Nebraska Data Center Moratorium Tracker
Nebraska has 3 state-level data-center restrictions in force. 23 city and county measures are tracked here, 19 of them in force. Every entry below links to its primary source: a legislature page, a governor's office, a local government, or the reporting of record.
State-level measures in Nebraska
Every statewide moratorium, pause, siting restriction, or tax-incentive rollback in Nebraska we can verify against a primary source. Strongest status first.
| Measure | Status | What it does | Source |
|---|---|---|---|
| NebraskaNebraska: LB1261 was signed April 10, 2026, allowing private developers to build and own power plants to serve large-scale electricity users like data centers | In force 2026-03 | LB1261 was signed April 10, 2026, allowing private developers to build and own power plants to serve large-scale electricity users like data centers, and prohibiting Nebraska's public power utilities from using eminent domain to acquire such plants. Connected to Google's proposed Nebraska data center that could require 1,000-3,000 MW (3x Lincoln's peak demand). The Legislature passed it 34-7 despite opposition arguing it fast-tracks a new business model threatening Nebraska's land, water, and utility rates. | |
| Executive Order 26-17Ends ImagiNE Act tax incentives for new data centers | In force 2026-07 | Gov. Pillen barred new data-center applications from ImagiNE Act tax incentives and ordered a multi-agency review and resource task force. Pillen framed it as a tax-incentive rollback, expressly 'not a moratorium.' | |
| State of NebraskaNebraska: Gov. Jim Pillen signed an executive order ending future ImagiNE Nebraska Act tax incentives for new data-center applications | In force 2026-07 | Gov. Jim Pillen signed an executive order ending future ImagiNE Nebraska Act tax incentives for new data-center applications; existing/already-approved projects are unaffected. Pillen characterized this explicitly as NOT a moratorium. The order also creates a task force to study resource-protection safeguards covering land, water, and electricity impacts of data centers. Distinct from the pending LB1111 statewide regulation bill, which remains in the Natural Resources Committee (see nebraska-statewide-ne-2026-01-16). | |
| LB 1319Eliminate a sales and use tax exemption relating to data centers | Failed / vetoed 2024-04 | Nebraska LB 1319 (108): Eliminate a sales and use tax exemption relating to data centers. Last action 2024-04-18: Indefinitely postponed. | |
| LB 209Provide tax exemptions relating to data centers | Failed / vetoed 2024-04 | Nebraska LB 209 (108): Provide tax exemptions relating to data centers. Last action 2024-04-18: Indefinitely postponed. | |
| LB 1131Adopt the Domestic Violence and Human Trafficking Service Providers Tax Credit Act and eliminate personal property tax and sales and use tax exemptions | Failed / vetoed 2026-04 | Nebraska LB 1131 (109): Adopt the Domestic Violence and Human Trafficking Service Providers Tax Credit Act and eliminate personal property tax and sales and use tax exemptions relating to data centers. Last action 2026-04-17: Indefinitely postponed. | |
| LB 468Change provisions relating to inheritance taxes, change certain fee and tax provisions, and eliminate a sales tax exemption relating to data centers | Failed / vetoed 2026-04 | Nebraska LB 468 (109): Change provisions relating to inheritance taxes, change certain fee and tax provisions, and eliminate a sales tax exemption relating to data centers. Last action 2026-04-17: Indefinitely postponed. |
City and county moratoria in Nebraska
Most of the movement is local, where a building pause or permit halt does not need a legislative session. 23 tracked measures in Nebraska, each with its source.
Where Nebraska stands
Across the whole tracker we hold 334 state-level measures in 49 states and 1253 city and county measures, against 1419 primary sources. Nebraska accounts for 7 of the state-level measures and 23 of the local ones.
By total measures on record it is #20 of the 50 states and DC carrying any tracked action, and #22 by city and county measures alone. Ranking is by count of sourced entries in this dataset, so it measures documented activity, not the size of the buildout.
Sources for Nebraska
21 citations behind the entries above. Each opens in a new tab.
- Statewide · Nebraska — Nebraska: LB1261 was signed April 10, 2026, allowing private developers to build and own power plants to serve large-scale electricity users like data centers nebraskapublicmedia.org →
- Statewide · Executive Order 26-17 — 2 separate measures, cited together governor.nebraska.gov →
- Statewide · LB 1319 — Eliminate a sales and use tax exemption relating to data centers nebraskalegislature.gov →
- Statewide · LB 209 — Provide tax exemptions relating to data centers nebraskalegislature.gov →
- Statewide · LB 1131 — Adopt the Domestic Violence and Human Trafficking Service Providers Tax Credit Act and eliminate personal property tax and sales and use tax exemptions nebraskalegislature.gov →
- Statewide · LB 468 — Change provisions relating to inheritance taxes, change certain fee and tax provisions, and eliminate a sales tax exemption relating to data centers nebraskalegislature.gov →
- Box Butte County and 8 other localities — 9 separate measures, cited together nebraskapublicmedia.org →
- Broken Bow — Broken Bow data center moratorium writing.strisker.com →
- Butler County — County moratorium on data centers for a stated term journal-news.com →
- Cass County — Cass County data center moratorium (proposed) klkntv.com →
- Cherry County — Six-month conditional-use-permit moratorium metro.newschannelnebraska.com →
- Fillmore County — 24-month moratorium on new data center applications (Resolution 2026-10) fillmorecountyne.gov →
- Gage County — 12-month moratorium on data center permits klkntv.com →
- Nance County — 12-month data center moratorium (Resolution 26-13) nancecountyne.gov →
- Nehawka — Town moratorium on data centers with no end date wowt.com →
- Otoe County — One-year data center moratorium journalstar.com →
- Seward County — One-year data center moratorium ksnblocal4.com →
- Garfield County — Proposed county moratorium on data centers nebraskapublicmedia.org →
- Hall County — Proposed county moratorium on data centers yahoo.com →
- Lancaster County — Proposed data center moratorium set aside for task forces nebraskapublicmedia.org →
- Lincoln County — Data center moratorium (rejected 3-2) knopnews2.com →
What does bind large loads in Nebraska
A moratorium is only one way a data center gets stopped. The grid operator decides whether it can connect at all, and on what terms. Nebraska sits in 1 footprint.
All-public-power state; NPPD, OPPD, and LES completed SPP membership 4/1/2009.
States next door
6 of the 6 states bordering Nebraska have at least one data-center measure on record. Restrictions tend to travel between neighbors, so this is usually where the next one comes from.
Data centers in Nebraska
The US Data Center Map identifies 39 facilities run by 20 operators in Nebraska, each one placed from primary sources and listed by city and by operator, with the measures on this page beside them.
Open the Nebraska data center map → · The US Data Center Map →
How to read this page
In force = a moratorium, siting restriction, or tax-incentive rollback that is currently enacted, by statute or executive order. Paused = a temporary hold on new incentives or applications. Proposed = introduced and still pending. Failed / vetoed = died in committee, was voted down, or was vetoed.
This page is generated from the same primary-sourced dataset as the national U.S. Data Center Moratorium Tracker and is re-checked on the same weekly cycle, whether or not anything changed. Legislative status changes quickly; it is informational, not legal advice. Spot something out of date in Nebraska? Tell us.
Companion references: the Data Center Grid Operator Watchlist for the interconnection and curtailment rules that bind here, the Data Center Water Tracker for water mandates, and the Data Center Delay Watchlist for named projects.
Why Nebraska is pushing back
The objections repeat from state to state: strain on the electric grid, water drawn for cooling, and the sense that a facility takes local resources without giving much back. SAVRN builds AI factories designed around those three objections: on-site power that does not lean on the public grid, direct-to-chip cooling that does not consume municipal water, and a training institute that puts local people to work inside the building.