Mississippi Data Center Investment Tracker

Mississippi carries 7 named site commitments worth at least $74.8B in disclosed capital, set against 5 projects blocked, delayed or restricted, 1 of them in the courts, as of October 8, 2026.

Updated October 8, 2026 7 named sites 5 blocked, delayed or restricted 1 financing transaction 26 sources
Mississippi
MS
6 capital providers on record
Named sites
7
Site-level commitments the atlas records in Mississippi
Disclosed capital floor
$74.8B
Sum of sites with a stated dollar figure. Sites without one are listed, not counted
Disclosed capacity
1,446 MW
Sum of sites with a stated megawatt figure
Blocked, delayed or restricted
5
Projects on the capital-at-risk record here
Who is investing

Who is investing in data centers in Mississippi?

The largest disclosed commitments in Mississippi are xAI (now operating under SpaceX / "SpaceXAI") (Colossus 2, Southaven, ~$35.8B); Brookfield (BAM / Brookfield Infrastructure Partners) (Compass Datacenters Meridian hyperscale campus, $10.0B); Ontario Teachers' Pension Plan (OTPP) (Compass Datacenters Meridian campus, $10.0B). Together the 7 named sites here carry a disclosed floor of $74.8B; sites with no dollar figure are listed but not counted.
Named sites

Named data center sites in Mississippi

Each row is one site-level commitment with its capital provider, the figure the source states, and the status the source gives it. Capital is shown as one compact figure; the verbatim wording is in the row's sources.

SiteCapital providerPlaceCapitalMWStatusSources
Colossus 2, Southaven
Projections to Q1 2027
xAI (now operating under SpaceX / "SpaceXAI") Southaven ~$35.8B 946 construction
Compass Datacenters Meridian hyperscale campus
eight-year construction period
Brookfield (BAM / Brookfield Infrastructure Partners)
with Ontario Teachers' Pension Plan
Meridian, Lauderdale County $10.0B 500 announced
Compass Datacenters Meridian campus
Ontario Teachers' Pension Plan (OTPP)
with Brookfield Infrastructure, Compass Datacenters
Meridian, Lauderdale $10.0B n.a. announced
Madison County data center complexes
Amazon (AWS) Madison County $10.0B n.a. announced
Eagle Rock Partners digital infrastructure campus (Jefferson Davis County)
Public hearing held Tuesday 29 September 2026; reported 29 to 30 September 2026 (WDAM; Mississippi Today headline, article walled to fetch)
Eagle Rock Partners
with Jefferson Davis County Economic Development Association
Near Bassfield (Gum Swamp Road, at the Covington County line), Jefferson Davis County ~$6.0B n.a. proposed
Vicksburg campus
Timeline presented 17 September 2026; operations targeted early 2029
Amazon (AWS) Vicksburg $3.0B n.a. announced
SpaceXAI Tulane Road data center (MZX Tech)
Approved 1 September 2026; reported 2 September 2026
MZX Tech LLC (SpaceXAI affiliate)
with City of Southaven
Southaven, DeSoto County n.a. n.a. approved
Capital at risk

Blocked, delayed or restricted in Mississippi

Every project in Mississippi on the atlas's capital-at-risk record: the action taken, who took it, and the announced capital affected. Restarts and reversals are recorded with the same weight as blocks.

ProjectDeveloperJurisdictionActionCapitalSources
DeSoto Innovation District data center component (Church Road and Craft Road)
delayed Data center use removed 9 June 2026; aldermen tabled project 4 August 2026
n.a. Olive Branch Planning Commission; Board of Mayor and Aldermen
The Olive Branch Planning Commission unanimously voted to deny the DeSoto Innovation District rezoning, and the data center conditional use was removed from the plan at the commission's 9 June meeting, according to the city's planning director. On 4 August the Board of Mayor and Aldermen tabled the 562-acre project after a three-hour hearing where many of the more than 100 residents present opposed it, some citing concern that a data center could return in later phases. A motion to approve only the first-phase landfill expansion and deny the industrial rezoning failed 4-3.
n.a.
Jackson 183-day data center moratorium
moratorium Imposed July 2026; 183 days
n.a. City of Jackson
The Jackson City Council approved a 183-day moratorium on data center development by a 5-2 vote, described as Mississippi's first. Council members said the capital city was not ready for a data center.
n.a.
Olive Branch data center zoning restrictions (conditional use only)
other Approved 18 August 2026; effective immediately
n.a. Olive Branch Board of Mayor and Aldermen
The Olive Branch Board of Mayor and Aldermen unanimously approved an ordinance, effective immediately, that allows data centers in the M-1 and M-2 industrial zones only as a conditional use instead of by right. The rules bar data centers without closed-loop cooling, restrict generator use between 2 and 5 p.m., set nighttime and daytime noise limits for hyperscale sites and require developers to pay full decommissioning costs. The city's planning director said Olive Branch could not adopt a moratorium, citing litigation risk.
n.a.
Walls industrial rezoning of about 1,200 acres (possible data center use)
other Planning Commission denial 22 September 2026; Board of Aldermen vote not scheduled
n.a. Town of Walls Planning Commission
After a public hearing on 22 September 2026, the Walls Planning Commission voted to deny a request to rezone roughly 1,200 acres from Agricultural Residential to M-1 Light Industrial, which would have opened the land to possible data center construction. Residents cited proximity to Lake Cormorant schools, a historic site and the xAI plant in Southaven. The Board of Aldermen has the final say, and no date had been set.
n.a.
xAI Southaven data center power plant
litigation NAACP challenge April 2026; resident suit June 2026; Memphis residents' federal class action filed 23 September 2026
xAI DeSoto County / Mississippi DEQ
xAI's Southaven site runs gas turbines to power its Memphis-area data centers, and the Mississippi Department of Environmental Quality issued an air permit for 41 permanent turbines. The NAACP filed a challenge in April 2026 alleging significant pollutant emissions and contesting the permit. Three Southaven residents filed suit in June 2026 alleging near-constant noise and vibration harming their health. The plant continues to operate. On 30 July 2026 the Mississippi Commission of Environmental Quality and MZX Tech LLC entered an Agreed Order covering the 69 mobile turbines at the Stanton Road facility, setting a retirement schedule after supply chain delays pushed back some of the 41 permitted stationary turbines. SpaceXAI said all temporary turbines would be removed by July 2027 as its 1.2 GW permanent plant comes online, and announced on 31 August 2026 that 11 of the 69 turbines had been powered down. A class action over turbine noise is pending in the US District Court for the Northern District of Mississippi On 30 July 2026 SpaceX announced an agreement with the Mississippi Department of Environmental Quality setting a timeline to remove all 69 temporary mobile turbines at the Southaven power site, starting as early as August and finishing by July 2027, as the 1.2 GW permanent plant of 41 turbines permitted in March 2026 comes online. On 23 September 2026 Lieff Cabraser Heimann & Bernstein and Greer Injury Lawyers filed a federal class action in Tennessee against X.AI Corp and MZX Tech LLC on behalf of southern Memphis residents, alleging noise ordinance violations, private and public nuisance, negligence, negligence per se and trespass from the data centers and gas-turbine plant on the Tennessee and Mississippi border. It seeks damages, abatement and an injunction to cease operations unless they can run without harming the community. Earlier, on 6 May 2026, the NAACP, represented by the Southern Environmental Law Center and Earthjustice, asked the federal court for a preliminary injunction to stop operation of the unpermitted turbines, saying xAI and MZX Tech had added six turbines after the February 2026 notice, bringing the total to 33.
n.a.
Financing

Financing transactions tied to Mississippi sites

Transactions the atlas ties to a named site in Mississippi: joint ventures, project bonds, credit facilities, leases and power agreements. Amounts are as stated; overlapping commitments are never summed.

PartiesInstrumentAmountDateSiteSources
xAI
xAI seeks $12bn in debt to fund the Colossus 2 data center, per DCD.
debt facility $12.0B Per summary table; first chips online in a few weeks per DCD headline Colossus 2, Southaven
Policy context

What governs a data center in Mississippi

The policy layer for Mississippi lives in three companion references: the Mississippi Data Center Moratorium Tracker for every state measure and local moratorium on record, the Water Tracker for the water rules that touch a site, and the Grid Operator Watchlist for the large-load rules of the RTO or utility that decides whether it can energize.

On the map

Data centers in Mississippi

The US Data Center Map identifies 14 facilities run by 6 operators in Mississippi, each one placed from primary sources and listed by city and by operator, with this atlas record beside it.

Sources

Sources for Mississippi

Every source cited on this page, once each. The full atlas source register is at Capital Atlas sources.

The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.