Iowa Data Center Investment Tracker

Iowa carries 3 named site commitments worth at least $7.0B in disclosed capital, set against 22 projects blocked, delayed or restricted, 1 cancelled or blocked and 19 delayed or under moratorium, as of October 8, 2026.

Updated October 8, 2026 3 named sites 22 blocked, delayed or restricted 0 financing transactions 40 sources
Iowa
IA
1 capital provider on record
Named sites
3
Site-level commitments the atlas records in Iowa
Disclosed capital floor
$7.0B
Sum of sites with a stated dollar figure. Sites without one are listed, not counted
Disclosed capacity
n.a.
Sum of sites with a stated megawatt figure
Blocked, delayed or restricted
22
$350M of announced capital in those projects
Who is investing

Who is investing in data centers in Iowa?

The largest disclosed commitments in Iowa are Alphabet / Google (Iowa: Council Bluffs expansion and new Cedar Rapids data center, $7.0B). Together the 3 named sites here carry a disclosed floor of $7.0B; sites with no dollar figure are listed but not counted.
Named sites

Named data center sites in Iowa

Each row is one site-level commitment with its capital provider, the figure the source states, and the status the source gives it. Capital is shown as one compact figure; the verbatim wording is in the row's sources.

SiteCapital providerPlaceCapitalMWStatusSources
Iowa: Council Bluffs expansion and new Cedar Rapids data center
Within the next two years from announcement
Alphabet / Google Council Bluffs and Cedar Rapids $7.0B n.a. expansion
Potential Google data center, Salix (MidAmerican Energy site)
Google named 3 August 2026; reimbursement MOU reviewed by council September 2026
Alphabet / Google
with MidAmerican Energy
Salix, Woodbury County n.a. n.a. exploratory
Proposed Google data center near Duane Arnold Energy Center (Palo)
Palo ordinance passed 20 July 2026
Alphabet / Google
with NextEra Energy, City of Palo, Linn County
Palo (unincorporated Linn County, possible annexation), Linn County n.a. n.a. proposed
Capital at risk

Blocked, delayed or restricted in Iowa

Every project in Iowa on the atlas's capital-at-risk record: the action taken, who took it, and the announced capital affected. Restarts and reversals are recorded with the same weight as blocks.

ProjectDeveloperJurisdictionActionCapitalSources
Marshalltown data center moratorium (Swarm Systems Edgewood Industrial Park proposal)
moratorium Motion approved 5-2 on 13 July 2026; ordinance adopted 24 August 2026; land offer expired 11 September 2026; moratorium runs to 23 November 2026, extendable 60 days
Swarm Systems (proposal) City of Marshalltown
The Marshalltown City Council approved a four-month data center moratorium motion 5-2 at a 13 July 2026 meeting, after a six-month pause failed 4-3 about three weeks earlier. The moratorium ordinance was adopted on 24 August 2026 and halts acceptance, processing and issuance of data center permits, applications and zoning amendments until 23 November 2026, with a possible 60-day extension. Swarm Systems CEO Amir Atefi presented a plan to buy 21 acres in the Edgewood Industrial Park for a 150,000-square-foot data center, and said he would wait out the moratorium. Records made public after the offer expired show Swarm Systems offered the city $1,113,200 on 21 July 2026 for about 29.33 acres, then about a month later the same amount for 21.77 acres (about $51,135 an acre), with closing by 31 March 2027 and contingencies requiring the moratorium to lapse and zoning acceptable to the buyer. The council deadlocked on acting on the offer after the 24 August 2026 presentation and it expired on 11 September 2026. CEO Amir Atefi said the company is also looking at other sites in Iowa and other states but has not moved on from Marshalltown.
$350M
Adair County proposal
moratorium Mar 25 2026
Applied Digital Adair County, IA
Indefinite moratorium
n.a.
Boone County data center moratorium
moratorium Adopted 9 September 2026; up to one year
n.a. Boone County Board of Supervisors
The Boone County Board of Supervisors adopted a moratorium of up to one year on the establishment, construction or permitting of new data centers on Wednesday 9 September 2026. Supervisor Shawn Bryant said the pause allows time to study and adopt data center ordinances. WOI noted other Iowa pauses in Marshalltown, Linn County and Woodbury County.
n.a.
Buchanan County data center moratorium
moratorium Enacted January 2026
n.a. Buchanan County
Buchanan County, Iowa, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated January 2026. Temporary moratorium on data centers. The measure has a stated duration whose end date is not recorded.
n.a.
Cascade data center moratorium (Simple Mining industrial park project)
moratorium Moratorium in place, reported 2 October 2026; runs to June 2027; adoption date not stated; single outlet
Simple Mining City of Cascade
The City of Cascade, Iowa, has paused data center development under a moratorium set to end in June 2027 while it writes regulations; neither Cascade nor Peosta had specific data center rules. Cedar Falls-based Simple Mining, which has bought land in the city's industrial park and has an initial agreement with the Cascade Economic Development Corp., cannot move forward until the city adopts regulations. The company's CEO said he welcomes clear restrictions.
n.a.
Clarke County data center moratorium
moratorium Enacted January 2026
n.a. Clarke County
Clarke County, Iowa, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated January 2026. Temporary moratorium while permanent rules are developed. The measure runs until a condition is met rather than to a date.
n.a.
Clayton County data center moratorium
moratorium Enacted February 2025
n.a. Clayton County
Clayton County, Iowa, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated February 2025. Clayton County Board of Supervisors approved a temporary moratorium on rezoning requests and conditional use permits for digital asset mining/data centers in February 2025. The moratorium was originally set to expire 31 December 2025, but supervisors extended it to 31 December 2026 to allow more time for research and policy development. County officials and the Planning and Zoning Board are studying potential concerns including noise, visual impact, water use, and effects on surrounding properties.
n.a.
Clinton data center moratorium (declined; QTS 1,100-acre site under contract)
other Moratorium declined 9 June 2026 (split vote); QTS land contract reported 2 September 2026
QTS (land under contract) City of Clinton
The Clinton City Council, in a split vote at its 9 June 2026 meeting, declined to implement a moratorium on data center development, with members saying it could signal the city was closed for business. Residents packed the meeting with concerns about a potential QTS site. The city has no data center zoning rules and is drafting an ordinance on setbacks, water, grid needs and noise. The mayor expects a QTS proposal after the ordinance is in place.
n.a.
Dickinson County six-month moratorium on data centers, bitcoin mining, solar and battery storage
moratorium Approved 4-1 on 12 May 2026; six months
n.a. Dickinson County Board of Supervisors
The Dickinson County Board of Supervisors voted 4-1 on Tuesday 12 May 2026, after a public hearing, to approve a six-month moratorium on zoning permits for data centers, bitcoin mining, solar and battery storage installations. Chairman Bill Leupold cast the only no vote. Supervisors said the pause can be extended and gives the county time to write specific ordinances.
n.a.
Dubuque six-month moratorium on hyperscale data centers
moratorium Approved; reported by KCRG 21 September 2026; six months
n.a. Dubuque City Council
The Dubuque City Council approved a temporary six-month moratorium on hyperscale data centers, placing an immediate hold on large facility applications and utility requests while the city drafts permanent rules, after delaying action at an earlier meeting to refine the ordinance. The city attorney said the pause preserves the status quo while the city evaluates whether and under what conditions land proposed for hyperscale data centers could be annexed or connected to public utilities. Staff will complete water, energy and infrastructure studies during the six months, and the council can extend it.
n.a.
EU-3 large-scale DC rezoning (~3,500 acres)
moratorium Jul 2026
n.a. Linn County, IA
Board of Supervisors voted 2-1
n.a.
Henry County moratorium on data centers, battery arrays and data mining
moratorium Effective 14 May 2026; runs to 31 December 2026; single outlet
n.a. Henry County Board of Supervisors
The Henry County Board of Supervisors adopted a moratorium halting development of data centers, large battery arrays and data mining sites, effective at noon on Thursday 14 May 2026 and running until 31 December 2026. Supervisor Chad White said the county wants zoning policy in place before any project arrives; the county has not received any offers to build.
n.a.
Ida County data center moratorium
moratorium Enacted June 2026
n.a. Ida County
Ida County, Iowa, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated June 2026. Indefinite moratorium, unanimous. Supervisors want more information before allowing development. The measure runs until a condition is met rather than to a date.
n.a.
Jefferson County data center moratorium
moratorium Enacted August 2026
n.a. Jefferson County
Jefferson County, Iowa, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated August 2026. 12-month moratorium adopted unanimously alongside a new data center ordinance; second and third readings waived so it took effect at once. County attorney recommended 1 year over the 24 months residents asked for, as more likely to survive a legal challenge. The measure runs to 11 August 2027.
n.a.
Johnson County (Iowa) data center moratorium
moratorium Approved 6 November 2025; expires 8 November 2026; extension to 8 August 2027 recommended 5-0 by the Planning and Zoning Commission on 14 September 2026, board vote pending
n.a. Johnson County Board of Supervisors
The Johnson County Board of Supervisors first approved a moratorium on 6 November 2025 that prevents approval of rezoning, subdivision and site plan applications and issuance of building permits related to data centers in unincorporated areas, while staff draft a data center ordinance. It is scheduled to expire 8 November 2026. The Planning and Zoning Commission voted 5-0 on 14 September 2026 to recommend a nine-month extension to 8 August 2027, which supervisors are weighing.
n.a.
LightEdge data center on city-owned land near the Ames airport
delayed Decision delayed to 1 May 2027 by a council vote in August 2026 (reported by KCCI 26 August 2026); Boone letter of intent announced 10 September 2026
LightEdge City of Ames
Des Moines-based LightEdge proposed a 100,000 sq ft data center on city-owned land near the Ames airport. After weeks of review and significant public opposition, the Ames City Council voted to delay a decision until 1 May 2027 and created a study committee on environmental impacts, with meetings from late September through December 2026. LightEdge then signed a letter of intent, announced 10 September 2026, to buy 10 acres in the Boone Business Park instead.
n.a.
Maquoketa South Highway 61 Industrial Park data center talks (ended)
cancelled Discussions ended 18 August 2026
n.a. City of Maquoketa
On 18 August 2026 Maquoketa city leaders and development consultant Gronen ended preliminary discussions on a potential data center in the South Highway 61 Industrial Park. The city said it will review Heavy Industrial District regulations before future proposals, including data centers.
n.a.
Marshall County six-month data center moratorium (unincorporated areas)
moratorium Adopted 23 September 2026; six months, extendable
n.a. Marshall County Board of Supervisors
The Marshall County Board of Supervisors voted 3-0 on Wednesday 23 September 2026 to adopt a resolution imposing a six-month moratorium on applications for data centers, AI computing facilities, data mining facilities and cryptocurrency mining operations. The final text removed the limit on how long the moratorium can be extended, and the Zoning Commission will hold monthly work sessions to draft an ordinance.
n.a.
Mitchell County data center moratorium
moratorium Enacted January 2025
n.a. Mitchell County
Mitchell County, Iowa, enacted a local data center moratorium or ban, recorded in SAVRN's moratorium tracker as dated January 2025. Resolution #1336-25; moratorium on data centers until 31 December 2026. Voted 4-1 (Frein, Marzen, Hartogh, Wherry yes; Hendrickson nay). The measure runs to 31 December 2026.
n.a.
Peosta data center moratorium (extended)
moratorium Original six-month moratorium adopted earlier in 2026; extension approved the week of 21 September 2026 (reported 25 September 2026); runs to 18 June 2027
n.a. Peosta City Council
The Peosta City Council voted unanimously the week of 21 September 2026 to extend the city's six-month data center moratorium by six months, to 18 June 2027. The original moratorium, passed earlier in 2026, was due to end in December; Mayor Russ Pfab said leaders felt that timeframe was not long enough.
n.a.
Salix Google data center (moratorium rejected)
other Moratorium rejected 3-2 on Thursday 20 August 2026
Google (customer) with MidAmerican Energy City of Salix
The Salix City Council voted 3-2 on 22 August 2026 to reject a one-year moratorium on data center development, allowing the Google-linked project to proceed. One council member changed her vote after Google's involvement was disclosed. The land still requires rezoning, and Woodbury County is challenging the annexation in court. KCAU reported the council voted 3-2 against the moratorium on Thursday night, 20 August 2026, after voting 3-2 in July to have attorneys draft it; the vote came a week after a meeting was cancelled over threats. In September 2026 the Salix Guardian Alliance petitioned a court for a declaratory judgment that the council had already approved a one-year moratorium in July 2026.
n.a.
Winneshiek County 12-month data center moratorium (unincorporated areas)
moratorium Approved unanimously 28 September 2026 after a public hearing; 12 months (single outlet for the vote, Decorah Leader; hearing confirmed by the county agenda)
n.a. Winneshiek County Board of Supervisors
On Monday 28 September 2026, after a public hearing on the item, the Winneshiek County Board of Supervisors voted unanimously to approve a 12-month moratorium on data centers. It applies only to rural, unincorporated areas; the county's eight cities may act on their own, and the City of Decorah has approved the first reading of an updated zoning ordinance regulating data centers.
n.a.
Policy context

What governs a data center in Iowa

The policy layer for Iowa lives in three companion references: the Iowa Data Center Moratorium Tracker for every state measure and local moratorium on record, the Water Tracker for the water rules that touch a site, and the Grid Operator Watchlist for the large-load rules of the RTO or utility that decides whether it can energize.

On the map

Data centers in Iowa

The US Data Center Map identifies 85 facilities run by 31 operators in Iowa, each one placed from primary sources and listed by city and by operator, with this atlas record beside it.

Sources

Sources for Iowa

Every source cited on this page, once each. The full atlas source register is at Capital Atlas sources.

The SAVRN reference set

Seven references, one system

Capital, delay, policy, water, grid, permits and scarcity are one system seen from seven sides. Each reference is primary-sourced, refreshed on a schedule, and links into the others, so a project can be followed from the money committed to the docket that stopped it.