North Dakota Data Center Investment Tracker
North Dakota carries 6 named site commitments worth at least $26.9B in disclosed capital, set against 4 projects blocked, delayed or restricted, 3 of them moratoria or delays, as of October 8, 2026.
Who is investing in data centers in North Dakota?
Named data center sites in North Dakota
Each row is one site-level commitment with its capital provider, the figure the source states, and the status the source gives it. Capital is shown as one compact figure; the verbatim wording is in the row's sources.
| Site | Capital provider | Place | Capital | MW | Status | Sources |
|---|---|---|---|---|---|---|
Polaris Forge 1 Building 2 completed (250 MW operational) 2 October 2026; third building ready-for-service calendar 2027 |
Applied Digital with CoreWeave |
Ellendale | ~$11.0B | 400 | operating | |
Project Fighting Pike data center (southwest of U.S. Highway 2 and U.S. 85 Bypass) Subdivision plat approved 25 March 2025; delay to late 2028 or early 2029 reported 17 September 2026; single outlet |
Critical Data House | Williston, Williams County | $10.0B | n.a. | announced | |
Polaris Forge 2 broke ground August 18, 2025 |
Applied Digital | Harwood | $5.0B | 200 | construction | |
Applied Digital Polaris Forge 1 facility executed October 7, 2025; first-tranche financing February 2025 |
Macquarie Asset Management with Applied Digital, CoreWeave |
Ellendale | $900M | 400 | construction | |
Harmony Energy Park data center (near the Bison Substation) Conditional use permit application filed; reported 29 September 2026 (North Dakota Monitor) |
Geronimo Power with Otter Tail Power (proposed large load tariff under PSC review) |
Harmony Township, north of Mapleton, Cass County | n.a. | 540 | proposed | |
Applied Digital Polaris Forge 3 May 20, 2026 |
Applied Digital | Center, Oliver | n.a. | 300 | announced |
Blocked, delayed or restricted in North Dakota
Every project in North Dakota on the atlas's capital-at-risk record: the action taken, who took it, and the announced capital affected. Restarts and reversals are recorded with the same weight as blocks.
| Project | Developer | Jurisdiction | Action | Capital | Sources |
|---|---|---|---|---|---|
Project Fighting Pike data center (Critical Data House) delayed Plat approved 25 March 2025; delay to late 2028 or early 2029 reported 17 September 2026; single outlet |
Critical Data House | City of Williston (title acquisition under Hague Convention service) | Critical Data House originally said its $10 billion, 450-acre Williston data center would operate by January 2027. No work has started since the city approved the subdivision plat on 25 March 2025, because the company cannot take clear title until more than 1,100 foreign investors in an abandoned development on the land, mostly in Malaysia and Singapore, are served under Hague Convention procedures. The company told the Williston Herald it now expects operations in late 2028 or early 2029, with a 20 to 24 month build once it holds title. |
$10.0B | |
Mandan large-scale data center ban (citizen petition, special election) other Special election set for 15 December 2026 (reported 7 October 2026); single outlet |
n.a. | City of Mandan | Following a citizen petition, Mandan voters will decide in a special election on Tuesday 15 December 2026 whether to ban large-scale data centers, City Administrator Jim Neubauer said; the measure cannot share a date with a separate special election for a vacant City Commission seat. |
n.a. | |
Mercer County campus (530+ acres) moratorium Mar 4 2026; dollar value n.a. |
NextEra / Boulevard Associates | Mercer County, ND | One-year moratorium |
n.a. | |
Morton County data center and cryptocurrency facility moratorium moratorium Hearing 12 September 2024 (adoption date not stated in sources); still in place 10 September 2026 when a data center ordinance passed 4-1; lifting pending |
n.a. | Morton County Commission | Morton County scheduled a public hearing for 12 September 2024 on a moratorium on data centers, following a July 2024 moratorium on direct air capture facilities. The Bismarck Tribune reported that the county's moratorium on data centers and cryptocurrency facilities, adopted by resolution, was still in place when the commission approved a data center ordinance 4-1 on 10 September 2026. The commission considered lifting the moratorium that day, but staff said a notice period was required and expected it at the next meeting. |
n.a. |
Financing transactions tied to North Dakota sites
Transactions the atlas ties to a named site in North Dakota: joint ventures, project bonds, credit facilities, leases and power agreements. Amounts are as stated; overlapping commitments are never summed.
| Parties | Instrument | Amount | Date | Site | Sources |
|---|---|---|---|---|---|
Applied Digital + CoreWeave Additional 150MW lease with CoreWeave, taking Ellendale to 400MW. |
lease | ≥$11.0B | August 29, 2025 | Polaris Forge 1 | |
Applied Digital + CoreWeave Two 15-year lease agreements with CoreWeave at Ellendale, North Dakota. |
lease | ~$7.0B | June 2, 2025 | Polaris Forge 1 | |
Applied Digital + unnamed investment-grade hyperscaler AI factory lease with a US-based, unnamed investment-grade hyperscaler at Polaris Forge 2. |
lease | $5.0B | October 22, 2025 | Polaris Forge 2 | |
Macquarie Asset Management + Applied Digital Executed with Macquarie Asset Management, not Blackstone (premise correction preserved from the source). |
preferred | $5.0B | executed October 7, 2025 | Applied Digital Polaris Forge 1 | |
Applied Digital Senior secured notes funding Polaris Forge 2. |
senior notes | $2.1B | priced March 4, 2026 | Polaris Forge 2 | |
Applied Digital + Macquarie Asset Management Earlier Ellendale financing referenced in the first-tranche coverage. |
debt facility | $375M | February 2025 | Applied Digital Polaris Forge 1 | |
Applied Digital + Base Electron Corporation On 4 October 2026 Applied Digital entered into a Power Purchase Agreement and a related credit support agreement with Base Electron for capacity and energy from an approximately 1,200 MW natural gas-fired generation facility Base Electron is to develop in Center, North Dakota, as dedicated generation for the Polaris Forge 3 campus. The agreement has a 15-year delivery term and may be terminated by Base Electron if financial close for the plant has not occurred by 31 March 2027. Base Electron is a related party: Applied Digital owns about 10% and it is owned and managed by certain Applied Digital officers and directors, including Wes Cummins; Applied Digital also holds a demand promissory note from Base Electron of up to $100 million ($59.3 million outstanding at 31 August 2026). |
ppa | n.a. | Signed 4 October 2026; disclosed in Applied Digital's Form 10-Q and earnings release filed 7 October 2026 | Applied Digital Polaris Forge 3 |
What governs a data center in North Dakota
The policy layer for North Dakota lives in three companion references: the North Dakota Data Center Moratorium Tracker for every state measure and local moratorium on record, the Water Tracker for the water rules that touch a site, and the Grid Operator Watchlist for the large-load rules of the RTO or utility that decides whether it can energize.
Data centers in North Dakota
The US Data Center Map identifies 26 facilities run by 10 operators in North Dakota, each one placed from primary sources and listed by city and by operator, with this atlas record beside it.
Sources for North Dakota
Every source cited on this page, once each. The full atlas source register is at Capital Atlas sources.
- stocktitan.netStockTitan 10-K summary
- ir.applieddigital.comAPLD
- ir.applieddigital.comAPLD
- sec.govSEC EDGAR (Applied Digital FY2026 Q4 press release, 27 July 2026)
- markets.businessinsider.comApplied Digital release via GlobeNewswire (Markets Insider), 2 October 2026
- ir.applieddigital.comApplied Digital release, 2 October 2026
- finance.yahoo.comProactive (Yahoo Finance)
- willistonherald.comWilliston Herald, 17 September 2026
- cnbc.comCNBC
- ir.applieddigital.comAPLD
- ir.applieddigital.comApplied Digital
- macquarie.comMacquarie
- datacenterdynamics.comDCD
- yahoo.comNorth Dakota Monitor (via Yahoo News), 29 September 2026
- kfgo.comKFGO, 30 September 2026
- ir.applieddigital.comAPLD
- sec.govSEC EDGAR (Applied Digital Form 10-Q, filed 7 October 2026)
- sec.govSEC EDGAR (Applied Digital Q1 FY2027 earnings release)
- kfyrtv.comKFYR-TV
- interconnectedcapital.comInterconnected Capital
- bismarcktribune.comBismarck Tribune
- govtech.comGovernment Technology (Bismarck Tribune/TNS)
- ir.applieddigital.comAPLD
- markets.businessinsider.comApplied Digital fiscal Q1 2027 results via GlobeNewswire (Markets Insider), 7 October 2026
- yahoo.comNorth Dakota Monitor via Yahoo
Every state, one page each
Figures beside each state are named sites and blocked, delayed or restricted projects.
Seven references, one system
Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.