State Connections

Explore a state’s data center issues, find states with similar evidence, and assemble a sourced working brief.

View my comparison →
Orange is your starting state.
Blue states share the selected kind of evidence.

Source statuses are retained as recorded. Existing tracker records have not all been freshly reverified for this view.

Start with Connected states. Review why a state matches, then add it to your working group.

Who is working through similar issues?

Open a state to inspect its evidence. Add states to a potential working group.

Use the map or state selector above to explore each state's published evidence.

Arizona: inspect the evidence.

Counts are records, not unique projects. Records can overlap across trackers.

Arizona three-year pause on data center sales tax exemptions Record-specific: State of Arizona (Governor and Legislature) · paused

Gov. Katie Hobbs and legislative leaders announced a budget deal on Tuesday 9 June 2026 that includes a three-year pause on tax exemptions for new data centers. The exemption, enacted in 2013, lasts up to 10 years for qualifying projects. The pause does not affect data centers already receiving the breaks, and companies can still build without them. Senate Majority Leader John Kavanagh said canceling existing incentives would have led to litigation.

Budget deal announced 9 June 2026; pause runs three years

Arizona's Family (KTVK/KPHO) ↗ Arizona Capitol Times ↗
Chandler AI data center (Queen Creek and Dobson roads) Record-specific: City of Chandler · rejected

The Chandler City Council voted 7-0 on 11 December 2025 against a proposed $2.5 billion AI data center on 40 acres near Queen Creek and Dobson roads. Neighbors cited noise already heard from existing data centers in the Price corridor. Former U.S. Sen. Kyrsten Sinema had lobbied the council for the project in October 2025.

Rejected 11 December 2025

azfamily ↗
Copia Power site west of Phoenix Record-specific: · construction

Carlyle has described roughly $2 billion invested in Copia's 20,000-acre site west of Phoenix with 1.5GW of solar. Platform-wide, Copia has brought 2.6 gigawatts into operation or construction; site-specific status is not separately stated. 1.5GW of solar roughly $2 billion invested 20,000-acre site with 1.5GW of solar

Date not recorded

Carlyle ↗ IREI ↗
Data center site, southeast corner of 7th Avenue and Grant Street, Phoenix Record-specific: Phoenix · proposed

A 5.43-acre data center site at the southeast corner of 7th Avenue and Grant Street, just south of downtown Phoenix, traded from Scottsdale-based LKY Development to GI Partners for $14,720,919 on 17 September 2026, according to Maricopa County property records cited by the Phoenix Business Journal. The project is moving ahead under a waiver the City of Phoenix granted in response to a Proposition 207 claim filed after the city's 2025 data center zoning ordinance. LKY had bought the land in 2012 for $3.15 million. Project cost not disclosed; land bought for $14,720,919 on 17 September 2026 (see deal) Not disclosed

Sale recorded 17 September 2026; reported 22 September 2026; single outlet (Phoenix Business Journal, syndicated by ABC15)

Phoenix Business Journal via ABC15 ↗ Phoenix Business Journal (publisher URL, paywalled) ↗
El Mirage land acquisition Record-specific: El Mirage · announced

Microsoft acquired 283 acres in El Mirage for $258 million in two all-cash transactions. $258 million for 283 acres in two all-cash transactions

Date not recorded

Arizona Technology Council ↗
Goodyear data center campus Record-specific: Goodyear · expansion

Microsoft is expanding its five-building, $1.5 billion data center campus in Goodyear, having earlier bought 272 acres near Goodyear Airport for $42 million in 2018. five-building, $1.5 billion data center campus; earlier bought 272 acres near Goodyear Airport for $42 million in 2018

Date not recorded

Arizona Technology Council ↗
Goodyear/Buckeye campus Record-specific: Maricopa County · withdrawn

Withdrawn

May 2024

Data Center Watch ↗
Grande Valley Industrial Data Center Campus Record-specific: Casa Grande · approved

The Casa Grande Planning and Zoning Commission approved a conditional use permit for the Grande Valley Industrial Data Center Campus by a 6-1 vote on Thursday 1 October 2026, the first hearing under the city's rules making data centers a conditional industrial use. The 954-acre site lies southwest and southeast of the intersection of Maricopa-Casa Grande Highway and Montgomery Road, about 8 miles from downtown. Plans include multiple buildings, closed-loop cooling, on-site Bloom Energy fuel cells (the company's first Arizona installation) and battery storage. The permit needs no City Council vote. The end user, investment and power demand were not disclosed. On-site Bloom Energy natural gas fuel cells and a battery energy storage system; grid connection not stated Not disclosed Not disclosed; 954-acre campus with multiple buildings, on-site natural gas fuel cell generation and battery storage; city limit of 300 acre-feet (about 97 million gallons) of water per year

Conditional use permit approved 6-1 on Thursday 1 October 2026

Casa Grande Dispatch (PinalCentral) ↗ KJZZ ↗
Hualapai Indian Reservation data center moratorium Record-specific: Hualapai Indian Reservation · moratorium

Hualapai Indian Reservation, Arizona, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated August 2026. Tribal Council passed resolution opposing data center construction on reservation land, citing water scarcity on the Colorado River, light pollution, and wastewater concerns. Tribal sovereignty makes this effectively a ban on all reservation land. The measure has no end date by design.

Enacted August 2026

knau.org ↗
La Osa Energy Center Record-specific: Pinal County · rejected

The Pinal County Board of Supervisors rejected the rezoning 4-1 on 26 August 2026. Vermaland had cut the project to roughly 80 percent of an earlier proposal of 59 data center buildings and 3 GW of energy demand, moved buildings several miles from neighbors, offered 22 additional development conditions between May and August 2026, and proposed a 600 acre-foot cap on fresh water, roughly 200 million gallons, with potential offset through effluent purchases from the Central Arizona Irrigation and Drainage District. Supervisor Jeff Serdy said he voted the will of the residents. Neighbors raised aquifer depletion, air quality, noise, wildlife and property value concerns and questioned whether power could be sourced reliably from more than 100 miles away.

Rejected 4-1 on 26 August 2026

KJZZ ↗ AZFamily ↗
Marana data center rezoning referendum petitions (Beale Infrastructure) Record-specific: Town of Marana; Arizona Court of Appeals, Division Two · litigation

The Marana Town Council unanimously rezoned two adjacent agricultural parcels for a data center in January 2026. In February 2026 the town clerk rejected two referendum petitions because the copies circulated to voters lacked required exhibits with the legal descriptions, and a Pima County Superior Court judge later upheld the rejection and denied a request by Beale subsidiary Fremont Peak Properties to compel the town to accept the petitions' withdrawal. A three-judge panel of the Arizona Court of Appeals, Division Two, unanimously affirmed the judgment for the town, leaving the zoning approvals in place with no ballot vote.

Rezoning January 2026; petitions rejected February 2026; Superior Court arguments 27 April 2026; Court of Appeals affirmance reported 1 October 2026 (ruling date not stated; single outlet for the appellate ruling)

Chamber Business News, 1 October 2026 ↗ AZPM News ↗ KOLD 13 News (via MSN), December 2025 ↗
Mesa data center Record-specific: Mesa · operating

The Mesa facility is now online. Once fully built out, it will represent an investment of more than $1 billion in the state of Arizona. 450 MW of new renewable energy via Salt River Project across three Meta-supported projects more than $1 billion once fully built out Three Meta-supported projects adding 450 megawatts of new renewable energy in Arizona via Salt River Project

Online as of January 2025 announcement

Meta Data Centers ↗
Pima County 120-day data center moratorium (unincorporated areas) Record-specific: Pima County Board of Supervisors · moratorium

On Tuesday 22 September 2026 the Pima County Board of Supervisors voted 3-2 for a resolution barring new data center projects in unincorporated areas from moving forward for 120 days, with a possible extension, while the county writes zoning requirements and studies air, water, land use and cumulative impacts. An amendment limited it to projects that had not yet submitted permits, which exempts Beale Infrastructure's Project Blue and the proposed 160-acre Project Gravel south of Tucson. This is separate from the City of Tucson's August 2026 data center ordinance (row 337). On 28 September 2026 the Goldwater Institute, a libertarian legal advocacy group, sent the Board of Supervisors a demand letter asking it to rescind the moratorium immediately, arguing that Arizona law allows county moratoria only for a shortage of essential public facilities or a compelling need defined as a clear and imminent danger to public health and safety, and that the pause raises claims under the state's Private Property Rights Protection Act. The supervisors who voted against the moratorium had cited legal concerns. No lawsuit had been reported as of 30 September 2026.

Approved 3-2 on 22 September 2026; 120 days, extendable; Goldwater Institute demand letter to rescind sent 28 September 2026

KJZZ ↗ Goldwater Institute (advocacy) ↗ The Center Square ↗
Prime PHX01, Avondale Record-specific: Avondale · announced

PHX01 in Avondale, Arizona, a $3B, 240 MW project announced May 2026. $3B 240 MW

announced May 2026

Business Wire ↗
Project Blue Record-specific: Tucson / Pima County · rejected

City Council voted unanimously to end annexation negotiations Aug 5-6 2025

Aug 2025; project continued outside city limits per source narrative

Western Water ↗ AZ Luminaria ↗ KJZZ ↗

Follow the issue to the utility and the customer.

Named organizations come from explicit record fields. Their presence is not confirmation of a serving-utility relationship, service availability, or customer eligibility.

Named parties in this state's evidence

Start from your position.

Screen an individual location ↗

Address-level utility verification and service agreements belong in the site screen. Private account data and individual household identities are not part of this public dataset.

Regional grid context and rules
Open the complete grid operator watchlist ↗

Explore generation and interconnection queues ↗ · Explore scarcity and market constraints ↗

Your comparison

See what your selected states have in common.

We bring together the shared issues and source records for the states you choose.

States appear side by side. Compare each topic, then open a cell for sources.

Add your own notes Optional

Notes are included when you open or save the comparison. Save a copy to keep them after leaving this page.

Sharing and data options

The link includes your states and issue filter. It does not include private notes. Source data downloads as JSON.

Your comparison

State comparison

Save a copy
Coverage, sources and how states are connected

All 50 states are selectable. A connection requires the same documented policy mechanism or the same structured tracker classification and status. The map is a discovery tool, not a legal-equivalence score, a project-risk ranking, or a complete census. No match means no matching evidence in this view.

Existing tracker publications supply most records. Their source status and date are retained; a page load is not a new source verification. Proposed, failed, enacted and reversed records remain distinct. Explicitly unverified or pending-review rows are excluded. Narrative and status can disagree in the underlying publication; inspect both before treating a restriction as active. No state-wide effect is inferred from a local action.

Data is read from the current tracker files and published overlays. Source changes invalidate the server's cached connections. Policy mechanisms use a separately reviewed evidence set. Generation queues and broad company commitments are not assigned to a data center or customer. Federal records and records without an explicit state are not assigned to a state by inference.

Download state evidence JSON · SAVRN methodology

Underlying dataset credits
  • 6abc Philadelphia
  • AEP Ohio Transmission Company (filed with Ohio Power Siting Board)
  • AI GridWatch moratorium tracker, CC BY 4.0 (aigridwatch.com)
  • Alabama Reflector
  • Alaska Beacon
  • American Transmission Company LLC (filed with PSC of Wisconsin)
  • Americus Times-Recorder
  • Arizona Mirror
  • Arkansas Advocate
  • Axios Pro Energy
  • Bisnow
  • Bisnow National
  • Bradenton Herald
  • CNBC Technology
  • Cardinal News VA
  • Central Florida Public Media
  • Chesterfield County public permit records
  • Chicago Construction News
  • City of Atlanta public permit records
  • City of Austin issued construction permits open data
  • City of Buckeye public permit records
  • City of Chandler public permit records
  • City of Charlotte public permit records
  • City of Chicago building permits open data
  • City of Fort Worth public permit records
  • City of Goodyear public permit records
  • City of Hillsboro public permit records
  • City of Mesa building permits open data
  • City of Mesa public permit records
  • City of Minneapolis construction permits (CCS) open data
  • City of Papillion public permit records
  • City of Phoenix public permit records
  • City of Red Oak public permit records
  • City of Reno public permit records
  • City of San Antonio public permit records
  • City of Statesboro, Georgia
  • City of Temple, Texas
  • Clearfield City Council (Utah Public Notice Website)
  • Colorado Newsline
  • Colorado Public Radio
  • Congress.gov (Library of Congress, public domain)
  • ConstructConnect News
  • Construction Dive
  • CourtListener DataCenter Dockets
  • CourtListener Opinions
  • Data Center Dynamics
  • Data Center Dynamics news
  • DataCenterTracker.org, CC BY 4.0
  • Dominion Energy Virginia
  • EIN News
  • East Bay Insiders Newsletter
  • Energy Central
  • FOX19 | Cincinnati
  • FOX5 Vegas
  • FOX6 News Milwaukee
  • Facilities Dive
  • Fairfax County public permit records
  • Florida Phoenix
  • Georgia Department of Community Affairs
  • Georgia EPD air permit records
  • Georgia Recorder
  • GovTech
  • Greensboro News and Record
  • Grist
  • Idaho Capital Sun
  • Illinois EPA air permit records
  • Indiana Capital Chronicle
  • Indiana Department of Environmental Management
  • Indiana IDEM air permit records
  • InkFreeNews.com
  • Iowa Capital Dispatch
  • Iowa DNR air permit records
  • KERA News
  • KEYC News Now
  • KGW
  • KRON4
  • Kansas City MO city issued permits open data
  • Kansas Reflector
  • Kentucky Lantern
  • Law360
  • Law360 Energy
  • LegiScan (legiscan.com) and the state legislature
  • Lehigh Valley Planning Commission
  • Local News Matters
  • Loudoun County public permit records
  • Loudoun Times-Mirror
  • Louisiana DEQ air permit records
  • Louisiana Illuminator
  • Maine Morning Star
  • Maricopa County Air Quality Department air permit records
  • Maricopa County public permit records
  • Maryland Matters
  • Mecklenburg County public permit records
  • Michigan Advance
  • Mid Bay News
  • Missouri Independent
  • Montana Free Press
  • NBC Bay Area
  • NBC4 Washington
  • NC Newsline
  • Native News Online
  • Nebraska Examiner
  • Nevada Current
  • Nevada NDEP air permit records
  • New Hampshire Bulletin
  • New Mexico Environment Department
  • North Carolina DEQ Division of Air Quality air permit records
  • North Dakota Department of Environmental Quality
  • North Dakota Monitor
  • Ohio Capital Journal
  • Ohio EPA air permit records
  • Oklahoma DEQ air permit records
  • Oklahoma Voice
  • OpenStates v3 (openstates.org), CC BY 4.0
  • Oregon Capital Chronicle
  • Orlando Sentinel
  • Pennsylvania Capital-Star
  • Pennsylvania Department of Environmental Protection
  • Pennsylvania Office of Consumer Advocate (filed with PA PUC)
  • Pioneer Press
  • Prince William County public permit records
  • Public Service Commission of Wisconsin
  • Public record (Legistar Web API, Granicus)
  • Rhode Island Current
  • Route Fifty
  • SEC EDGAR company submissions, public domain
  • SEC EDGAR full-text search, public domain
  • Searchlight New Mexico
  • Smithfield Township, Monroe County, PA
  • Source New Mexico
  • South Carolina Department of Environmental Services
  • South Dakota Searchlight
  • Springfield Daily Citizen
  • Stafford County public permit records
  • Statesman Journal
  • Strisker data center notes
  • Tennessee Lookout
  • Texas Commission on Environmental Quality
  • Texas TCEQ air permit records
  • The Baltimore Banner
  • The Current (GA)
  • The Detroit News
  • The Hill Energy
  • The North State Journal
  • The Pantagraph
  • The Real Deal
  • The Register
  • The Texas Tribune
  • The Verge
  • Times-Standard
  • Town of Culpeper public permit records
  • Tuscaloosa Thread
  • U.S. EPA ECHO
  • Union-Bulletin
  • Uprise RI
  • Utah Division of Air Quality
  • Utah Division of Air Quality air permit records
  • Utah News Dispatch
  • Utah Public Radio
  • Utility Dive
  • Virginia Business
  • Virginia DEQ air permit records
  • Virginia Electric and Power Company (filed with Virginia SCC)
  • Virginia Mercury
  • Visalia Times-Delta
  • WBUR
  • WCPO 9 Cincinnati
  • WGLT
  • WHEC.com
  • WJON
  • WKYT
  • WLOS
  • WLUK
  • WPBF
  • WQCS
  • WRAL (NC)
  • WUNC News
  • WVPE
  • Washington County public permit records
  • Washington Ecology air permit records
  • Washington State SEPA Register public permit records
  • Washington State Standard
  • Washoe County public permit records
  • Wausau Pilot & Review
  • West Virginia Watch
  • Winston-Salem Journal
  • Wisconsin Department of Natural Resources
  • Wisconsin Examiner
  • Yale Daily News
  • citybiz
  • contracosta.news
  • ictnews.org
  • indianapublicradio.org
  • inkfreenews.com
  • lex18.com
  • mountaintimesoregon.com
  • newmedia-wi.com
  • newscentermaine.com
  • thegazette.com
  • tuscaloosathread.com
  • wcpo.com
  • www.cities929.com

SAVRN Policy Connections

How state policies connect.

Find shared policy mechanisms, compare the differences, and assemble a framework from documented state provisions.

9 states with documented provisions29 provisions · 14 mechanisms · all 50 states available for comparison

An initial evidence set, not an exhaustive survey. A missing relationship means not documented here, never no policy. Source review verifies the cited instrument, not every later amendment or implementing action. Sources reviewed 3 October 2026.

Shared goals. Different requirements.

Each number opens the provisions connecting a state to a policy family. States can belong to several groups. A shared family is not proof of identical law.

Documented relationships by policy family. A dash means not documented in this evidence set.
StateProject readinessCost responsibilityGrid flexibilityWater safeguardsReporting & oversightEnergy & emissionsLocal authorityEnvironmental review
Georgia–2––––––
Indiana–3––1–––
Minnesota–2–1–1––
New York–––1–––2
Ohio–1––––––
Oregon–2––11––
South Dakota–2–11–1–
Texas111––1––
Virginia––––2–––

Choose a mechanism to see states connected by that specific policy tool.

Inspect the provision, not just the category.

All 29 documented provisions. Open a record for its source, scope, and difference from similar tools.

Texas Verify the proposed site Documented in cited instrument

Interconnection standards must include a way to demonstrate a legal interest in the proposed location.

Shared mechanism
Evidence of site control
Scope
ERCOT large-load interconnection; applicability and exceptions in the statute.
Important difference
Evidence of site control does not establish that all permits or financing are secured.
Source location
Section 37.0561(g)
Texas SB 6, enrolled text ↗

Statutory text · Source reviewed 2026-10-03

Texas Back transmission commitments Documented in cited instrument

Standards must set financial commitments supporting transmission infrastructure for covered loads.

Shared mechanism
Financial security
Scope
ERCOT large-load interconnection; applicability and exceptions in the statute.
Important difference
Permitted security forms and release rules depend on implementation; not a minimum energy bill.
Source location
Section 37.0561(h)-(j)
Texas SB 6, enrolled text ↗

Statutory text · Source reviewed 2026-10-03

Texas Define emergency response Documented in cited instrument

Covered backup-equipped loads may be directed to deploy backup generation or curtail after the specified market-service sequence.

Shared mechanism
Emergency response
Scope
ERCOT large-load interconnection; applicability and exceptions in the statute.
Important difference
An emergency mechanism, not a general voluntary demand-response tariff.
Source location
Section 37.0561(e)
Texas SB 6, enrolled text ↗

Statutory text · Source reviewed 2026-10-03

Texas Retain emissions limits Documented in cited instrument

Emergency direction does not authorize violation of emissions or environmental requirements.

Shared mechanism
Emissions safeguards
Scope
ERCOT large-load interconnection; applicability and exceptions in the statute.
Important difference
Backup generation remains constrained by applicable environmental rules.
Source location
Section 37.0561(e)(1)
Texas SB 6, enrolled text ↗

Statutory text · Source reviewed 2026-10-03

Minnesota Assign attributable utility costs Documented in cited instrument

Commission review of very-large-customer service terms must address attributable costs and protection of other customers.

Shared mechanism
Attributable-cost allocation
Scope
Scope varies by section: data-center water provisions, public-utility service, and optional clean-energy contracts.
Important difference
A regulatory framework with customer-class and agreement decisions, not a uniform minimum billing percentage.
Source location
Section 9, subdivision 2
Minnesota 2025 special-session Chapter 12 ↗

Session law · Source reviewed 2026-10-03

Minnesota Protect against stranded costs Documented in cited instrument

Tariff or agreement review must include protections against other customers paying stranded service costs.

Shared mechanism
Departure / reduced-load protection
Scope
Scope varies by section: data-center water provisions, public-utility service, and optional clean-energy contracts.
Important difference
Existing-service exceptions appear in subdivision 3.
Source location
Section 9, subdivision 2(3)
Minnesota 2025 special-session Chapter 12 ↗

Session law · Source reviewed 2026-10-03

Minnesota Evaluate consumptive water demand Documented in cited instrument

Preapplication review links covered consumptive demand and permit needs to site-specific water availability.

Shared mechanism
Water-supply review
Scope
Scope varies by section: data-center water provisions, public-utility service, and optional clean-energy contracts.
Important difference
Facility definition and water-use/permit conditions apply together; not all withdrawals trigger this review.
Source location
Sections 3-4
Minnesota 2025 special-session Chapter 12 ↗

Session law · Source reviewed 2026-10-03

Minnesota Offer optional clean-energy service Documented in cited instrument

Utilities must offer a clean-energy and capacity tariff with participating customers paying proportional resource costs.

Shared mechanism
Clean-energy service terms
Scope
Scope varies by section: data-center water provisions, public-utility service, and optional clean-energy contracts.
Important difference
Customer participation is optional; do not classify it as a universal clean-energy purchase mandate.
Source location
Section 10
Minnesota 2025 special-session Chapter 12 ↗

Session law · Source reviewed 2026-10-03

South Dakota Recover attributable electricity costs Documented in cited instrument

Separate service terms must recover costs fairly attributable to the data center.

Shared mechanism
Attributable-cost allocation
Scope
Statutorily defined data centers; electricity providers, water providers, and local governments.
Important difference
Applies through provider terms rather than a published statewide minimum billing percentage.
Source location
Section 3
South Dakota SB 135, Chapter 190 ↗

Session law · Source reviewed 2026-10-03

South Dakota Address departure and reduced load Documented in cited instrument

Cost responsibility includes costs incurred if the customer departs or materially reduces load.

Shared mechanism
Departure / reduced-load protection
Scope
Statutorily defined data centers; electricity providers, water providers, and local governments.
Important difference
The law states cost responsibility; it does not supply a universal exit-fee formula.
Source location
Section 3
South Dakota SB 135, Chapter 190 ↗

Session law · Source reviewed 2026-10-03

South Dakota Obtain local supply determinations Documented in cited instrument

Water providers assess compatibility, with board review and allocation limits protecting priority uses.

Shared mechanism
Water-supply review
Scope
Statutorily defined data centers; electricity providers, water providers, and local governments.
Important difference
Local supply determinations are distinct from the Minnesota consumptive-use permit review.
Source location
Section 5
South Dakota SB 135, Chapter 190 ↗

Session law · Source reviewed 2026-10-03

South Dakota Publish water-use data Documented in cited instrument

Operators report usage to the board, which makes usage data available to the public.

Shared mechanism
Water-use reporting
Scope
Statutorily defined data centers; electricity providers, water providers, and local governments.
Important difference
Operator reporting differs from Virginia supplier category reporting.
Source location
Section 6
South Dakota SB 135, Chapter 190 ↗

Session law · Source reviewed 2026-10-03

South Dakota Preserve local regulation Documented in cited instrument

The state may not limit local authority to regulate data-center development or operation.

Shared mechanism
Preserved local authority
Scope
Statutorily defined data centers; electricity providers, water providers, and local governments.
Important difference
Preservation of local authority is not evidence that a local ban exists.
Source location
Section 4
South Dakota SB 135, Chapter 190 ↗

Session law · Source reviewed 2026-10-03

Ohio Address underused infrastructure risk Documented in cited instrument

PUCO adopted a settlement aimed at protecting other customers from cost shifting due to underused data-center investments.

Shared mechanism
Attributable-cost allocation
Scope
AEP Ohio data-center tariff proceeding; not a tariff for every Ohio utility.
Important difference
The cited announcement directs tariff filing; consult the filed tariff for binding customer terms.
Source location
Decision announcement, case background
PUCO decision announcement, case 24-508-EL-ATA ↗

Commission decision announcement · Source reviewed 2026-10-03

Indiana Set minimum billing obligations Documented in cited instrument

The approved settlement establishes minimum billing-demand and charge provisions for covered large loads.

Shared mechanism
Minimum payment commitments
Scope
Indiana Michigan Power Tariff I.P., Indiana jurisdiction; covered large-load customers.
Important difference
The approved settlement differs from the original utility proposal; I&M territory only.
Source location
Order pp. 32-35 and ordering paragraphs p. 49
IURC order, Cause 46097 ↗

Commission order · Source reviewed 2026-10-03

Indiana Address early termination Documented in cited instrument

The approved settlement contains contract termination protections for covered large-load service.

Shared mechanism
Departure / reduced-load protection
Scope
Indiana Michigan Power Tariff I.P., Indiana jurisdiction; covered large-load customers.
Important difference
Customer-specific conditions and the settlement govern; not statewide terms for every provider.
Source location
Settlement agreement; order approval pp. 49-50
IURC order, Cause 46097 ↗

Commission order · Source reviewed 2026-10-03

Indiana Require collateral arrangements Documented in cited instrument

The approved settlement includes financial-security terms for covered large-load customers.

Shared mechanism
Financial security
Scope
Indiana Michigan Power Tariff I.P., Indiana jurisdiction; covered large-load customers.
Important difference
Collateral and exceptions depend on tariff eligibility and customer circumstances.
Source location
Settlement agreement; order approval pp. 49-50
IURC order, Cause 46097 ↗

Commission order · Source reviewed 2026-10-03

Indiana Report large-load developments Documented in cited instrument

The order addresses recurring reports and protection of confidential information.

Shared mechanism
Regulatory reporting
Scope
Indiana Michigan Power Tariff I.P., Indiana jurisdiction; covered large-load customers.
Important difference
Regulator access is not equivalent to public disclosure of all reported data.
Source location
Order p. 49
IURC order, Cause 46097 ↗

Commission order · Source reviewed 2026-10-03

Georgia Allocate infrastructure costs Documented in cited instrument

The PSC approved additional service terms addressing site and upstream power-system costs.

Shared mechanism
Attributable-cost allocation
Scope
Georgia Power covered new large-load customers; not every Georgia utility.
Important difference
Applies to the specified Georgia Power customer category; implementation is contract-specific.
Source location
Commission announcement p. 1
Georgia PSC rule approval announcement ↗

Commission decision announcement · Source reviewed 2026-10-03

Georgia Allow longer contracts and minimum bills Documented in cited instrument

The approved rule allows longer contracts and minimum billing for covered high-load customers.

Shared mechanism
Minimum payment commitments
Scope
Georgia Power covered new large-load customers; not every Georgia utility.
Important difference
Authority to impose terms is not a universal mandatory billing percentage.
Source location
Commission announcement p. 1
Georgia PSC rule approval announcement ↗

Commission decision announcement · Source reviewed 2026-10-03

Oregon Create a separate service class Documented in cited instrument

The act calls for tariffs assigning covered service costs to large energy use facilities and mitigating cost shifts.

Shared mechanism
Attributable-cost allocation
Scope
Covered large energy use facilities served by electric companies; tariff and contract provisions have distinct applicability.
Important difference
Separate tariff approval and transition provisions matter; a statute is not itself a completed tariff.
Source location
Section 2
Oregon HB 3546, enrolled text ↗

Enrolled text; Chapter 323 confirmed · Source reviewed 2026-10-03

Oregon Require contractual minimum payments Documented in cited instrument

Covered service contracts must include a minimum payment amount or percentage determined by the commission.

Shared mechanism
Minimum payment commitments
Scope
Covered large energy use facilities served by electric companies; tariff and contract provisions have distinct applicability.
Important difference
The law leaves the amount or percentage to the commission.
Source location
Sections 5-6
Oregon HB 3546, enrolled text ↗

Enrolled text; Chapter 323 confirmed · Source reviewed 2026-10-03

Oregon Consider clean-energy compatibility Documented in cited instrument

Commission tariff review must consider effects on clean-energy targets and compatible resource procurement.

Shared mechanism
Clean-energy service terms
Scope
Covered large energy use facilities served by electric companies; tariff and contract provisions have distinct applicability.
Important difference
A tariff-review criterion differs from Minnesota optional clean-energy procurement.
Source location
Section 2(3)
Oregon HB 3546, enrolled text ↗

Enrolled text; Chapter 323 confirmed · Source reviewed 2026-10-03

Oregon Report load trends to lawmakers Documented in cited instrument

The commission must report on large-load trends and implications while protecting proprietary information.

Shared mechanism
Regulatory reporting
Scope
Covered large energy use facilities served by electric companies; tariff and contract provisions have distinct applicability.
Important difference
A legislative reporting mechanism, not disclosure of every customer contract.
Source location
Section 7
Oregon HB 3546, enrolled text ↗

Enrolled text; Chapter 323 confirmed · Source reviewed 2026-10-03

Virginia Separate potable and reclaimed volumes Enacted, future effective

The future-effective code adds supplier reporting by customer category, separating potable and reclaimed water.

Shared mechanism
Water-use reporting
Scope
Registered water users supplying water offsite; categorized reporting, not universal facility-level public disclosure.
Important difference
Monthly data can be replaced by quarterly totals where unavailable; facility-specific disclosure is not established here.
Effective date in source
2027-01-01
Source location
Subsection C, version effective January 1, 2027
Virginia Code 62.1-44.38, future-effective subsection C ↗

Enacted, future effective · Source reviewed 2026-10-03

Virginia Connect electricity, water and generators Official report listed

The official report listing describes a cross-resource account of service agreements, water usage and generator permits.

Shared mechanism
Regulatory reporting
Scope
Report description covers utility agreements, water use and generator permitting; underlying report data not ingested.
Important difference
This confirms the report description, not completeness or accuracy of individual facility records.
Source location
RD637 executive summary
Virginia SCC RD637 report listing ↗

Official report listing · Source reviewed 2026-10-03

New York Assess cumulative development impacts Documented in cited instrument

The order directs a generic environmental impact statement for covered data-center development.

Shared mechanism
Environmental assessment
Scope
Covered data centers and discretionary DEC permits; definition and exemptions must be checked.
Important difference
A statewide review process differs from a project-specific approval.
Source location
Order section 1
New York Executive Order 62 ↗

Executive order · Source reviewed 2026-10-03

New York Link permit restraint to review Documented in cited instrument

The order holds covered discretionary DEC permits in abeyance subject to its scope and exclusions.

Shared mechanism
Interim permit restraint
Scope
Covered data centers and discretionary DEC permits; definition and exemptions must be checked.
Important difference
Applies to covered DEC applications not determined complete before the order; local-government permits are excluded. Not proof that a named project stopped.
Source location
Order section 1 and definition in section 6
New York Executive Order 62 ↗

Executive order · Source reviewed 2026-10-03

New York Review water-withdrawal rules Agency review directed

DEC must assess whether water-withdrawal rules, reporting or guidance should change for large users.

Shared mechanism
Water-supply review
Scope
Covered data centers and discretionary DEC permits; definition and exemptions must be checked.
Important difference
Agency review direction, not an enacted new facility-level water cap.
Source location
Order section 5
New York Executive Order 62 ↗

Executive order · Source reviewed 2026-10-03

How relationships and coverage are defined

One relationship joins a state, an instrument, and a specific provision to a normalized mechanism. States are connected when documented provisions share a mechanism. Groups overlap; the system does not infer legal equivalence, adoption by neighboring states, policy effectiveness, or an absence of policy from missing records.

The matrix counts provisions in this dataset, not laws or affected projects. Comparison and framework selections can be shared by URL. Downloads preserve scope, source location, status, and review date. Future-effective provisions and agency review directions keep their labels.

The initial taxonomy was informed by Ahmed Saeed and Josiah Hester's Governing Datacenter Growth and research paper. SAVRN's source-backed comparison extends beyond the study. Framework purposes, dependencies, and tradeoff prompts are SAVRN analysis, not measured outcomes or statements of law.

Download the evidence dataset (JSON) · Research methodology