SAVRN Research · Capital Atlas · New Hampshire

New Hampshire Data Center Investment Tracker

New Hampshire shows 5 blocked, delayed or restricted data center projects in the Capital Atlas, 1 cancelled or blocked, and no named capital commitment on record as of October 8, 2026.

Updated October 8, 2026 0 named sites 5 blocked, delayed or restricted 0 financing transactions 7 sources
New Hampshire
NH
0 capital providers on record
Named sites
0
Site-level commitments the atlas records in New Hampshire
Disclosed capital floor
n.a.
Sum of sites with a stated dollar figure. Sites without one are listed, not counted
Disclosed capacity
n.a.
Sum of sites with a stated megawatt figure
Blocked, delayed or restricted
5
Projects on the capital-at-risk record here
Who is investing

Who is investing in data centers in New Hampshire?

No capital provider has a named site commitment on record in New Hampshire as of October 8, 2026. The atlas records a site the day it can be tied to a filing, an issuer release, a government announcement or reporting of record, not before. The activity here is on the other side of the ledger: 5 projects blocked, delayed or restricted, listed below.
Named sites

Named data center sites in New Hampshire

No named site commitment is on record in New Hampshire as of October 8, 2026.
Capital at risk

Blocked, delayed or restricted in New Hampshire

Every project in New Hampshire on the atlas's capital-at-risk record: the action taken, who took it, and the announced capital affected. Restarts and reversals are recorded with the same weight as blocks.

ProjectDeveloperJurisdictionActionCapitalSources
Bow data center (former Merrimack Station site)
other 2 September 2026
Granite Shore Power State of New Hampshire
Governor Kelly Ayotte said on 2 September 2026 that she opposes the proposed Bow hyperscale data center and any data center in New Hampshire, and that she will include a multi-year moratorium in her next state budget proposal, which would not take effect before July 2027. She said an executive order could impose a ban sooner. State House Democrats separately announced plans to file 24-month moratorium legislation for the 2027 session. The project is at feasibility-study stage: Eversource Energy is conducting a study at Granite Shore Power's request for a hyperscale data center tied to the Bow coal plant that ceased operating in 2025. No moratorium has been enacted and no formal application has been filed. FERC filings describe a preliminary Eversource study, requested by Merrimack Station owner Granite Shore Power, on the viability of connecting a 350 MW project to the grid, while an Eversource executive mentioned a developer considering a data center of up to 200 MW in Bow. On 2 September 2026 Gov. Kelly Ayotte said she opposes the potential Bow data center and plans to propose a statewide moratorium on data centers.
n.a.
Canterbury data center moratorium
moratorium Enacted March 2026
n.a. Canterbury
Canterbury, New Hampshire, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated March 2026. Voters approved zoning amendment banning data centers in all zones, 322-63; Planning Board proposed marking 'Data Centers' as 'Not Allowed' in every zone. The measure has no end date by design.
n.a.
Nottingham 12-month data center moratorium
moratorium Approved by town vote 8 September 2026; reported 9 September 2026; 12 months
n.a. Town of Nottingham
Nottingham voters approved a 12-month moratorium on any data center development within town limits by 1,335 votes to 143. The moratorium gives town officials time to consider permanent zoning changes. A Merrimack County Superior Court judge dismissed a lawsuit arguing the ballot question was misleading and too confusing to go before voters.
n.a.
Nottingham Business Park data center
withdrawn Withdrawn 27 May 2026
Thomas Moulton Town of Nottingham
Developer Thomas Moulton withdrew his proposal to convert a vacant Route 4 warehouse into a data center on 27 May 2026, hours before a planning board meeting where a large turnout was expected. More than 25,000 people signed a petition against it, citing water, energy costs, noise and the Lamprey River watershed. The withdrawal letter said the applicant would study whether the use is appropriate, leaving a possible return open.
n.a.
Rochester data center moratorium
moratorium Enacted September 2026
n.a. Rochester
Rochester, New Hampshire, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated September 2026. City Council enacted ordinance prohibiting data centers in every zoning district except Recycling Industrial zone (conditional use permit required); Waste Management owns most land in that zone, making construction effectively impossible. Two hours of resident testimony at Aug 18 public hearing. The measure has no end date by design.
n.a.
Policy context

What governs a data center in New Hampshire

New Hampshire (statewide)state
No moratorium enacted. Governor Kelly Ayotte said on 2 September 2026 she will propose a multi-year moratorium in her next state budget, effective no earlier than July 2027, and raised the possibility of an earlier executive order. State House Democrats plan 24-month moratorium legislation for the 2027 session. No project-level dollar or megawatt figures disclosed.
New Hampshire enters the atlas as a proposed-restriction jurisdiction rather than an enacted one. The governor stated opposition to siting any data center in the state on energy-price grounds, in the context of a Granite Shore Power hyperscale proposal at the retired Bow coal plant for which Eversource Energy is conducting a feasibility study.

The policy layer for New Hampshire lives in three companion references: the New Hampshire Data Center Moratorium Tracker for every state measure and local moratorium on record, the Water Tracker for the water rules that touch a site, and the Grid Operator Watchlist for the large-load rules of the RTO or utility that decides whether it can energize.

On the map

Data centers in New Hampshire

The US Data Center Map identifies 17 facilities run by 7 operators in New Hampshire, each one placed from primary sources and listed by city and by operator, with this atlas record beside it.

Sources

Sources for New Hampshire

Every source cited on this page, once each. The full atlas source register is at Capital Atlas sources.

The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.