Georgia Data Center Moratorium Tracker
Georgia has 2 data-center bills pending in the legislature. 60 city and county measures are tracked here, 49 of them in force. Every entry below links to its primary source: a legislature page, a governor's office, a local government, or the reporting of record.
State-level measures in Georgia
Every statewide moratorium, pause, siting restriction, or tax-incentive rollback in Georgia we can verify against a primary source. Strongest status first.
| Measure | Status | What it does | Source |
|---|---|---|---|
| SB 476Elimination of state tax credits reaching data centers | Proposed 2026-02 | Would eliminate nearly all state-sponsored tax credits, precluding new data center tax credits. Passed the State Senate on Feb. 12, 2026; did not become law. | |
| Debate over data center growth in Georgia heats up race for governor | Proposed 2026-09 | Georgia gubernatorial candidates Keisha Lance Bottoms and Rick Jackson have proposed opposing approaches to regulating the state's rapidly expanding data center industry. The article discusses the political debate around data center regulation in Georgia during the gubernatorial race. | |
| HB 1192Sales and use tax; certain high-technology data center equipment; prohibit issuance of new certificates of exemption | Failed / vetoed 2024-05 | Georgia HB 1192 (2023_24): Sales and use tax; certain high-technology data center equipment; prohibit issuance of new certificates of exemption. Last action 2024-05-07: Veto V7. | |
| SB34Georgia SB34 would have prohibited data center fuel generation and transmission costs from being included in residential electricity rates | Failed / vetoed 2026-01 | Georgia SB34 would have prohibited data center fuel generation and transmission costs from being included in residential electricity rates, requiring commercial data centers to cover all increased fuel, power, and transmission system upgrade costs. The bill emerged after the Public Service Commission authorized Georgia Power to expand production by nearly 10 GW, mostly for data centers, including new methane-burning facilities. The Senate avoided a final vote after a last-minute alternative measure based on House Bill 1063 appeared to have the votes to pass. | |
| HB 1059Georgia HB 1059 (Rep. Derrick Jackson D-Tyrone) would have established a moratorium on new data center construction from July 1, 2026 through December 31 | Failed / vetoed 2026-01 | Georgia HB 1059 (Rep. Derrick Jackson D-Tyrone) would have established a moratorium on new data center construction from July 1, 2026 through December 31, 2028, plus a 14-member Data Center Impact Commission. The bill failed to advance during the 2026 legislative session, which ended in early April with Georgia lawmakers passing NO data center bills despite months of debate. The General Assembly left intact ~$2.5B/year in data center tax breaks even after a state report estimated Georgia would miss out on $2.5B in tax revenue in 2026. With no statewide restrictions, county commissions and planning boards remain the front line of defense, and Democrats are reportedly viewing the failure as an electoral gift heading into November 2026. By April 15-18, 2026, advocates reported that around 20 bills aimed at the data center industry introduced during the 2026 Georgia legislative session all failed to pass after the Senate adjourned without action. Failed measures included HB 1012, SB 408, and SB 410, along with HB 1059 (the Data Center Impact Assessment and Development Moratorium Act of 2026). Georgia's data center sales-tax exemption (projected to cost the state $2.5 billion in FY 2026) remains in effect through 2032. | |
| Georgia (statewide)Georgia: Requires electric utilities and new data centers (100+ MWH peak annual demand) to agree on contract terms that shield other power customers | Failed / vetoed 2026-02 | Requires electric utilities and new data centers (100+ MWH peak annual demand) to agree on contract terms that shield other power customers from construction and operation costs. Includes minimum billing requirements, performance/credit provisions, and termination protections. Passed Georgia House 159-5, now in Senate. | |
| HB 559Georgia HB 559 would accelerate the sunset date for the state's data center sales and use tax exemption program, ending tax breaks for new data centers by 2026 | Failed / vetoed 2026-02 | Georgia HB 559 would accelerate the sunset date for the state's data center sales and use tax exemption program, ending tax breaks for new data centers by 2026 rather than the originally scheduled later date. The bill is part of a wave of Georgia legislation targeting data center incentives in the 2026 session, alongside SB 410 (which passed the Senate to repeal exemptions entirely) and HB 1063 (which passed the House 159-5 requiring data centers to pay infrastructure costs). Per Inside Climate News (April 9, 2026), all data center ratepayer protection bills failed in the 2026 Georgia session; the tax exemption is set to remain in place until 2032. | |
| SB 408Georgia: SB 408, sponsored by Sen. Nan Orrock (D-Atlanta), would move the sunset date for Georgia's data center sales and use tax exemption from January 1 | Failed / vetoed 2026-02 | SB 408, sponsored by Sen. Nan Orrock (D-Atlanta), would move the sunset date for Georgia's data center sales and use tax exemption from January 1, 2032 to January 1, 2027, effectively ending the incentive five years early. It is one of several bills introduced in the 2025-26 session targeting the exemption, including SB 410 (immediate repeal) and HB 559 (sunset December 31, 2026). A state audit found the exemption has cost Georgia significant revenue while creating relatively few jobs per dollar of tax benefit. Per Inside Climate News (April 9, 2026), SB 408 did not reach a vote in the Senate; the exemption remains until 2032. | |
| SB436Georgia SB436 suspends new sales and use tax exemptions for data centers from July 1, 2026 through June 30, 2027, and prohibits local governments from entering | Failed / vetoed 2026-02 | Georgia SB436 suspends new sales and use tax exemptions for data centers from July 1, 2026 through June 30, 2027, and prohibits local governments from entering into nondisclosure agreements related to data center water and electricity usage. The bill is part of a wave of Georgia data center legislation in 2026, the Senate also passed SB410 to outright end tax exemptions, while the House passed HB1063 (159-5) requiring data centers to pay down payments and sign longer contracts covering infrastructure costs. Georgia adjourned sine die Apr 3, 2026 with no data center regulation enacted; SB 436 (suspend tax exemptions + ban NDAs) died in Senate Finance and HB 1063 died in the Senate after crossover. | |
| HB 1012One-year data center construction moratorium | Failed / vetoed 2026-04 | Would impose a roughly one-year moratorium on new data center construction (ending Mar 1 2027) to study impacts; died before adjournment. | |
| SB 410Phase-out of data center tax breaks | Failed / vetoed 2026-04 | Would phase out sales-tax exemptions for new data centers; passed the Senate 32-21 (Mar 6) but died in the House when the session adjourned Apr 2. |
City and county moratoria in Georgia
Most of the movement is local, where a building pause or permit halt does not need a legislative session. 60 tracked measures in Georgia, each with its source.
Where Georgia stands
Across the whole tracker we hold 334 state-level measures in 49 states and 1253 city and county measures, against 1419 primary sources. Georgia accounts for 11 of the state-level measures and 60 of the local ones.
By total measures on record it is #4 of the 50 states and DC carrying any tracked action, and #5 by city and county measures alone. Ranking is by count of sourced entries in this dataset, so it measures documented activity, not the size of the buildout.
Sources for Georgia
69 citations behind the entries above. Each opens in a new tab.
- Statewide · SB 476 — Elimination of state tax credits reaching data centers afslaw.com →
- Statewide — Debate over data center growth in Georgia heats up race for governor thecurrentga.org →
- Statewide · HB 1192 — Sales and use tax; certain high-technology data center equipment; prohibit issuance of new certificates of exemption webservices.legis.ga.gov →
- Statewide · SB34 — Georgia SB34 would have prohibited data center fuel generation and transmission costs from being included in residential electricity rates legis.ga.gov →
- Statewide · HB 1059 — Georgia HB 1059 (Rep. Derrick Jackson D-Tyrone) would have established a moratorium on new data center construction from July 1, 2026 through December 31 legiscan.com →
- Statewide · Georgia (statewide) — Georgia: Requires electric utilities and new data centers (100+ MWH peak annual demand) to agree on contract terms that shield other power customers legis.ga.gov →
- Statewide · HB 559 — Georgia HB 559 would accelerate the sunset date for the state's data center sales and use tax exemption program, ending tax breaks for new data centers by 2026 legis.ga.gov →
- Statewide · SB 408 — Georgia: SB 408, sponsored by Sen. Nan Orrock (D-Atlanta), would move the sunset date for Georgia's data center sales and use tax exemption from January 1 legis.ga.gov →
- Statewide · SB436 — Georgia SB436 suspends new sales and use tax exemptions for data centers from July 1, 2026 through June 30, 2027, and prohibits local governments from entering legis.ga.gov →
- Statewide · HB 1012 — One-year data center construction moratorium wabe.org →
- Statewide · SB 410 — Phase-out of data center tax breaks georgiawatch.org →
- Albany — Albany data center moratorium (proposed) walb.com →
- Americus — 30-day data center moratorium americustimesrecorder.com →
- Athens-Clarke County — Local moratorium on data centers until a condition is met flagpole.com →
- Atlanta — Local moratorium on data centers with no end date gpb.org →
- Augusta — Augusta data center moratorium theaugustapress.com →
- Augusta-Richmond County — County moratorium on data centers through September 19, 2026 wrdw.com →
- Bloomingdale — 180-day data center moratorium wsav.com →
- Bulloch County — Data center moratorium through Dec. 31, 2026 thegeorgiavirtue.com →
- Bulloch County Commissioners (5-0 moratorium extension through Dec 31; 5-0 to draft permanent prohibition), GA — Bulloch County Commissioners (5-0 moratorium extension through Dec 31; 5-0 to draft permanent prohibition), GA data center moratorium statesboroherald.com →
- Camden County — Six-month data center moratorium gpb.org →
- Carroll County — 100-day data center and BESS moratorium (unincorporated areas) times-georgian.com →
- Chatham County — 155-day moratorium on data centers of 10 MW or more thecurrentga.org →
- Cherokee County — Data center moratorium extended by 180 days wsbtv.com →
- Clayton County — Clayton County data center moratorium claytoncountyga.gov →
- Cobb County — 180-day data center moratorium (unincorporated areas) fox5atlanta.com →
- Colquitt County — County moratorium on data centers moultrieobserver.com →
- Coweta County — 180-day moratorium on data center proposals wsbtv.com →
- DeKalb County — Data center moratorium, repeatedly extended wabe.org →
- Decatur County — County moratorium on data centers wctv.tv →
- Dougherty County — Data center moratorium, extended walb.com →
- Douglas County — 90-day data center moratorium fox5atlanta.com →
- Fannin County — Data center moratorium extended through Dec. 31, 2026 citizenportal.ai →
- Fayetteville — 90-day moratorium, later permanent ban fayette-news.net →
- Forest Park — 90-day data center moratorium news-daily.com →
- Franklin County — County moratorium on data centers through December 31, 2028 921wlhr.com →
- Garden City — Six-month data center moratorium thecurrentga.org →
- Gordon County — Local moratorium on data centers through January 29, 2027 discovergordoncounty.com →
- Griffin (Spalding County) and 1 other locality — 2 separate measures, cited together griffindailynews.com →
- Hall County — 180-day moratorium (data centers, high-density residential, detention centers) accessnorthga.com →
- Hart County — County moratorium on data centers 921wlhr.com →
- Lamar County and 1 other locality — 2 separate measures, cited together gpb.org →
- Lincoln County — Data center moratorium through Dec. 31, 2026 citizenportal.ai →
- Lovejoy — Citywide ban on data centers atlantanewsfirst.com →
- Lowndes County — County moratorium on data centers through October 25, 2026 valdostadailytimes.com →
- Madison County — County moratorium on data centers 921wlhr.com →
- Marietta — Six-month data center moratorium fox5atlanta.com →
- Meriwether County — Data center moratorium extended 90 days meriwethercountyga.gov →
- Monroe County — Bolingbroke data center rezoning denied govtech.com →
- Murray County — Data center moratorium extended to July 7, 2027 hoodline.com →
- Newton County — Data center moratorium (extended 180 days) covnews.com →
- Palmetto — Local moratorium on data centers with no end date wabe.org →
- Paulding County — Local moratorium on data centers through January 1, 2027 fox5atlanta.com →
- Rockdale County (data center + battery-energy-storage moratorium extended through Sept 8), GA — Rockdale County (data center + battery-energy-storage moratorium extended through Sept 8), GA data center moratorium atlantanewsfirst.com →
- Roswell — City moratorium on data centers through September 20, 2026 roswellconnections.com →
- Savannah — 155-day moratorium on large-scale data centers wtoc.com →
- Social Circle — Social Circle data center moratorium wsbtv.com →
- Thomas County — Thomas County data center moratorium wctv.tv →
- Walker County — Local moratorium on data centers through February 3, 2027 local3news.com →
- Candler County — Data center moratorium item tabled yahoo.com →
- Columbia County — Proposed local moratorium on data centers wfxg.com →
- Lee County (moratorium extension + dedicated data center zoning district), GA — Lee County (moratorium extension + dedicated data center zoning district), GA data center moratorium (proposed) leecountyga.gov →
- City of LaGrange — City of LaGrange data center moratorium (failed) wsbtv.com →
- Covington — City data center moratorium, lifted Aug. 31, 2026 covnews.com →
- Floyd County — Expired county moratorium on data centers through August 28, 2026 northwestgeorgianews.com →
- Hogansville — Expired local moratorium on data centers through September 1, 2026 lagrangenews.com →
- Jesup — Data center moratorium voted down yahoo.com →
- Kingsland — Expired city moratorium on data centers through August 9, 2026 kingslandgeorgia.com →
- Rockdale County — Expired county moratorium on data centers through September 8, 2026 fox5atlanta.com →
What does bind large loads in Georgia
A moratorium is only one way a data center gets stopped. The grid operator decides whether it can connect at all, and on what terms. Georgia sits in 1 footprint.
Georgia Power (Southern Co), Oglethorpe/EMCs, MEAG; no RTO.
States next door
5 of the 5 states bordering Georgia have at least one data-center measure on record. Restrictions tend to travel between neighbors, so this is usually where the next one comes from.
Data centers in Georgia
The US Data Center Map identifies 262 facilities run by 124 operators in Georgia, each one placed from primary sources and listed by city and by operator, with the measures on this page beside them.
Open the Georgia data center map → · The US Data Center Map →
How to read this page
In force = a moratorium, siting restriction, or tax-incentive rollback that is currently enacted, by statute or executive order. Paused = a temporary hold on new incentives or applications. Proposed = introduced and still pending. Failed / vetoed = died in committee, was voted down, or was vetoed.
This page is generated from the same primary-sourced dataset as the national U.S. Data Center Moratorium Tracker and is re-checked on the same weekly cycle, whether or not anything changed. Legislative status changes quickly; it is informational, not legal advice. Spot something out of date in Georgia? Tell us.
Companion references: the Data Center Grid Operator Watchlist for the interconnection and curtailment rules that bind here, the Data Center Water Tracker for water mandates, and the Data Center Delay Watchlist for named projects.
Why Georgia is pushing back
The objections repeat from state to state: strain on the electric grid, water drawn for cooling, and the sense that a facility takes local resources without giving much back. SAVRN builds AI factories designed around those three objections: on-site power that does not lean on the public grid, direct-to-chip cooling that does not consume municipal water, and a training institute that puts local people to work inside the building.