SAVRN Research · Capital Atlas · Louisiana

Louisiana Data Center Investment Tracker

Louisiana carries 7 named site commitments worth at least $102B in disclosed capital, set against 3 projects blocked, delayed or restricted, 1 of them in the courts, as of October 8, 2026.

Updated October 8, 2026 7 named sites 3 blocked, delayed or restricted 5 financing transactions 39 sources
Louisiana
LA
7 capital providers on record
Named sites
7
Site-level commitments the atlas records in Louisiana
Disclosed capital floor
$102B
Sum of sites with a stated dollar figure. Sites without one are listed, not counted
Disclosed capacity
6,675 MW
Sum of sites with a stated megawatt figure
Blocked, delayed or restricted
3
$12.0B of announced capital in those projects
Who is investing

Who is investing in data centers in Louisiana?

The largest disclosed commitments in Louisiana are Meta Platforms (Hyperion, Holly Ridge, Richland Parish, ≥$50.0B); IPI Partners / Blue Owl (Meta Hyperion campus (Blue Owl JV), ~$27.0B); Amazon (AWS) (AWS northwest Louisiana campuses (Caddo and Bossier parishes, incl. third campus at Resilient Technologies Park, Shreveport), $18.0B). Together the 7 named sites here carry a disclosed floor of $102B; sites with no dollar figure are listed but not counted.
Named sites

Named data center sites in Louisiana

Each row is one site-level commitment with its capital provider, the figure the source states, and the status the source gives it. Capital is shown as one compact figure; the verbatim wording is in the row's sources.

SiteCapital providerPlaceCapitalMWStatusSources
Hyperion, Holly Ridge, Richland Parish
Announced December 2024; Blue Owl JV 21 October 2025; $50B+/5 GW scope reported July 2026
Meta Platforms
with Blue Owl Capital, Entergy
Holly Ridge, Richland Parish ≥$50.0B 5,000 construction
Meta Hyperion campus (Blue Owl JV)
JV entered October 21, 2025
IPI Partners / Blue Owl
with Meta
Richland Parish ~$27.0B n.a. announced
AWS northwest Louisiana campuses (Caddo and Bossier parishes, incl. third campus at Resilient Technologies Park, Shreveport)
Announced 18 August 2026 (prior $12 billion commitment announced 23 February 2026)
Amazon (AWS)
with Southwestern Electric Power Company (SWEPCO)
Shreveport, Caddo and Bossier parishes $18.0B n.a. announced
Applied Digital Delta Forge 1
Leases signed 20-22 April 2026; state announcement 26 May 2026; PSC expedited review 16 September 2026
Applied Digital Boyce, Rapides Parish ≥$3.6B 430 announced
River Bend campus
Construction progress reported 4 August 2026
Hut 8
with Fluidstack, Anthropic
St. Francisville, West Feliciana Parish $3.2B 245 under construction
Project Barracuda energy park and co-located data center (La. 1)
Named in the ONE Nuclear and Hennessy VII closing release 23 September 2026; location and acreage reported by NOLA 28 September 2026
ONE Nuclear Energy
with Landowners under letters of intent
Along La. 1 near the Ascension-Iberville parish line, Iberville Parish n.a. 1,000 proposed
Project Cayman energy project and co-located data center campus
Binding LOI announced 31 August 2026 (company release)
One Nuclear Energy
with Unnamed Louisiana landowner group
Ascension Parish n.a. n.a. announced
Capital at risk

Blocked, delayed or restricted in Louisiana

Every project in Louisiana on the atlas's capital-at-risk record: the action taken, who took it, and the announced capital affected. Restarts and reversals are recorded with the same weight as blocks.

ProjectDeveloperJurisdictionActionCapitalSources
Amazon/AWS Caddo Parish
moratorium February 2, 2026
Amazon/AWS Caddo Parish
Following Governor Jeff Landry's announcement of Amazon's $12 billion investment in three interconnected data center campuses across Caddo, Louisiana, and Bossier parishes, Commissioner Chris Kracman proposed a one-year
$12.0B
Amazon west Shreveport data center special-use permit (appeal)
under appeal Appeal argued 29 September 2026; no ruling yet
Amazon Louisiana Second Circuit Court of Appeal / City of Shreveport
On Tuesday 29 September 2026 the Louisiana Second Circuit Court of Appeal heard opponents' challenge to the Shreveport City Council's unanimous approval of a special-use permit for an Amazon data center in west Shreveport, which the Metropolitan Planning Commission had initially denied. Opponents' attorney Clay Garside argued the council approved the permit without a detailed operational plan on noise, light and water impacts or a Louisiana DEQ water withdrawal permit; the city argued the application met requirements. The judges did not rule at the hearing.
n.a.
Caddo Parish data center moratorium referral (Resolution 53)
other Referral rejected 6-4 on 31 August 2026
Amazon Web Services (area projects) Caddo Parish Commission
Caddo Parish commissioners voted 6-4, with two members absent, against Resolution 53, which would have asked the parish Planning and Zoning Commission to consider recommending a moratorium on data center construction in commercially and industrially zoned parts of unincorporated Caddo Parish. The measure was introduced by Commissioner John-Paul Young after public concern over data center development in the region. An earlier effort to enact a parishwide moratorium directly had stalled after the parish attorney said it required an ordinance.
n.a.
Financing

Financing transactions tied to Louisiana sites

Transactions the atlas ties to a named site in Louisiana: joint ventures, project bonds, credit facilities, leases and power agreements. Amounts are as stated; overlapping commitments are never summed.

PartiesInstrumentAmountDateSiteSources
Meta + Blue Owl Capital
Meta and funds managed by Blue Owl Capital entered a joint venture to develop and own the Hyperion data center campus, with the parties committing pro rata shares of approximately $27 billion in total development costs. Blue Owl made a cash contribution of approximately $7 billion, Meta received a one-time distribution of approximately $3 billion, leases have a four-year initial term with extension options, and Meta provided a residual value guarantee for the first 16 years of operations.
jv equity ~$27.0B Joint venture agreement entered 21 October 2025 Hyperion, Holly Ridge, Richland Parish
Blue Owl + Meta
JV for the Hyperion campus with a four-year initial lease term and a residual value guarantee covering the first 16 years of operations.
jv equity ~$27.0B entered October 21, 2025 Meta Hyperion campus (Blue Owl JV)
Applied Digital + undisclosed US hyperscaler
Applied Digital subsidiaries APLD AEX-01 LLC and APLD AEX-02 LLC signed leases on 20 and 22 April 2026 with a US hyperscaler for 300 MW of critical IT load at Delta Forge 1, a 430 MW campus near Boyce, Rapides Parish, Louisiana, worth about $7.5 billion over about 15 years, with operations from mid-2027
lease ≥$7.5B April 23, 2026 Applied Digital Delta Forge 1
Entergy + Meta
Utility Entergy is planning three new natural gas plants near the Hyperion site at a cost of $3 billion. This record describes the original 2024 plan. For the 5 GW expansion Entergy has proposed seven additional generating units, which are before the Louisiana Public Service Commission; see the Hyperion site record. A second Entergy Louisiana agreement with Meta, filed with the Louisiana PSC on 25 March 2026, adds seven combined-cycle gas units of more than 5,200 MW plus batteries and 500 kV transmission, paid for by Meta (recorded separately as entergy-meta-evest-seven-ccgt-2026).
other $3.0B Announced alongside the December 2024 Hyperion announcement Hyperion, Holly Ridge, Richland Parish
Entergy Louisiana + Meta (Evest LLC)
Under a second agreement supporting Meta's Hyperion campus in Richland Parish, Entergy Louisiana plans, paid for by Meta, seven new natural gas combined-cycle units totaling more than 5,200 MW (about 5,278 MW, roughly 754 MW each; four near the Richland Parish campus and three near Big Cajun in Pointe Coupee Parish), three battery storage projects and about 240 miles of new 500 kV transmission. The customer entity is Evest LLC. The Louisiana PSC holds a three-day evidentiary hearing from 7 October; intervenors include the Alliance for Affordable Energy, Sierra Club, Union of Concerned Scientists, Louisiana Energy Users Group and Walmart. This is in addition to the three gas plants approved in 2025 (meta-entergy-gas-plants).
power supply agreement n.a. Agreement announced by Entergy Louisiana in late March 2026; LPSC application filed 25 March 2026 (Docket U-37882); evidentiary hearing set for 7 to 9 October; LPSC decision expected 16 December 2026 Hyperion, Holly Ridge, Richland Parish
Policy context

What governs a data center in Louisiana

New Orleanscity
New Orleans passed a one-year moratorium, part of a broader wave of political exposure that also includes Madison, Wisconsin and a complete moratorium passed by the Seminole Nation in March.
Louisiana (PSC vote on Meta Hyperion records)state
Applies to discovery in Entergy Louisiana's applications to build generation for Meta's Hyperion campus in Richland Parish
The Louisiana Public Service Commission voted 3-1 on 12 August 2026, along party lines with one commissioner absent, to overturn an administrative law judge's order that would have required Meta to disclose how it calculated job projections and electricity needs for Hyperion. Advocacy groups sought the records before the commission approves Entergy's additional generating units for the 5 GW expansion. According to an Earthjustice release of 28 September 2026, the Alliance for Affordable Energy and the Union of Concerned Scientists, represented by Earthjustice, have appealed the commission's decision to the Civil District Court for the 19th Judicial District, asking it to reverse the vote and reinstate the subpoena the administrative law judge granted in July, which would require Meta to substantiate Hyperion's job and electricity load projections in the review of Entergy Louisiana's proposed seven additional gas plants (advocacy group release).
Louisiana (PSC large-load fast-track directive)state
Large-load applications that meet the criteria (15-year electric service agreement, demonstrated capacity need, customer paying at least half the cost of new infrastructure, Louisiana Economic Development letter of support) get an eight-month commission timeline and may skip market-based testing for new generation. Adopted 16 December 2025. An acceleration measure, not a moratorium
At its monthly meeting in Natchitoches on Tuesday 16 December 2025 the Louisiana Public Service Commission voted 3-2 to adopt Commissioner Jean-Paul Coussan's directive, aligned with Gov. Jeff Landry's Lightning Speed Initiative executive order of September 2025, letting utilities bypass the market-based mechanism used since the 1980s to show they are pursuing least-cost power when serving qualifying large loads such as data centers. Applications meeting the criteria get commission action within eight months. Commissioner Davante Lewis and consumer advocates objected that it weakens consumer protections; Lewis's separate proposal for a broader review of large-load interconnection and cost allocation was deferred to January 2026 on a 4-1 vote.

The policy layer for Louisiana lives in three companion references: the Louisiana Data Center Moratorium Tracker for every state measure and local moratorium on record, the Water Tracker for the water rules that touch a site, and the Grid Operator Watchlist for the large-load rules of the RTO or utility that decides whether it can energize.

On the map

Data centers in Louisiana

The US Data Center Map identifies 22 facilities run by 10 operators in Louisiana, each one placed from primary sources and listed by city and by operator, with this atlas record beside it.

Sources

Sources for Louisiana

Every source cited on this page, once each. The full atlas source register is at Capital Atlas sources.

The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.