Utah Data Center Moratorium Tracker

Utah has 2 state-level data-center restrictions in force. 10 city and county measures are tracked here, 9 of them in force. Every entry below links to its primary source: a legislature page, a governor's office, a local government, or the reporting of record.

Last updated October 2026 2 state-level measures 10 local measures 12 primary sources
Utah
UT
In force
2
State-level measures on record, 2 in force
10
City and county measures, 9 in force
12
Primary sources cited on this page
#36
of 50 states with anything on record, by measure count

State-level measures in Utah

Every statewide moratorium, pause, siting restriction, or tax-incentive rollback in Utah we can verify against a primary source. Strongest status first.

MeasureStatusWhat it doesSource
HB 76Utah: In Utah, Governor Cox signed HB 76 on March 23, 2026, Requiring new data centers (10,000+ sq ft) to notify water providers of projected demands In force 2026-02 In Utah, Governor Cox signed HB 76 on March 23, 2026, Requiring new data centers (10,000+ sq ft) to notify water providers of projected demands and report actual water consumption annually to the state. Sponsored by Rep. Jill Koford (R-Ogden), the bill nearly failed in the Senate but passed after being amended to apply only to new facilities. The bill had unanimous support in the House and was part of a broader legislative push to protect Great Salt Lake and conserve water.
Executive Order 2026-03A higher bar for data-center development In force 2026-05 Gov. Cox created a Data Center Framework directing agencies to apply heightened review for water (Great Salt Lake), air quality, ratepayers, and wildlife, plus a new unused-water provision. This raises the siting bar rather than imposing a hard ban.

City and county moratoria in Utah

Most of the movement is local, where a building pause or permit halt does not need a legislative session. 10 tracked measures in Utah, each with its source.

Box Elder County
2026-06
In force
180-day data center moratorium
Commissioners unanimously imposed a 180-day moratorium on new data centers and data center power plants in unincorporated areas June 10, 2026; the MIDA-approved Stratos Project is not covered.
Box Elder County (180-day data center moratorium; Stratos/MIDA exempt), UT
2026-06
In force
Box Elder County (180-day data center moratorium; Stratos/MIDA exempt), UT data center moratorium
On June 10, 2026 the Box Elder County Commission unanimously approved a 180-day moratorium on new data center development in unincorporated Box Elder County (zoned and unzoned land), to study land-use codes and data-center guidelines. The Kevin O'Leary-backed Stratos Project is EXPLICITLY EXEMPT because MIDA projects bypass standard local land-use approval, so residents (BEAR mobilized for the meeting) argued the moratorium is insufficient; one told commissioners 'your descendants will curse you.' Hence a mixed outcome. In-window follow-up coverage (Utah Public Radio, June 17, 2026; KSL) on the Box Elder County Commission's June 10, 2026 unanimous 180-day moratorium on new data centers and data-center power plants in unincorporated areas. The reporting explicitly confirms the moratorium does NOT apply to the controversial Stratos Project, because the commission...
Cache County
2026-06
In force
180-day data center moratorium
County Council voted 6-0 to enact a 180-day moratorium on data center developments in unincorporated areas while it drafts county codes.
Clearfield
2026-09
In force
City moratorium on data centers through March 7, 2027
180-day moratorium on data center development, 4-0 unanimous; preemptive, no proposal pending; city code had no definition or zoning for data centers. Prompted by Stratos project in neighboring Box Elder County. The measure runs to March 7, 2027.
Grand County
2026-07
In force
Local moratorium on data centers through January 3, 2027
180-day temporary land use regulation, unanimous: pauses acceptance, processing and approval of applications, permits and licenses for data centers, data center power plants and associated digital infrastructure. Pre-emptive -- nothing was in the queue. The measure runs to January 3, 2027.
Logan
2026-06
In force
Local moratorium on data centers through December 27, 2026
180-day temporary land use regulation (Ordinance 26-12): the city will not accept, process or approve any application or permit for a data center or data center power plant within city limits while it writes permanent rules. End date is 180 days from adoption. The measure runs to December 27, 2026.
Milford
2026-06
In force
City moratorium on data centers through December 13, 2026
Ordinance 04-2026: 180-day moratorium on data centers, data center power plants, and solar energy facilities; 5-0 unanimous. Council determined data centers are not appropriate land use within city limits. The measure runs to December 13, 2026.
Salt Lake County
2026-09
In force
Proposed 180-day data center temporary land use regulation
The Salt Lake County Council unanimously adopted a resolution on Tuesday, Sept. 15, 2026 directing staff to develop data center regulations for unincorporated areas. Under the resolution the county will not consider new data centers until the rules are adopted, expected by mid-February 2027. This is a resolution-based pause, not a formally adopted 180-day moratorium ordinance.
Wayne County
2026-07
In force
Local moratorium on data centers through January 17, 2027
Resolution 2026-04: immediate 180-day moratorium on all land use applications for data centers, data center power plants (explicitly including nuclear) and supporting digital infrastructure, unanimous. County code did not address data centers at all. The measure runs to January 17, 2027.
Iron County
2026-09
Paused
Iron County is making new rules while data center development is paused
Iron County is pausing data center development while new rules are being created. This action was reported on 2026-09-18.

Would you like the weekly update?

Every week we re-verify every state and local measure on this map and publish what changed. You get one email when it goes out.

Also send me

Receive a short introduction on days 3, 7 and 14, plus the updates you select. Unsubscribe in one click. Privacy ·

You're on the list. The next weekly update will land in your inbox when it publishes.
You are subscribed. Read the latest tracker

Where Utah stands

Across the whole tracker we hold 334 state-level measures in 49 states and 1253 city and county measures, against 1419 primary sources. Utah accounts for 2 of the state-level measures and 10 of the local ones.

By total measures on record it is #36 of the 50 states and DC carrying any tracked action, and #33 by city and county measures alone. Ranking is by count of sourced entries in this dataset, so it measures documented activity, not the size of the buildout.

Sources for Utah

12 citations behind the entries above. Each opens in a new tab.

  • Statewide · HB 76 — Utah: In Utah, Governor Cox signed HB 76 on March 23, 2026, Requiring new data centers (10,000+ sq ft) to notify water providers of projected demands (In force, 2026-02) le.utah.gov →
  • Statewide · Executive Order 2026-03 — A higher bar for data-center development (In force, 2026-05) governor.utah.gov →
  • Box Elder County — 180-day data center moratorium (In force, 2026-06) sltrib.com →
  • Box Elder County (180-day data center moratorium; Stratos/MIDA exempt), UT — Box Elder County (180-day data center moratorium; Stratos/MIDA exempt), UT data center moratorium (In force, 2026-06) ksl.com →
  • Cache County — 180-day data center moratorium (In force, 2026-06) hjnews.com →
  • Clearfield — City moratorium on data centers through March 7, 2027 (In force, 2026-09) standard.net →
  • Grand County — Local moratorium on data centers through January 3, 2027 (In force, 2026-07) moabtimes.com →
  • Logan — Local moratorium on data centers through December 27, 2026 (In force, 2026-06) loganutah.gov →
  • Milford — City moratorium on data centers through December 13, 2026 (In force, 2026-06) utah.gov →
  • Salt Lake County — Proposed 180-day data center temporary land use regulation (In force, 2026-09) sltrib.com →
  • Wayne County — Local moratorium on data centers through January 17, 2027 (In force, 2026-07) ironcountytoday.com →
  • Iron County — Iron County is making new rules while data center development is paused (Paused, 2026-09) news.google.com →

See all 1419 sources across every state →

What does bind large loads in Utah

A moratorium is only one way a data center gets stopped. The grid operator decides whether it can connect at all, and on what terms. Utah sits in 2 footprints.

Non-RTO utility territoryDominant
No RTO or ISO market here. Interconnection terms, study queues and curtailment rights for a large load are set by the individual utility and its state commission.
SPP
Speed in exchange for curtailability under the approved HILL framework.

PacifiCorp/Rocky Mountain Power non-RTO (WECC); Deseret Power joined SPP RTO West 4/1/2026.

See the full Data Center Grid Operator Watchlist →

States next door

6 of the 6 states bordering Utah have at least one data-center measure on record. Restrictions tend to travel between neighbors, so this is usually where the next one comes from.

Data centers in Utah

The US Data Center Map identifies 49 facilities run by 20 operators in Utah, each one placed from primary sources and listed by city and by operator, with the measures on this page beside them.

Open the Utah data center map → · The US Data Center Map →

How to read this page

In force = a moratorium, siting restriction, or tax-incentive rollback that is currently enacted, by statute or executive order. Paused = a temporary hold on new incentives or applications. Proposed = introduced and still pending. Failed / vetoed = died in committee, was voted down, or was vetoed.

This page is generated from the same primary-sourced dataset as the national U.S. Data Center Moratorium Tracker and is re-checked on the same weekly cycle, whether or not anything changed. Legislative status changes quickly; it is informational, not legal advice. Spot something out of date in Utah? Tell us.

Companion references: the Data Center Grid Operator Watchlist for the interconnection and curtailment rules that bind here, the Data Center Water Tracker for water mandates, and the Data Center Delay Watchlist for named projects.

Why Utah is pushing back

The objections repeat from state to state: strain on the electric grid, water drawn for cooling, and the sense that a facility takes local resources without giving much back. SAVRN builds AI factories designed around those three objections: on-site power that does not lean on the public grid, direct-to-chip cooling that does not consume municipal water, and a training institute that puts local people to work inside the building.