence score, a project-risk ranking, or a complete census. No match means no matching evidence in this view.

Existing tracker publications supply most records. Their source status and date are retained; a page load is not a new source verification. Proposed, failed, enacted and reversed records remain distinct. Explicitly unverified or pending-review rows are excluded. Narrative and status can disagree in the underlying publication; inspect both before treating a restriction as active. No state-wide effect is inferred from a local action.

Data is read from the current tracker files and published overlays. Source changes invalidate the server's cached connections. Policy mechanisms use a separately reviewed evidence set. Generation queues and broad company commitments are not assigned to a data center or customer. Federal records and records without an explicit state are not assigned to a state by inference.

Download state evidence JSON · SAVRN methodology

Underlying dataset credits
  • 6abc Philadelphia
  • AEP Ohio Transmission Company (filed with Ohio Power Siting Board)
  • AI GridWatch moratorium tracker, CC BY 4.0 (aigridwatch.com)
  • Alabama Reflector
  • Alaska Beacon
  • American Transmission Company LLC (filed with PSC of Wisconsin)
  • Americus Times-Recorder
  • Arizona Mirror
  • Arkansas Advocate
  • Axios Pro Energy
  • Bisnow
  • Bisnow National
  • Bradenton Herald
  • CNBC Technology
  • Cardinal News VA
  • Central Florida Public Media
  • Chesterfield County public permit records
  • Chicago Construction News
  • City of Atlanta public permit records
  • City of Austin issued construction permits open data
  • City of Buckeye public permit records
  • City of Chandler public permit records
  • City of Charlotte public permit records
  • City of Chicago building permits open data
  • City of Fort Worth public permit records
  • City of Goodyear public permit records
  • City of Hillsboro public permit records
  • City of Mesa building permits open data
  • City of Mesa public permit records
  • City of Minneapolis construction permits (CCS) open data
  • City of Papillion public permit records
  • City of Phoenix public permit records
  • City of Red Oak public permit records
  • City of Reno public permit records
  • City of San Antonio public permit records
  • City of Statesboro, Georgia
  • City of Temple, Texas
  • Clearfield City Council (Utah Public Notice Website)
  • Colorado Newsline
  • Colorado Public Radio
  • Congress.gov (Library of Congress, public domain)
  • ConstructConnect News
  • Construction Dive
  • CourtListener DataCenter Dockets
  • CourtListener Opinions
  • Data Center Dynamics
  • Data Center Dynamics news
  • DataCenterTracker.org, CC BY 4.0
  • Dominion Energy Virginia
  • EIN News
  • East Bay Insiders Newsletter
  • Energy Central
  • FOX19 | Cincinnati
  • FOX5 Vegas
  • FOX6 News Milwaukee
  • Facilities Dive
  • Fairfax County public permit records
  • Florida Phoenix
  • Georgia Department of Community Affairs
  • Georgia EPD air permit records
  • Georgia Recorder
  • GovTech
  • Greensboro News and Record
  • Grist
  • Idaho Capital Sun
  • Illinois EPA air permit records
  • Indiana Capital Chronicle
  • Indiana Department of Environmental Management
  • Indiana IDEM air permit records
  • InkFreeNews.com
  • Iowa Capital Dispatch
  • Iowa DNR air permit records
  • KERA News
  • KEYC News Now
  • KGW
  • KRON4
  • Kansas City MO city issued permits open data
  • Kansas Reflector
  • Kentucky Lantern
  • Law360
  • Law360 Energy
  • LegiScan (legiscan.com) and the state legislature
  • Lehigh Valley Planning Commission
  • Local News Matters
  • Loudoun County public permit records
  • Loudoun Times-Mirror
  • Louisiana DEQ air permit records
  • Louisiana Illuminator
  • Maine Morning Star
  • Maricopa County Air Quality Department air permit records
  • Maricopa County public permit records
  • Maryland Matters
  • Mecklenburg County public permit records
  • Michigan Advance
  • Mid Bay News
  • Missouri Independent
  • Montana Free Press
  • NBC Bay Area
  • NBC4 Washington
  • NC Newsline
  • Native News Online
  • Nebraska Examiner
  • Nevada Current
  • Nevada NDEP air permit records
  • New Hampshire Bulletin
  • New Mexico Environment Department
  • North Carolina DEQ Division of Air Quality air permit records
  • North Dakota Department of Environmental Quality
  • North Dakota Monitor
  • Ohio Capital Journal
  • Ohio EPA air permit records
  • Oklahoma DEQ air permit records
  • Oklahoma Voice
  • OpenStates v3 (openstates.org), CC BY 4.0
  • Oregon Capital Chronicle
  • Orlando Sentinel
  • Pennsylvania Capital-Star
  • Pennsylvania Department of Environmental Protection
  • Pennsylvania Office of Consumer Advocate (filed with PA PUC)
  • Pioneer Press
  • Prince William County public permit records
  • Public Service Commission of Wisconsin
  • Public record (Legistar Web API, Granicus)
  • Rhode Island Current
  • Route Fifty
  • SEC EDGAR company submissions, public domain
  • SEC EDGAR full-text search, public domain
  • Searchlight New Mexico
  • Smithfield Township, Monroe County, PA
  • Source New Mexico
  • South Carolina Department of Environmental Services
  • South Dakota Searchlight
  • Springfield Daily Citizen
  • Stafford County public permit records
  • Statesman Journal
  • Strisker data center notes
  • Tennessee Lookout
  • Texas Commission on Environmental Quality
  • Texas TCEQ air permit records
  • The Baltimore Banner
  • The Current (GA)
  • The Detroit News
  • The Hill Energy
  • The North State Journal
  • The Pantagraph
  • The Real Deal
  • The Register
  • The Texas Tribune
  • The Verge
  • Times-Standard
  • Town of Culpeper public permit records
  • Tuscaloosa Thread
  • U.S. EPA ECHO
  • Union-Bulletin
  • Uprise RI
  • Utah Division of Air Quality
  • Utah Division of Air Quality air permit records
  • Utah News Dispatch
  • Utah Public Radio
  • Utility Dive
  • Virginia Business
  • Virginia DEQ air permit records
  • Virginia Electric and Power Company (filed with Virginia SCC)
  • Virginia Mercury
  • Visalia Times-Delta
  • WBUR
  • WCPO 9 Cincinnati
  • WGLT
  • WHEC.com
  • WJON
  • WKYT
  • WLOS
  • WLUK
  • WPBF
  • WQCS
  • WRAL (NC)
  • WUNC News
  • WVPE
  • Washington County public permit records
  • Washington Ecology air permit records
  • Washington State SEPA Register public permit records
  • Washington State Standard
  • Washoe County public permit records
  • Wausau Pilot & Review
  • West Virginia Watch
  • Winston-Salem Journal
  • Wisconsin Department of Natural Resources
  • Wisconsin Examiner
  • Yale Daily News
  • citybiz
  • contracosta.news
  • ictnews.org
  • indianapublicradio.org
  • inkfreenews.com
  • lex18.com
  • mountaintimesoregon.com
  • newmedia-wi.com
  • newscentermaine.com
  • thegazette.com
  • tuscaloosathread.com
  • wcpo.com
  • www.cities929.com

SAVRN Policy Connections

How state policies connect.

Find shared policy mechanisms, compare the differences, and assemble a framework from documented state provisions.

9 states with documented provisions29 provisions · 14 mechanisms · all 50 states available for comparison

An initial evidence set, not an exhaustive survey. A missing relationship means not documented here, never no policy. Source review verifies the cited instrument, not every later amendment or implementing action. Sources reviewed 3 October 2026.

Shared goals. Different requirements.

Each number opens the provisions connecting a state to a policy family. States can belong to several groups. A shared family is not proof of identical law.

Documented relationships by policy family. A dash means not documented in this evidence set.
StateProject readinessCost responsibilityGrid flexibilityWater safeguardsReporting & oversightEnergy & emissionsLocal authorityEnvironmental review
Georgia–2––––––
Indiana–3––1–––
Minnesota–2–1–1––
New York–––1–––2
Ohio–1––––––
Oregon–2––11––
South Dakota–2–11–1–
Texas111––1––
Virginia––––2–––

Choose a mechanism to see states connected by that specific policy tool.

Inspect the provision, not just the category.

All 29 documented provisions. Open a record for its source, scope, and difference from similar tools.

Texas Verify the proposed site Documented in cited instrument

Interconnection standards must include a way to demonstrate a legal interest in the proposed location.

Shared mechanism
Evidence of site control
Scope
ERCOT large-load interconnection; applicability and exceptions in the statute.
Important difference
Evidence of site control does not establish that all permits or financing are secured.
Source location
Section 37.0561(g)
Texas SB 6, enrolled text ↗

Statutory text · Source reviewed 2026-10-03

Texas Back transmission commitments Documented in cited instrument

Standards must set financial commitments supporting transmission infrastructure for covered loads.

Shared mechanism
Financial security
Scope
ERCOT large-load interconnection; applicability and exceptions in the statute.
Important difference
Permitted security forms and release rules depend on implementation; not a minimum energy bill.
Source location
Section 37.0561(h)-(j)
Texas SB 6, enrolled text ↗

Statutory text · Source reviewed 2026-10-03

Texas Define emergency response Documented in cited instrument

Covered backup-equipped loads may be directed to deploy backup generation or curtail after the specified market-service sequence.

Shared mechanism
Emergency response
Scope
ERCOT large-load interconnection; applicability and exceptions in the statute.
Important difference
An emergency mechanism, not a general voluntary demand-response tariff.
Source location
Section 37.0561(e)
Texas SB 6, enrolled text ↗

Statutory text · Source reviewed 2026-10-03

Texas Retain emissions limits Documented in cited instrument

Emergency direction does not authorize violation of emissions or environmental requirements.

Shared mechanism
Emissions safeguards
Scope
ERCOT large-load interconnection; applicability and exceptions in the statute.
Important difference
Backup generation remains constrained by applicable environmental rules.
Source location
Section 37.0561(e)(1)
Texas SB 6, enrolled text ↗

Statutory text · Source reviewed 2026-10-03

Minnesota Assign attributable utility costs Documented in cited instrument

Commission review of very-large-customer service terms must address attributable costs and protection of other customers.

Shared mechanism
Attributable-cost allocation
Scope
Scope varies by section: data-center water provisions, public-utility service, and optional clean-energy contracts.
Important difference
A regulatory framework with customer-class and agreement decisions, not a uniform minimum billing percentage.
Source location
Section 9, subdivision 2
Minnesota 2025 special-session Chapter 12 ↗

Session law · Source reviewed 2026-10-03

Minnesota Protect against stranded costs Documented in cited instrument

Tariff or agreement review must include protections against other customers paying stranded service costs.

Shared mechanism
Departure / reduced-load protection
Scope
Scope varies by section: data-center water provisions, public-utility service, and optional clean-energy contracts.
Important difference
Existing-service exceptions appear in subdivision 3.
Source location
Section 9, subdivision 2(3)
Minnesota 2025 special-session Chapter 12 ↗

Session law · Source reviewed 2026-10-03

Minnesota Evaluate consumptive water demand Documented in cited instrument

Preapplication review links covered consumptive demand and permit needs to site-specific water availability.

Shared mechanism
Water-supply review
Scope
Scope varies by section: data-center water provisions, public-utility service, and optional clean-energy contracts.
Important difference
Facility definition and water-use/permit conditions apply together; not all withdrawals trigger this review.
Source location
Sections 3-4
Minnesota 2025 special-session Chapter 12 ↗

Session law · Source reviewed 2026-10-03

Minnesota Offer optional clean-energy service Documented in cited instrument

Utilities must offer a clean-energy and capacity tariff with participating customers paying proportional resource costs.

Shared mechanism
Clean-energy service terms
Scope
Scope varies by section: data-center water provisions, public-utility service, and optional clean-energy contracts.
Important difference
Customer participation is optional; do not classify it as a universal clean-energy purchase mandate.
Source location
Section 10
Minnesota 2025 special-session Chapter 12 ↗

Session law · Source reviewed 2026-10-03

South Dakota Recover attributable electricity costs Documented in cited instrument

Separate service terms must recover costs fairly attributable to the data center.

Shared mechanism
Attributable-cost allocation
Scope
Statutorily defined data centers; electricity providers, water providers, and local governments.
Important difference
Applies through provider terms rather than a published statewide minimum billing percentage.
Source location
Section 3
South Dakota SB 135, Chapter 190 ↗

Session law · Source reviewed 2026-10-03

South Dakota Address departure and reduced load Documented in cited instrument

Cost responsibility includes costs incurred if the customer departs or materially reduces load.

Shared mechanism
Departure / reduced-load protection
Scope
Statutorily defined data centers; electricity providers, water providers, and local governments.
Important difference
The law states cost responsibility; it does not supply a universal exit-fee formula.
Source location
Section 3
South Dakota SB 135, Chapter 190 ↗

Session law · Source reviewed 2026-10-03

South Dakota Obtain local supply determinations Documented in cited instrument

Water providers assess compatibility, with board review and allocation limits protecting priority uses.

Shared mechanism
Water-supply review
Scope
Statutorily defined data centers; electricity providers, water providers, and local governments.
Important difference
Local supply determinations are distinct from the Minnesota consumptive-use permit review.
Source location
Section 5
South Dakota SB 135, Chapter 190 ↗

Session law · Source reviewed 2026-10-03

South Dakota Publish water-use data Documented in cited instrument

Operators report usage to the board, which makes usage data available to the public.

Shared mechanism
Water-use reporting
Scope
Statutorily defined data centers; electricity providers, water providers, and local governments.
Important difference
Operator reporting differs from Virginia supplier category reporting.
Source location
Section 6
South Dakota SB 135, Chapter 190 ↗

Session law · Source reviewed 2026-10-03

South Dakota Preserve local regulation Documented in cited instrument

The state may not limit local authority to regulate data-center development or operation.

Shared mechanism
Preserved local authority
Scope
Statutorily defined data centers; electricity providers, water providers, and local governments.
Important difference
Preservation of local authority is not evidence that a local ban exists.
Source location
Section 4
South Dakota SB 135, Chapter 190 ↗

Session law · Source reviewed 2026-10-03

Ohio Address underused infrastructure risk Documented in cited instrument

PUCO adopted a settlement aimed at protecting other customers from cost shifting due to underused data-center investments.

Shared mechanism
Attributable-cost allocation
Scope
AEP Ohio data-center tariff proceeding; not a tariff for every Ohio utility.
Important difference
The cited announcement directs tariff filing; consult the filed tariff for binding customer terms.
Source location
Decision announcement, case background
PUCO decision announcement, case 24-508-EL-ATA ↗

Commission decision announcement · Source reviewed 2026-10-03

Indiana Set minimum billing obligations Documented in cited instrument

The approved settlement establishes minimum billing-demand and charge provisions for covered large loads.

Shared mechanism
Minimum payment commitments
Scope
Indiana Michigan Power Tariff I.P., Indiana jurisdiction; covered large-load customers.
Important difference
The approved settlement differs from the original utility proposal; I&M territory only.
Source location
Order pp. 32-35 and ordering paragraphs p. 49
IURC order, Cause 46097 ↗

Commission order · Source reviewed 2026-10-03

Indiana Address early termination Documented in cited instrument

The approved settlement contains contract termination protections for covered large-load service.

Shared mechanism
Departure / reduced-load protection
Scope
Indiana Michigan Power Tariff I.P., Indiana jurisdiction; covered large-load customers.
Important difference
Customer-specific conditions and the settlement govern; not statewide terms for every provider.
Source location
Settlement agreement; order approval pp. 49-50
IURC order, Cause 46097 ↗

Commission order · Source reviewed 2026-10-03

Indiana Require collateral arrangements Documented in cited instrument

The approved settlement includes financial-security terms for covered large-load customers.

Shared mechanism
Financial security
Scope
Indiana Michigan Power Tariff I.P., Indiana jurisdiction; covered large-load customers.
Important difference
Collateral and exceptions depend on tariff eligibility and customer circumstances.
Source location
Settlement agreement; order approval pp. 49-50
IURC order, Cause 46097 ↗

Commission order · Source reviewed 2026-10-03

Indiana Report large-load developments Documented in cited instrument

The order addresses recurring reports and protection of confidential information.

Shared mechanism
Regulatory reporting
Scope
Indiana Michigan Power Tariff I.P., Indiana jurisdiction; covered large-load customers.
Important difference
Regulator access is not equivalent to public disclosure of all reported data.
Source location
Order p. 49
IURC order, Cause 46097 ↗

Commission order · Source reviewed 2026-10-03

Georgia Allocate infrastructure costs Documented in cited instrument

The PSC approved additional service terms addressing site and upstream power-system costs.

Shared mechanism
Attributable-cost allocation
Scope
Georgia Power covered new large-load customers; not every Georgia utility.
Important difference
Applies to the specified Georgia Power customer category; implementation is contract-specific.
Source location
Commission announcement p. 1
Georgia PSC rule approval announcement ↗

Commission decision announcement · Source reviewed 2026-10-03

Georgia Allow longer contracts and minimum bills Documented in cited instrument

The approved rule allows longer contracts and minimum billing for covered high-load customers.

Shared mechanism
Minimum payment commitments
Scope
Georgia Power covered new large-load customers; not every Georgia utility.
Important difference
Authority to impose terms is not a universal mandatory billing percentage.
Source location
Commission announcement p. 1
Georgia PSC rule approval announcement ↗

Commission decision announcement · Source reviewed 2026-10-03

Oregon Create a separate service class Documented in cited instrument

The act calls for tariffs assigning covered service costs to large energy use facilities and mitigating cost shifts.

Shared mechanism
Attributable-cost allocation
Scope
Covered large energy use facilities served by electric companies; tariff and contract provisions have distinct applicability.
Important difference
Separate tariff approval and transition provisions matter; a statute is not itself a completed tariff.
Source location
Section 2
Oregon HB 3546, enrolled text ↗

Enrolled text; Chapter 323 confirmed · Source reviewed 2026-10-03

Oregon Require contractual minimum payments Documented in cited instrument

Covered service contracts must include a minimum payment amount or percentage determined by the commission.

Shared mechanism
Minimum payment commitments
Scope
Covered large energy use facilities served by electric companies; tariff and contract provisions have distinct applicability.
Important difference
The law leaves the amount or percentage to the commission.
Source location
Sections 5-6
Oregon HB 3546, enrolled text ↗

Enrolled text; Chapter 323 confirmed · Source reviewed 2026-10-03

Oregon Consider clean-energy compatibility Documented in cited instrument

Commission tariff review must consider effects on clean-energy targets and compatible resource procurement.

Shared mechanism
Clean-energy service terms
Scope
Covered large energy use facilities served by electric companies; tariff and contract provisions have distinct applicability.
Important difference
A tariff-review criterion differs from Minnesota optional clean-energy procurement.
Source location
Section 2(3)
Oregon HB 3546, enrolled text ↗

Enrolled text; Chapter 323 confirmed · Source reviewed 2026-10-03

Oregon Report load trends to lawmakers Documented in cited instrument

The commission must report on large-load trends and implications while protecting proprietary information.

Shared mechanism
Regulatory reporting
Scope
Covered large energy use facilities served by electric companies; tariff and contract provisions have distinct applicability.
Important difference
A legislative reporting mechanism, not disclosure of every customer contract.
Source location
Section 7
Oregon HB 3546, enrolled text ↗

Enrolled text; Chapter 323 confirmed · Source reviewed 2026-10-03

Virginia Separate potable and reclaimed volumes Enacted, future effective

The future-effective code adds supplier reporting by customer category, separating potable and reclaimed water.

Shared mechanism
Water-use reporting
Scope
Registered water users supplying water offsite; categorized reporting, not universal facility-level public disclosure.
Important difference
Monthly data can be replaced by quarterly totals where unavailable; facility-specific disclosure is not established here.
Effective date in source
2027-01-01
Source location
Subsection C, version effective January 1, 2027
Virginia Code 62.1-44.38, future-effective subsection C ↗

Enacted, future effective · Source reviewed 2026-10-03

Virginia Connect electricity, water and generators Official report listed

The official report listing describes a cross-resource account of service agreements, water usage and generator permits.

Shared mechanism
Regulatory reporting
Scope
Report description covers utility agreements, water use and generator permitting; underlying report data not ingested.
Important difference
This confirms the report description, not completeness or accuracy of individual facility records.
Source location
RD637 executive summary
Virginia SCC RD637 report listing ↗

Official report listing · Source reviewed 2026-10-03

New York Assess cumulative development impacts Documented in cited instrument

The order directs a generic environmental impact statement for covered data-center development.

Shared mechanism
Environmental assessment
Scope
Covered data centers and discretionary DEC permits; definition and exemptions must be checked.
Important difference
A statewide review process differs from a project-specific approval.
Source location
Order section 1
New York Executive Order 62 ↗

Executive order · Source reviewed 2026-10-03

New York Link permit restraint to review Documented in cited instrument

The order holds covered discretionary DEC permits in abeyance subject to its scope and exclusions.

Shared mechanism
Interim permit restraint
Scope
Covered data centers and discretionary DEC permits; definition and exemptions must be checked.
Important difference
Applies to covered DEC applications not determined complete before the order; local-government permits are excluded. Not proof that a named project stopped.
Source location
Order section 1 and definition in section 6
New York Executive Order 62 ↗

Executive order · Source reviewed 2026-10-03

New York Review water-withdrawal rules Agency review directed

DEC must assess whether water-withdrawal rules, reporting or guidance should change for large users.

Shared mechanism
Water-supply review
Scope
Covered data centers and discretionary DEC permits; definition and exemptions must be checked.
Important difference
Agency review direction, not an enacted new facility-level water cap.
Source location
Order section 5
New York Executive Order 62 ↗

Executive order · Source reviewed 2026-10-03

How relationships and coverage are defined

One relationship joins a state, an instrument, and a specific provision to a normalized mechanism. States are connected when documented provisions share a mechanism. Groups overlap; the system does not infer legal equivalence, adoption by neighboring states, policy effectiveness, or an absence of policy from missing records.

The matrix counts provisions in this dataset, not laws or affected projects. Comparison and framework selections can be shared by URL. Downloads preserve scope, source location, status, and review date. Future-effective provisions and agency review directions keep their labels.

The initial taxonomy was informed by Ahmed Saeed and Josiah Hester's Governing Datacenter Growth and research paper. SAVRN's source-backed comparison extends beyond the study. Framework purposes, dependencies, and tradeoff prompts are SAVRN analysis, not measured outcomes or statements of law.

Download the evidence dataset (JSON) · Research methodology