Tennessee Data Center Moratorium Tracker
Tennessee has 1 state-level data-center restriction in force. 1 more bill is pending. 38 city and county measures are tracked here, 33 of them in force. Every entry below links to its primary source: a legislature page, a governor's office, a local government, or the reporting of record.
State-level measures in Tennessee
Every statewide moratorium, pause, siting restriction, or tax-incentive rollback in Tennessee we can verify against a primary source. Strongest status first.
| Measure | Status | What it does | Source |
|---|---|---|---|
| HB 1847 / SB 2128Data Center Cost Responsibility Act | In force 2026-05 | Signed by Gov. Lee on May 7, 2026 and effective on signing. Requires owners and operators of proposed and existing data centers to pay the full cost of the utility infrastructure needed to serve them and bars electric utilities from raising other customers' rates to support data centers. The Senate passed it unanimously; the House passed it 76-14. | |
| SB 2584Taxes, Sales - As introduced, authorizes a qualified data center that applies for job tax credits to certify electronically that it has | Proposed 2026-04 | Tennessee SB 2584 (114): Taxes, Sales - As introduced, authorizes a qualified data center that applies for job tax credits to certify electronically that it has not, within the previous 12 months. Last action 2026-04-20: Placed on Senate Finance, Ways, and Means Committee calendar for 4/21/2026. | |
| SB 2266Taxes, Sales - As enacted, specifies that any entity that qualifies for exemption as a spallation neutron source facility will not be eligible for a sales | Failed / vetoed 2018-05 | Tennessee SB 2266 (110): Taxes, Sales - As enacted, specifies that any entity that qualifies for exemption as a spallation neutron source facility will not be eligible for a sales and use tax exemption with regard to any. Last action 2018-05-18: Effective date(s) 05/15/2018. | |
| SB 2653Tennessee: SB2653 creates the Tennessee Data Center Impact Review Act, establishing a formal review process for data center impacts on communities | Failed / vetoed 2026-02 | SB2653 creates the Tennessee Data Center Impact Review Act, establishing a formal review process for data center impacts on communities, environment, and infrastructure. The bill amends multiple Tennessee Code sections across eight titles and was introduced February 2, 2026 with companion bill HB2392. It was deferred in the Senate Commerce and Labor Committee to March 17, 2026, while HB2392 was placed on the Agriculture and Natural Resources Subcommittee calendar for March 18. SB 2653 (Impact Review Act) stalled in Senate Commerce & Labor; TN adjourned Apr 23, 2026 with only the industry-friendly self-generation bill passing. |
City and county moratoria in Tennessee
Most of the movement is local, where a building pause or permit halt does not need a legislative session. 38 tracked measures in Tennessee, each with its source.
Where Tennessee stands
Across the whole tracker we hold 334 state-level measures in 49 states and 1253 city and county measures, against 1419 primary sources. Tennessee accounts for 4 of the state-level measures and 38 of the local ones.
By total measures on record it is #15 of the 50 states and DC carrying any tracked action, and #12 by city and county measures alone. Ranking is by count of sourced entries in this dataset, so it measures documented activity, not the size of the buildout.
Sources for Tennessee
40 citations behind the entries above. Each opens in a new tab.
- Statewide · HB 1847 / SB 2128 — Data Center Cost Responsibility Act wkrn.com →
- Statewide · SB 2584 — Taxes, Sales - As introduced, authorizes a qualified data center that applies for job tax credits to certify electronically that it has wapp.capitol.tn.gov →
- Statewide · SB 2266 — Taxes, Sales - As enacted, specifies that any entity that qualifies for exemption as a spallation neutron source facility will not be eligible for a sales wapp.capitol.tn.gov →
- Statewide · SB 2653 — Tennessee: SB2653 creates the Tennessee Data Center Impact Review Act, establishing a formal review process for data center impacts on communities wapp.capitol.tn.gov →
- Anderson County and 1 other locality — 2 separate measures, cited together wvlt.tv →
- Bristol — Local moratorium on data centers through October 24, 2027 supertalk929.com →
- Carter County — Local moratorium on data centers through August 17, 2027 elizabethton.com →
- Cedar Hill — Local moratorium on data centers through June 1, 2028 mainstreetmediatn.com →
- Cedar Hill (Robertson County, mayor proposing 2-year data center + crypto moratorium), TN — Cedar Hill (Robertson County, mayor proposing 2-year data center + crypto moratorium), TN data center moratorium fox17.com →
- Clinton — Local moratorium on data centers through December 22, 2026 mycouriernews.com →
- Coffee County — One-year data center moratorium newschannel5.com →
- Crossville — Local moratorium on data centers through August 12, 2028 1025wowcountry.com →
- Dickson County — Six-month moratorium on data center rezonings mainstreetmediatn.com →
- Grundy County — County moratorium on data centers through May 18, 2028 sewaneemessenger.com →
- Hamblen County — County moratorium on data centers through July 7, 2027 hamblencountytn.gov →
- Hamilton County — County moratorium on data centers through July 15, 2027 local3news.com →
- Hawkins County — Resolution banning data centers and cryptocurrency mines wjhl.com →
- Johnson City — Data center moratorium extended to Dec. 3, 2026 supertalk929.com →
- Jonesborough and 1 other locality — 2 separate measures, cited together servercountry.org →
- Knox County — One-year data center moratorium (through June 30, 2027) wate.com →
- Knoxville — One-year moratorium on large data centers (10 MW+) knoxvilletn.gov →
- Loudon County — County moratorium on data centers through December 30, 2026 wvlt.tv →
- Maury County — County moratorium on data centers through July 19, 2027 frontporchradiotn.com →
- McMinnville — Local moratorium on data centers through December 3, 2027 wsmv.com →
- McMinnville (18-month data center moratorium, first reading), TN — McMinnville (18-month data center moratorium, first reading), TN data center moratorium theucnow.com →
- Morgan County — County moratorium on data centers through June 12, 2028 themountainpress.com →
- Nashville — Local moratorium on data centers through December 1, 2026 nashvillebanner.com →
- Nashville-Davidson County — Data center permit moratorium plus zoning regulations wsmv.com →
- Roane County — Roane County data center moratorium wvlt.tv →
- Shelbyville — Local moratorium on data centers for a stated term wsmv.com →
- Smithville — 18-month moratorium on data centers and crypto mining wjle.com →
- Spring City — Two-year moratorium on AI data centers wdef.com →
- Washington County — One-year data center moratorium (through June 30, 2027) wjhl.com →
- White County — County moratorium on data centers with no end date wsmv.com →
- Wilson County — Temporary data center moratorium mainstreetmediatn.com →
- Memphis — Proposed 12-month data center pause businessinsider.com →
- Gallatin — Proposed twelve-month moratorium on new data centers newschannel5.com →
- Moore County — Moore County data center moratorium (proposed) mcobserver.news →
- Rutherford County — Proposed six-month data center moratorium cpo.soar.com →
- Sullivan County — Sullivan County data center moratorium (proposed) heraldcourier.com →
What does bind large loads in Tennessee
A moratorium is only one way a data center gets stopped. The grid operator decides whether it can connect at all, and on what terms. Tennessee sits in 2 footprints.
TVA serves nearly the whole state, no RTO; Appalachian Power/AEP's Kingsport-area territory in northeast TN is PJM (TN is in PJM's 13-state list).
States next door
8 of the 8 states bordering Tennessee have at least one data-center measure on record. Restrictions tend to travel between neighbors, so this is usually where the next one comes from.
Data centers in Tennessee
The US Data Center Map identifies 75 facilities run by 31 operators in Tennessee, each one placed from primary sources and listed by city and by operator, with the measures on this page beside them.
Open the Tennessee data center map → · The US Data Center Map →
How to read this page
In force = a moratorium, siting restriction, or tax-incentive rollback that is currently enacted, by statute or executive order. Paused = a temporary hold on new incentives or applications. Proposed = introduced and still pending. Failed / vetoed = died in committee, was voted down, or was vetoed.
This page is generated from the same primary-sourced dataset as the national U.S. Data Center Moratorium Tracker and is re-checked on the same weekly cycle, whether or not anything changed. Legislative status changes quickly; it is informational, not legal advice. Spot something out of date in Tennessee? Tell us.
Companion references: the Data Center Grid Operator Watchlist for the interconnection and curtailment rules that bind here, the Data Center Water Tracker for water mandates, and the Data Center Delay Watchlist for named projects.
Why Tennessee is pushing back
The objections repeat from state to state: strain on the electric grid, water drawn for cooling, and the sense that a facility takes local resources without giving much back. SAVRN builds AI factories designed around those three objections: on-site power that does not lean on the public grid, direct-to-chip cooling that does not consume municipal water, and a training institute that puts local people to work inside the building.