Skip to page content
SAVRN
Search Plan a project
SAVRN Research · Capital Atlas · Kansas

Kansas Data Center Investment Tracker

Kansas carries 5 named site commitments worth at least $10.9B in disclosed capital, set against 19 projects blocked, delayed or restricted, 1 cancelled or blocked and 12 delayed or under moratorium, as of October 8, 2026.

Updated October 8, 2026 5 named sites 19 blocked, delayed or restricted 2 financing transactions 52 sources
Kansas
KS
5 capital providers on record
Named sites
5
Site-level commitments the atlas records in Kansas
Disclosed capital floor
$10.9B
Sum of sites with a stated dollar figure. Sites without one are listed, not counted
Disclosed capacity
1,700 MW
Sum of sites with a stated megawatt figure
Blocked, delayed or restricted
19
$12.9B of announced capital in those projects
Who is investing

Who is investing in data centers in Kansas?

The largest disclosed commitments in Kansas are Alcove Development (Project Catalyst data center (across from Osawatomie State Hospital), ~$10.0B); DAMAC Digital (DAMAC Group) (DAMAC Digital Edgerton data center (Logistics Park Kansas City), $860M). Together the 5 named sites here carry a disclosed floor of $10.9B; sites with no dollar figure are listed but not counted.
Named sites

Named data center sites in Kansas

Each row is one site-level commitment with its capital provider, the figure the source states, and the status the source gives it. Capital is shown as one compact figure; the verbatim wording is in the row's sources.

SiteCapital providerPlaceCapitalMWStatusSources
Project Catalyst data center (across from Osawatomie State Hospital)
KCUR 18 September 2026 (500 MW, $10 billion); acreage growth and amended pre-development agreement terms per city minutes as reported by KSHB 41
Alcove Development
with MDH Partners (Atlanta, financing the proposal), City of Osawatomie (pre-development agreement)
Osawatomie, Miami County ~$10.0B 500 proposed
DAMAC Digital Edgerton data center (Logistics Park Kansas City)
Council approval Thursday 16 July 2026
DAMAC Digital (DAMAC Group) Edgerton, Johnson County $860M n.a. approved
Project Bluestem hyperscale data center
First proposed March 2026; resubmitted at up to 1.2 GW; county public meeting 16 September 2026 (KCTV)
Cloverleaf Infrastructure Tonganoxie, Leavenworth County n.a. 1,200 proposed
Digital Realty Ad Astra Enterprise Park campus
Reported 10 August 2026
Digital Realty Trust De Soto, Johnson County n.a. n.a. approved
Project Helium (Sharon)
Development agreement approved 31 August 2026
Alphabet / Google Sharon, Barber County n.a. n.a. announced
Capital at risk

Blocked, delayed or restricted in Kansas

Every project in Kansas on the atlas's capital-at-risk record: the action taken, who took it, and the announced capital affected. Restarts and reversals are recorded with the same weight as blocks.

ProjectDeveloperJurisdictionActionCapitalSources
Red Wolf hyperscale data center (Parallel Parkway)
litigation North tract rezoning failed 31 July 2025; lawsuit reported on hold November 2025
Red Wolf DCD Properties Unified Government of Wyandotte County and Kansas City, Kansas
The Unified Government approved zoning for the $12 billion campus in May 2025, but protest petitions triggered a supermajority requirement and on 31 July 2025 the north side rezoning failed that threshold on a 7-3 vote. Landowners then sued over the rezoning, and KCUR reported in November 2025 that the petition and lawsuit had put the project on hold. Data Center Watch reported that on 29 October 2025 a Wyandotte County judge let the south tract case proceed.
~$12.0B
DAMAC Digital Edgerton data center (citizen ban petition)
litigation Site plans approved mid-July 2026; ruling for petitioners 3 September 2026; mandamus hearing 24 September 2026, briefs due 9 October 2026
DAMAC Digital Johnson County District Court / City of Edgerton
In mid-July 2026 the Edgerton City Council voted to deny a data center moratorium and overrode a planning commission rejection to approve final site plans for DAMAC Digital's US$860 million data center. Residents then filed a petition with 208 signatures to ban large data centers, which county officials validated, but the city sued to stop it. On Thursday 3 September 2026 Johnson County District Judge Stephanie Goodenow ruled the city's suit violated the Kansas Public Speech Protection Act and that the petition can move forward for now. On Thursday 24 September 2026 petition organizers Carrie Schmidt and Kim Twente argued for a writ of mandamus ordering the city to submit the ban referendum to the Johnson County Election Office; attorneys for Edgerton and DAMAC argued the plan is not subject to a referendum. Briefs are due 9 October 2026, after which Judge Stephanie Goodenow will issue a written opinion. Organizers said the timeline rules out the November ballot and they hope for a special election.
$860M
Beale Infrastructure data center application (Gardner)
withdrawn Withdrawal announced 6 May 2026; single outlet
Beale Infrastructure City of Gardner
The City of Gardner announced on Wednesday 6 May 2026 that Beale Infrastructure had withdrawn its data center application. According to the city's press release, Gardner told the developer it would not offer tax incentives for the project, and Beale then withdrew. About 200 people from three counties had turned out at the City Council meeting two days earlier to oppose the proposal; Beale said it would not move forward with the project at this time.
n.a.
Bourbon County 365-day moratorium (data centers, crypto mining, utility-scale power, waste disposal)
moratorium Enacted 3-0 on 15 June 2026; 365 days; single outlet
n.a. Bourbon County Commission
The Bourbon County Commission enacted a 365-day moratorium on utility-scale power generation, crypto mining, data center and waste disposal operations under Resolution 24-26 on Monday 15 June 2026. The vote was 3-0, with Commissioners Joe Allen and Gregg Motley abstaining; a previous moratorium had expired the day before. Solar projects of Tennyson Creek Solar LLC, Tennyson Creek Solar II LLC and Hinton Creek Solar LLC are exempt, and the county hired a consultant to write a comprehensive plan and zoning regulations.
n.a.
El Dorado citizen initiative banning high-impact data centers and Tier 2 and Tier 3 battery storage for 10 years
other Court ruling 21 August 2026; ballot resolution 5-0 on 25 August 2026; election November 2026
n.a. City of El Dorado; Butler County District Court
Protect the Heartland submitted a petition with more than 700 signatures to ban high-impact data centers and Tier 2 and Tier 3 battery energy storage systems in El Dorado, and the city sought a declaratory judgment that it was not a proper initiative, heard on 14 August 2026. A district judge ruled for the petitioners on Friday 21 August 2026, and the City Commission voted 5-0 at a special meeting on 25 August to place a 10-year ban on the November 2026 ballot. The Kansas City Star reported on 22 September 2026 that the judge ruled the vote's outcome will be binding.
n.a.
Emporia digital infrastructure district and citizen data center ban petition
litigation Ordinances approved 5-0 on 22 July 2026; landowner suit filed 19 August 2026 (reported 2 October 2026); petition placed on November 2026 ballot by court order in August 2026
n.a. City of Emporia
On 22 July 2026 the Emporia City Commission voted 5-0 to approve three ordinances establishing a digital infrastructure district. It did not act on a validated citizen petition to ban high-impact data centers. If commissioners did not approve the petition within three weeks, it was to go to the November 2026 general election ballot. The city did not adopt the petition ordinance and sought judicial review; in August 2026 Senior Judge Glenn Braun of Lyon County District Court ordered the question onto the November 2026 ballot without deciding whether the petition is legislative or administrative, so its legal status remains pending. The Kansas City Star reported on 22 September 2026 that the Emporia judge ruled the ordinance's legal effect stays pending a final ruling regardless of the election result, and that no further hearing had been scheduled. Separately, three landowners (Amanda Mendoza, Kenneth Bruner and Ann Bruner) filed suit against the City of Emporia in Lyon County District Court on 19 August 2026 asking the court to declare the 22 July approvals (Ordinances 26-21, 26-22 and 26-23: the Digital Infrastructure Overlay District, the rezoning of 11 tracts and their placement in the overlay) unlawful and unreasonable. They allege the city applied the overlay before the ordinance creating it took effect and set no adequate standards for development agreements. A clerk's order of 18 September 2026 extended the city's time to respond to 8 October 2026; there has been no ruling on the merits. The Emporia Gazette describes the citizen question on the November 2026 ballot as a 10-year ban.
n.a.
Harvey County data center moratorium (through 2028)
moratorium Approved unanimously 13 January 2026; runs through the end of 2028; single outlet
n.a. Harvey County Commission
The Harvey County Commission unanimously approved a resolution on Tuesday 13 January 2026 placing a moratorium on construction of data centers in unincorporated parts of the county through the end of 2028. The county said no application had been submitted and that the pause gives its planning and zoning bodies time to write regulations; the commission can rescind or extend it at any time.
n.a.
Kingman County data center moratorium
moratorium Enacted February 2026
n.a. Kingman County
Kingman County, Kansas, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated February 2026. Resolution No. 2026-R9 imposing temporary moratorium on data centers in unincorporated county. The measure has no documented term.
n.a.
Lawrence two-year large-scale data center moratorium
moratorium Approved unanimously 14 July 2026; two years
n.a. City of Lawrence
The Lawrence City Commission unanimously approved a two-year moratorium on large-scale data centers on 14 July 2026, doubling the initially proposed duration. The measure includes an exception process to limit liability. Staff will study longer-term code changes and draft regulations.
n.a.
Lyon County data center and battery storage moratorium
moratorium Approved 23 July 2026; data center moratorium runs to 22 January 2027
n.a. Lyon County Board of County Commissioners
Lyon County commissioners approved two moratorium resolutions on Thursday 23 July 2026. Resolution No. 12-26 halts applications for data centers and battery energy storage systems until 22 January 2027, and Resolution No. 13-26 halts commercial solar applications until 1 December 2026. Both may be extended, amended or ended by the commission. The vote came a day after the Emporia City Commission approved data center resolutions at a heated 22 July meeting.
n.a.
Marysville 12-month data center moratorium
moratorium Adopted unanimously on 14 September 2026; runs 12 months
n.a. City of Marysville
Marysville City Council unanimously adopted a 12-month moratorium on data center development at its Monday meeting (14 September 2026). No applications for data center development will be accepted or processed during the moratorium. The pause gives the Planning Commission and city staff time to examine zoning changes and hear from residents and stakeholders. The ordinance defines data centers broadly to include cloud computing and AI infrastructure.
n.a.
McPherson County data center moratorium
moratorium Enacted January 2026
n.a. McPherson County
McPherson County, Kansas, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated January 2026. Resolution 2026-21; permanent ban on data centers and utility-scale battery storage in unincorporated areas. Voted 3-0. Replaced earlier moratorium from summer 2025. The measure has no end date by design.
n.a.
Miami County data center moratorium
moratorium Enacted January 2026
n.a. Miami County
Miami County, Kansas, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated January 2026. Three-year moratorium restricting data centers, battery storage, and similar technologies in unincorporated areas; excludes Osawatomie's in-city Project Catalyst site. The measure has a stated duration whose end date is not recorded.
n.a.
Ottawa citizen initiative to ban data centers over 25 MW (Lightfield Energy Proximity Park)
litigation Ballot ruling 3 September 2026; next hearing 20 October 2026; election November 2026; final legal ruling pending
Lightfield Energy LLC (Proximity Park buyer) Franklin County District Court / City of Ottawa
Franklin County District Court Judge Eric W. Godderz ruled on Thursday 3 September 2026 that a citizen-initiated ordinance banning data centers using more than 25 MW in Ottawa will go on the November 2026 ballot. Ottawa United Inc. had sued the city, alleging it ignored a petition verified on 7 August with the required 658 signatures, after commissioners took no action on legal advice. The court still must decide whether the ordinance is legislative or administrative. The measure targets a proposed 300-acre Proximity Park development that Lightfield Energy agreed to buy in December 2024. The Kansas City Star reported on 22 September 2026 that the ordinance's legal effect stays pending a final ruling regardless of the vote, with the next hearing on 20 October 2026.
n.a.
Rose Hill citizen initiative banning data centers and battery energy storage (kept off ballot)
other Resolution passed 5 October 2026
n.a. City of Rose Hill
On Monday 5 October 2026 the Rose Hill City Council passed Resolution 719 declaring that a citizen petition (230 signatures, almost 100 more than required) for an ordinance banning certain data centers and battery energy storage systems is administrative rather than legislative and so exempt from the initiative process, keeping it off the ballot. The council authorized the city attorney to defend the decision in court, distinguishing the El Dorado ruling that sent a similar initiative to the ballot.
n.a.
Sedgwick County campus (1,000+ acres)
moratorium Adopted January 2026; third extension 2 September 2026, to at least 25 December 2026; next decision 2 December 2026
n.a. Sedgwick County, KS
Moratorium active, extended twice. The county's interim development control on hyperscale data centers, in place since 14 January 2026, was extended for a third time on Wednesday 2 September 2026, by three months to at least 25 December 2026; proposed zoning rules were to be released 24 September 2026 and commissioners plan to consider continuing the pause into 2027 on 2 December 2026.
n.a.
Shawnee County data center moratorium
moratorium Enacted August 2026
n.a. Shawnee County
Shawnee County, Kansas, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated August 2026. 2-1: no final action on data center land use applications until 17 February 2027. Applications may still be filed, Compass Datacenters can resubmit, they just cannot be decided. The measure runs to 17 February 2027.
n.a.
South Hutchinson data center moratorium
moratorium Enacted May 2026
n.a. South Hutchinson
South Hutchinson, Kansas, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated May 2026. One-year moratorium on large-scale data centers and battery energy storage systems; revised after original draft would have halted even small-scale container-sized data centers. The measure runs to 26 May 2027.
n.a.
Topeka 12-month data center and battery storage moratorium
moratorium Approved 14 July 2026; 12 months; utility-connection amendment 11 August 2026
n.a. City of Topeka
The Topeka City Council unanimously approved a 12-month moratorium on data centers within the city on Tuesday 14 July 2026, amending it before the vote to include battery storage facilities. On 11 August 2026 the council amended the moratorium to restrict city utility connections for data centers inside and outside city limits, preventing staff from extending service to a data center outside the city. The measure followed Compass Datacenters' proposed 10-building campus southwest of Topeka in Shawnee County, which has its own moratorium (row 574).
n.a.
Financing

Financing transactions tied to Kansas sites

Transactions the atlas ties to a named site in Kansas: joint ventures, project bonds, credit facilities, leases and power agreements. Amounts are as stated; overlapping commitments are never summed.

PartiesInstrumentAmountDateSiteSources
Digital Realty + Seller not disclosed
Digital Realty announced the purchase of about 1,440 acres at Astra Enterprise Park near Kansas City for $475 million, a powered land site it said would support 600 MW by early 2028 and 2 GW at full delivery. The three transactions announced that day were funded mainly by issuing 6.3 million common shares and operating partnership units at a weighted average of $197.54. The release does not name the seller or state a closing date.
acquisition ~$475M Announced 22 June 2026 (company release) Digital Realty Ad Astra Enterprise Park campus
Digital Realty + City of De Soto
Digital Realty applied to use an existing 2021 tax increment financing district at Ad Astra Enterprise Park in De Soto, Kansas, for a nine-building campus on about 1,400 acres. Phase 1 construction is expected in 2027 to 2028 and Phase 2 in 2028 to 2031
incentive n.a. Reported 10 August 2026 Digital Realty Ad Astra Enterprise Park campus
Policy context

What governs a data center in Kansas

Kansas (KCC order on Evergy Large Load Power Service tariff)state
Applies to new facilities above 75 MW in Evergy's Kansas territories; approved Thursday 6 November 2025. Conditions on service, not a moratorium
The Kansas Corporation Commission approved on Thursday 6 November 2025 a settlement among Evergy's Kansas utilities, the Data Center Coalition, the Sierra Club, the Natural Resources Defense Council, Google and others creating a large load power service rate plan for new facilities over 75 MW. Customers may ramp up over as long as five years, must then take service for at least 12 years, pay a minimum monthly bill based on 80% of contract demand and pay for transmission upgrades needed to serve them. KCC staff estimated large-load customers will pay 7% to 10% more than existing industrial customers. The plan includes four clean energy options. Evergy had cited more than 20 prospective large-load customers totaling over 6 GW in Kansas.

The policy layer for Kansas lives in three companion references: the Kansas Data Center Moratorium Tracker for every state measure and local moratorium on record, the Water Tracker for the water rules that touch a site, and the Grid Operator Watchlist for the large-load rules of the RTO or utility that decides whether it can energize.

On the map

Data centers in Kansas

The US Data Center Map identifies 20 facilities run by 11 operators in Kansas, each one placed from primary sources and listed by city and by operator, with this atlas record beside it.

Sources

Sources for Kansas

Every source cited on this page, once each. The full atlas source register is at Capital Atlas sources.

The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.

Have a specific address? Site Intelligence reads all seven references against one location, county, utility and grid operator included, and cites every finding.
Check an address →